High CourtsSingle Bench(2026) 08 TEL CK 5319

Batta Jangaiah vs The State Of Telangana & Ors.

Telangana High Court · Decided on 25 August 2026

HON’BLE JUDGES
B. Vijaysen Reddy, J
RESULT
Disposed Of
CASE NUMBER
Writ Petition No. 27926 of 2026

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

5 paragraphs · 194 words

Heard Mr. P. Ramprasad, learned counsel for the petitioner and Mr. K. Laxmaiah, learned standing counsel for respondents No.2 to 4.

2.

Learned counsel for the petitioner submitted that without prior notice and without referring to the provisions of the Greater Hyderabad Municipal Corporation Act, 1955, the respondent authorities have partly demolished the structures of the petitioner in property bearing H.No.3-27/208/E/2/A/1, Sy.No.208/UU/2, Gandipet Mandal, Cyberabad, Ranga Reddy District. The petitioner is the owner of the property by virtue of pattadar passbook bearing No.T05070070006.

3.

Learned standing counsel submitted that encroachment was noticed by the Cyberabad Municipal Corporation officials on the public road and structures were removed. However, learned standing counsel submitted that due process of law will be followed if any action is to be taken against the petitioner.

4.

Recording the above submission, the writ petition is disposed of with a direction to the respondents No.3 and 4 not to interfere with the possession and enjoyment of the petitioner over property bearing H.No.3-27/208/E/2/A/1, Sy.No.208/UU/2, Puppalaguda, Gandipet Mandal, Cyberabad, Ranga Reddy District, without following due process of law.

The miscellaneous applications, pending if any, shall stand closed. There shall be no order as costs.