Judgment
The Indian Statistical Institute Cooperative Group Housing Society Limited (the Applicant), a Society registered under the Delhi Cooperative Societies Act, 1972, made an application on 22 June 2020 for registration of its Group Housing project developed on a lease hold plot obtained by the Applicant Society from DDA admeasuring 3500 sq. mtrs. situated at Plot No.7, Cooperative Group Housing Complex, Dhirpur Phase I, Delhi 110009.
The application and the attached documents were scrutinized and a number of deficiencies were found in the application and accordingly a deficiency letter was issued to the Applicant Society on 17 July 2020. In submitting its reply on 28 July 2020 the Applicant Society enclosed 23 additional documents in response to the deficiencies pointed out by the Authority. The said reply was scrutinized and it was found that a number of deficiencies had not been addressed adequately. In order to provide a further opportunity for rectification of defects as well as for a hearing, a show cause notice was issued to the Applicant Society requiring it to provide additional documentation, if any, in respect of the remaining deficiencies and to appear before the Authority on 8 September 2020.
The Authorized Representative (AR) of the Applicant Society, Shri Ram Avtar Gupta, submitted during the hearing held on 8 September 2020 that a further response to the show cause notice had been submitted by the Applicant Society on 7 September 2020 whereby ten more documents in respect of uncured deficiencies has been furnished. He further stated that the Applicant Society was not able to apply for the registration within the prescribed time on account of lack of awareness and clarity with regard to the applicability of the provisions of the Real Estate (Regulation and Development) Act, 2016 and requested for some more time to file a formal statement of reasons for delay in making the application, and to file more documents in support of its submissions.
During the final hearing held on 13 October 2020, the AR of the Applicant Society submitted that a full response to the various deficiencies had been filed by them and recounted that the work relating to the project had commenced in November 2014 and that the same was completed in June 2018 but prior to completion of the work, the Applicant Society had to made an application for a revised sanction plan in November 2017, which revised sanction plan was approved by DDA on 17 December 2018. He added that subsequently the project was accorded a Completion Certificate by DDA in June 2019. Upon enquiry, the AR further stated that the total project cost of Rs. 42 crore was inclusive of the cost of construction of 21 apartments under EWS category and that the amount of money received from the proceeds of EWS apartments shall be distributed among its sixty members in due course.
Taking into account the totality of the circumstances, we are of the considered view that while the Applicant Society has rectified the defects in the application, it has not been able to provide any cogent reasons to explain the delay of almost three years in making the application for registration of the above stated project and non-conformity to provisions contained in Section 3 and 4 of the Act during the period of delay. In accordance with Section 59 of the Act, if the Promoter does not comply with the provisions, he shall be liable to a penalty which may extend to 10% of the total estimated cost of the Real Estate project as determined by the Authority. Also, there is no provision in the Act or the Rules framed there-under, where the Authority is empowered to condone the delay in making the application for registration of a real estate project.
In view of the above, and looking into the facts submitted by the Applicant Society, we are of the considered view that it is appropriate to impose a penalty of an amount equal to three times the registration fees payable for the project, which total penalty is less than one-tenth of one percent of the total estimated project cost.
We accordingly order that for the delay in making the application for registration of its real estate project, which was ongoing as on the date of entry in to force of the Act (1 May 2017), a penalty of an amount equal to three times the registration fees payable for the project be imposed on the Applicant Society. Let the penalty be deposited by the Applicant Society in accordance with the provisions of the Act and the project be registered subject to usual conditions upon payment of such penalty.