The AR of the Applicant/ Noticee appeared and submitted that Applicant had provided its response to various deficiencies pointed out to the Society.
During the course of the hearing, the AR recounted that the work relating to the project was commenced in November 2014 and the same was completed in June 2018 but prior to the completion of the work, the Applicant Society had made an application for a revised sanction plan in November 2017 which revised sanction plan was approved by DDA on 17 December 2018. Subsequently, the project was accorded a Completion Certificate by DDA in June 2019.
The AR further stated that the total project cost of Rs.42 crore included the cost of construction of 21 apartments under EWS category and that the amount of money recovered from the proceeds of these EWS apartments shall be distributed among the 60 Members in due course.
The AR of the Applicant Society further submitted that the reasons for delay in making an application for registration of the project had been submitted in writing, and that they have nothing further to add.