Judgment
The M/s Delhi Municipal Press Co-operative Group Housing Society Ltd., a society registered under the Delhi Cooperative Societies Act, 1972, made an application on 03 February 2021 for registration of its Group Housing residential project developed on a lease hold plot obtained by the Applicant Society, from DDA admeasuring 4499.88 sq. mtrs of land situated at Plot No.29A, Sector 10, Dwarka, New Delhi 110075.
The application and attached documents were scrutinized and a number of deficiencies were found in the application, and accordingly a deficiency letter was issued to the Applicant Society on 01 March 2021. In submitting its reply on 19 April 2021, the Applicant Society submitted a number of documents. The said reply was scrutinized and it was found that some of the deficiencies had not been addressed adequately, and that in particular the Applicant Society did not furnish a statement of reasons for delay in making application for registration of their ongoing project under provisions of the Real Estate (Regulation and Development) Act, 2016 except to say that as per their understanding the work related to the society was completed in October 2016 and that they applied for registration only when the Registrar of Cooperative Societies, Govt of NCT Delhi had asked for documentation relating to such registration with RERA.
In order to provide a further opportunity for rectification of remaining deficiencies as well as for a hearing on the issues relating to delay in making an application for registration, a Show Cause Notice was issued on 26 August 2021 to the Applicant Society requiring it to provide additional documentation, if any, in respect of the remaining deficiencies and to appear before this Authority on 8 September 2021.
The Applicant Society was represented by Shri Parvinder Chauhan, Ld. Counsel. The Ld. Counsel submitted during the hearing held on 8 September 20221 that he has already filed reply to the deficiencies communicated by the Authority on 01 September 2021. During the course of the hearing, he again submitted that there has been some delay due to not being aware of the provisions of RERA that the project was required to be registered with RERA, only after the Registrar, Co-operative Societies directed for getting the project registered with RERA and accordingly the Society has filed this application for registration of the project.
It is clear from the documents available on record that all construction work in relation to the project had been completed by October 2016 when the Applicant Society applied for a Occupancy Cum Completion Certificate (CC), which CC was issued by MCD on 06 November 2018.
Taking into account the totality of the circumstances, we are of the considered view that while the Applicant Society has rectified the defects in application, it has not been able to provide any cogent reasons to explain the delay of three years and 09 months in making the application for registration of the above stated project and non-conformity to the provisions contained in Section 3 and 4 of the Real Estate (Regulation and Development) Act, 2016 during the period of delay.
In accordance with Section 59 of the said Act, if the Promoter does not comply with the provisions, he shall be liable to pay a penalty which may extend to ten percent of the total estimated cost of the real estate project as determined by the Authority. Also, there is no provision in the Act or the Rules framed there under where the Authority is empowered to condone the delay in making the application for registration of a real estate project.
In view of the above and looking into the facts submitted by the Applicant Society, I am of the considered view that it is appropriate to impose a penalty of four times of registration fees payable for the project, which total penalty is less than one eighth of the one percent of the total estimated cost of the project.
I accordingly order that for the delay in making the application for registration of its real estate project, which was ongoing as on the date of entry into force of the Act (01 May 2017), a penalty of an amount equal to four times of the registration fees payable for the project be imposed on the Applicant Society. Let the penalty be deposited by the Applicant Society in accordance with the provisions of the Act, and the project be registered subject to usual conditions upon payment of such penalty.