Tribunals and CommissionsDivision Bench(2024) 08 RERA CK 2353

Umesh Chandra Joshi vs Delhi Development Authority & Ors.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 22 August 2024

CASE NUMBER
Com/23/05/2023

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

71 paragraphs · 4,905 words
1.

The Complainant has filed this complaint under Section 31 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as RE(RD)Act‖ or ―the Act‖) against the Delhi Development Authority, Delhi alleging, inter alia, that he was allotted flat No. 256 Pocket-6 3rd floor in Nasirpur (Dwarka), Delhi advertised as 3BHK/HIG Flat in the Brochure in DDA Housing Scheme, 2021 against which he made full payment of demanded amount and submitted requisite documents within prescribed time period. However, the flat allotted to the Complainant is a 2BHK MIG category flat in the same project. The allotted flat is in very bad condition and is not habitable without repairs. The physical Possession of said allotted flat has not been handed over to the Complainant despite repeated requests/visits to office of concerned Executive Engineer. The Complainant has also alleged violation of Section 3 of the Act, as the Respondents DDA advertised and sold flats under the Scheme without registering the project with Real Estate Regularity Authority, NCT of Delhi under the RE(RD)Act.

2.

The matter was heard on 07.08.2023, 03.10.2023, 14.12.2023, 06.03.2024 and 25.04.2024. Respondents filed their reply on 08.01.2024 stating that they will file detailed reply if circumstances so warrants but did not consider it necessary to file any additional detailed reply therefore the reply dated 08.01.2024 is taken as final reply to the complaint. The Complainant has filed rejoinder to the said reply on 05.02.2024

3.

The matter was finally heard on 30.05.2024.

4.

Arguments of both the parties have been heard and the documents submitted by both the parties have been perused.

BRIEF FACTS OF THE CASE:

5.

The Complainant has alleged that the Respondents, Delhi Development Authority, an Authority constituted under Section 3(1) of the Delhi Development Authority Act, 1957 for the development of land and property in NCT of Delhi in a planned and transparent manner, launched DDA Housing Scheme 2021 (hereinafter referred to as the Scheme) for the disposal of newly built-up houses. Copy of Advertisement Brochure of the Scheme has been enclosed along with the complaint (as Annexure A). Through the said Scheme, the Respondents invited application for allotment of about 1350 flats containing 254 HIG flats, 757 MIG flats, 52 LIG flats and 291 EWS flats.

6.

As per the Advertisement Brochure, DDA, advertised 252 flats of 3 BHK type and 2 flats of 2 BHK type under HIG Category at various localities besides MIG, LIG and EWS category flats. At serial number 5 of the Advertisement Brochure, one flat at Nasirpur (Dwarka), having Locality Code number 15, was listed under 3 BHK/HIG category.

7.

The Complainant, being eligible under the said Scheme, applied for allotment of a flat and mentioned his preferences as HIG-Nasirpur (Dwarka) and Pashchim Vihar Locality Code number 15 as first preference. MIG-Rohini-Sector 23 Locality Code number 34 as second preference and MIG-Dwarka, Sector 19, Sector-1, Sector-12 and Sector-3 Locality Code number 35 as his third preference. (Annexure C)

8.

Vide Demand -cum-Allotment letter dated 30.03.2021(Annexure F), DDA allotted the HIG flat bearing number 256 in Pocket-6, 3rd floor, Nasirpur (Dwarka) to the Complainant. The Complainant paid the demanded cost of flat Rs. 67, 70,722/- by 29.06.2021 and uploaded requisite documents on 30.06.2021. Assistant Director (Housing, DDA) issued a letter on 27.10.2021(Annexure G) to the Executive Engineer (Housing Division) informing him that flat number 256 in Pocket-6, 3rd Floor Nasirpur (Dwarka), West Zone, Delhi has been allotted to Complainant under DDA Housing Scheme 2021 and advised the Executive Engineer to hand over possession of said flat to the allottee within 90 days. The Complainant deposited this possession slip with EE, DPD-2 on 3.11.2021 and he was allowed physical inspection of the flat on 17.11. 2021. After inspection the Complainant noticed the defects in the flat and communicated the same, and also that it is 2BHK Flat while he was allotted a 3BHK Flat/HIG Category to the EE, DPD-2 Dwarka vide his letter dated 17.11.2021(Annexure J).

9.

The EE floated a tender for repair of the house on 23.06.2022 but repair work is not completed till date. Possession of the said flat has not been handed over to the Complainant till date.

10.

The Complainant has therefore prayed that DDA be directed to;

i.

To repair/maintain the house in terms of clause 9 of the brochure to make it habitable by carrying out both Civil and electrical work in 3 BHK/HIG flat norms.

ii.

To provide one Bedroom and other amenities advertised in prospectus for a 3 BHK/HIG flat in terms of Section 14(3) of RERA Act, 2016 as the present dwelling unit has only 2 BHK which is contrary to the prospectus and advertisement of the DDA for the scheme, 2021, the DDA is otherwise also obliged to provide the facilities in terms of Section 35(2) of DDA Act, 1957 and bear the expenses in terms of Section 35(3) of the said Act or reimburse the expenses so calculated to the Complainant.

iii.

To pay interest to the Complainant on cost of the dwelling unit for delay in handing over the possession of the flat in terms of proviso to Section 18(1) of RERA Act, 2016 read with clause 10(ii) of brochure @10%.

iv.

To pay compensation to the Complainant under Section 12 of the Act for misleading Advertisement Brochure wherein the subject property was mentioned as 3BHK/HIG flat while in fact it is a 2BHK/MIG Flat.

v.

To pay compensations and penalties on various grounds as detailed in his complaint.

vi.

To pay penalty for contravention of Section 3 and 4 of the Act in terms of Section 59 and 60 respectively, of the Act.

REPLY OF THE RESPONDENTS/DDA

11.

The Respondents, in their reply have stated that DDA floated the ―DDA Housing Scheme 2021‖ and in the draw of allotment of flats held on 10.03.2021 the Complainant was declared successful for allotment of HIG flat number 256, 3rd Floor, Pocket-6, Nasirpur (Dwarka) having plinth area of 88.96 Sq. mtrs. and carpet area of 70 sq. mtrs. on cash down basis.

12.

Respondents further stated that clause 17(iv) of the Advertisement Brochure specifically mentioned that, ―…..the property is being offered on ―as is where is basis‖ and the DDA will not entertain any request for additions or alterations or any complaints whatsoever regarding property circumstances as defined in Regulation 19 of the DDA (Management and Disposal of Housing state) Regulation 1968. DDA shall also not entertain any complaint about cost of flat, its design, quality of material used, workmanship or any other defects‖.

13.

Respondents have stated that the Complainant had chance to inspect the flat before applying but he chose not to inspect the flat before applying. He raised many objections related to flat only after completing all the formalities, did not take possession and himself delayed the possession by refusing to take possession. As such, the delay in possession is solely attributed to the Complainant and not to the Respondents/DDA. However, objections raised by the Complainant have been put forward before the Senior Officers and in June-2022 DDA decided to float a tender for repair of the flats at the estimated cost of Rs. 1,18,237/-. The first tender was rejected because only one tender was received. The work has been awarded on 26.10.2022 as per due process. The Complainant is aware of the development and has acknowledged the same vide his e-mail dated 27.10.2022.

14.

The Respondents have further stated that allotted flat is a 2 BHK flat constructed at third floor of 4 storied building in Pocket-6. The 4 storied building has only 2 BHK flats. The complete area of said allotted 2 BHK category flat is equal to 2BHK/HIG category flats. This flat was to be advertised as 2BHK/HIG flat as has been done in the case of flat at serial number 7 of the Advertisement Brochure. However, due to inadvertent typographical error the said flat has been advertised in the category of 3 BHK/HIG flat at serial no. 5 of the Advertisement Brochure. This error was neither deliberate nor intentional.

15.

Respondents have further stated that Engineering Department would complete the repair works and hand over the physical possession of the subject flat to the Complainant after Housing Department takes appropriate corrective action by mentioning the BHK category of the flat.

16.

The reply filed by the Respondents, is conspicuously silent about the registration of the subject project under the RE (RD) Act, 2016.

Analysis and Conclusion

Jurisdiction of the Authority and violation of Section 3 of the RE(RD) Act, 2016:

17.

The RE (RD) Act was enacted in 2016 and Section 3 of the Act was notified with effect from 01.05.2017. The mandate of Section 3 is that all the real estate projects meant for sale are required to be registered with the Authority. It further provided that all the ―ongoing project‖ shall also be registered within three months of the notification of the provision. Thus, the jurisdiction of the Authority extends to all the real estate projects which satisfy the criteria for registration as prescribed under the Act.

Section 3 of the Act reads as under:

“Prior registration of real estate project with Real Estate Regulatory Authority.—(1) No promoter shall advertise, market, book, sell or offer for sale, or invite persons to purchase in any manner any plot, apartment or building, as the case may be, in any real estate project or part of it, in any planning area, without registering the real estate project with the Real Estate Regulatory Authority established under this Act: Provided that projects that are ongoing on the date of commencement of this Act and for which the completion certificate has not been issued, the promoter shall make an application to the Authority for registration of the said project within a period of three months from the date of commencement of this Act: Provided further that if the Authority thinks necessary, in the interest of allottees, for projects which are developed beyond the planning area but with the requisite permission of the local authority, it may, by order, direct the promoter of such project to register with the Authority, and the provisions of this Act or the rules and regulations made thereunder, shall apply to such projects from that stage of registration. (2) Notwithstanding anything contained in sub-section (1), no registration of the real estate project shall be required— (a) where the area of land proposed to be developed does not exceed five hundred square meters or the number of apartments proposed to be developed does not exceed eight inclusive of all phases: Provided that, if the appropriate Government considers it necessary, it may, reduce the threshold below five hundred square meters or eight apartments, as the case may be, inclusive of all phases, for exemption from registration under this Act; (b) where the promoter has received completion certificate for a real estate project prior to commencement of this Act; (c) for the purpose of renovation or repair or re-development which does not involve marketing, advertising selling or new allotment of any apartment, plot or building, as the case may be, under the real estate project.‖

18.

As per the mandate of Section 3 a promoter cannot advertise, market, book, sell or offer for sale, or invite persons to purchase in any manner any plot, apartment or building in any planning area without registering the project with the Real Estate Regulatory Authority. The Act does not put restrictions on construction of apartments/flats/houses but a promoter cannot advertise or sell them unless the real estate project is registered with the Authority. This is admitted fact that the Respondents/DDA have constructed, advertised and offered for sale flats at different locations, to general public through the Advertisement Brochure under the ―DDA Housing Scheme,2021‖ much after 01.05.2017.

19.

The Respondents/DDA fall in the definition of promoter as categorized and defined in Section 2(zk) of the Act. Clause (iii) of Section 2(zk) of the Act says that a promoter means, ― any development authority or any other public body in respect of allottees of (a) building or apartments, as the case may be, constructed by such authority or body on land owned by them or placed at their disposal by the Government; or (b) plots owned by such authority or body or placed at their disposal by the Government, for the purpose of selling all or some of the apartments or plots;…..‖

20.

Thus, the real estate project ―DDA Housing Scheme 2021‖ promoted by the Respondents/DDA as promoter, were required to be registered under the RE (RD) Act, 2016 being a registrable project. Therefore, the Respondents being promoter were subject to all the provisions of the Act. Hence, this Authority has the requisite jurisdiction to entertain, adjudicate and dispose of the present complaint in accordance with the provisions of the Act.

21.

The Respondents/DDA have admitted that the scheme was launched, advertised and units were auctioned and sold. The advertisement Brochure in its Annexure-A has mentioned under Note-2 that, ―The Registration of current housing project is under process with RERA‖ indicating thereby that Respondents/DDA were well aware that project was registerable as per Section 3 of the Act. The violation of Section 3 of the Act is thus apparent from the records, which prohibit advertisement, sale and even offer for sale without registration of the project. The Respondents/DDA have not given any explanation in the reply why the advertisement, auction and sale were undertaken without registering the project though there was specific allegation of violation of Section 3 of the Act. Thus, we hold that Respondents/DDA in contravention of Section 3 of the Act have advertised, auctioned and sold flats under its scheme ―DDA Housing Scheme,2021‖ and therefore liable for penalty under Section 59 of the Act.

Misleading advertisement in Advertisement Brochure:

22.

Documents filed by the parties have been perused. It is noted that the DDA, in its Advertisement Brochure, have given typical unit plan layout of 3 BHK/HIG flats at Pocket 9B Jasola and 3BHK/HIG flat at Vasant Kunj. Each lay out contained 3 Bedrooms. Typical unit plan of 2 BHK/MIG flat at Vasant Kunj, Sector 19B, Dwarka and Sector 16B, Dwarka were also furnished. Layout plan for flat in Nasirpur (Dwarka), advertised to be 3 BHK/HIG flat, was not given in the said Brochure. Layout plans for 2 BHK/HIG flats at Vasant Kunj were also not given in the Advertisement Brochure.

23.

Perusal of the Advertisement Brochure reveals that the subject flat is having plinth area of 88.96 sq. mtrs. It is further revealed from Serial Number 7 and 8 of the Advertisement Brochure of DDA that flats having plinth area of 88.94 to 101.69 and 87.98 to 108.98 sq.mtrs in the locality Code 21 and 22 in Vasant Kunj have been categorized as 2 BHK/HIG flats in the Advertisement Brochure. The Respondents/DDA have clarified that the flat allotted to the Complainant is a 2BHK flat and not a 3BHK flat. Therefore, in the Advertisement Brochure it should have been categorized under the category of 2BHK/HIG category as has been done in the case of flats at serial number 7 and 8. Advertising the subject flat in the category of 3 BHK/HIG is a mistake. Respondents have clarified that this is inadvertent mistake. The Complainant has been allotted a HIG flat. The cost of construction is based on plinth area of the flat and relates to HIG category.

24.

Further, it was submitted that the clause 20(i) of the Advertisement Brochure of the Scheme clearly states that ―the Applicants are advised to visit the site and inspect the flat and satisfy himself/herself with regard to location, size and cost before applying for allotment‖. The clause 17(iv) clearly stated that ―the property is being offered on as is where basis is‖ and the DDA will not entertain any request for additions or alterations or any complaints whatsoever regarding property circumstances. DDA shall also not entertain complaint about cost of the flat its design, quality of material used, workmanship or any other defects. These submissions, however, cut no ice with us. The Respondents/DDA could not have put any conditions in the advertisement brochure which are not in consonance with the provisions of RE(RD) Act. The conditions that no complaint against the workmanship and other defects will be entertained and property will be sold on ―as is where basis‖ are against the spirit of the RE(RD)Act which has an avowed object of protecting the rights of homebuyers. The advisory in the brochure that Applicants can visit the site and flat can not absolve the Respondents/DDA of their responsibility to give the unit/flat as per the specification and in habitable condition..

25.

The Respondents had no answer to the submissions of the Complainant that he had visited the site as well as locality, in terms of condition in clause 20 (i) and 3(vii) of the scheme and then finalized the priority, as per details in the Brochure. He also inspected the sample flat as mandated in clause 20(iii) of the Brochure. He submitted that details of flat were not shared with the Demand Letter. He submitted that the condition to accept flat on ―as is where is basis‖ is unfair, unilateral and void. He referred to the judgments in Pioneer Urban Land and Infrastructure Ltd. vs Govindan Raghvan and IREO Grace Realtech Pvt.Ltd vs Abhishek Khanna wherein it was held that unilateral, and unfair clauses of contracts amount to unfair trade practice and void.

26.

The Complainant has, however sought compensation under Section 12 of the Act on account of misleading advertisement and consequent loss he suffered.

27.

Section 12 of the Act reads as under:

“Obligations of promoter regarding veracity of the advertisement

or prospectus.—Where any person makes an advance or a deposit on the basis of the information contained in the notice, advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:

Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.‖

28.

As is evident from the plain language of Section 12 if an allottee sustains any loss or damage by reason of any incorrect or false statement in the advertisement or prospectus etc. he can claim compensation and if he intends to withdraw from the project, he shall be entitled for the refund of his investment along with interest. The Complainant is seeking compensation. As per Section 71 of the RE(RD), Act compensation under Section 12, 14, 18 and 19 are to be adjudged by the Adjudicating Officer appointed under the Act, after holding an inquiry. It has been held in Newtech Promoters and Developers Pvt.Ltd vs State of U.P. that when it comes to a question of seeking the relief of adjudging compensation and interest thereon under Sections 12, 14, 18 and 19 the Adjudicating Officer exclusively has the power to determine. Thus, all matters pertaining to compensation under the Act are within the domain and jurisdiction of Adjudicating Officer and not the Authority. Therefore, we hold that since the Complainant is not seeking refund of his investment under Section 12 but only compensation, he has to apply to the Adjudicating Officer in Form N to seek this relief.

Delay in handing over possession and Liability of Respondents to pay interest under Section 18 of the Act:

29.

The Complainant submitted that he deposited all the requisite documents and cost of the flat as per the demand letter and the advertisement brochure, within the prescribed time but the Respondents/DDA till date have not handed over the physical possession of the flat to him. He has prayed for directions to the Respondents/DDA to handover the possession of the flat and to pay interest on the cost of flat for delay in handing over the possession in terms of the Proviso to Section 18(1) of the Act.

30.

The Respondents/DDA, on the other hand, have submitted that the Complainant himself has delayed the possession by refusing it. It is submitted that tender for repair was floated for repair of the flat and the repair work was started on 26.10.2022 in view of urgency. This submission of the Respondents that the Complainant has delayed possession is as hollow as it is far from truth which is evident from the documents on the record.

31.

Section 18 reads as under:

“Return of amount and compensation.—(1) If the promoter fails to complete or is unable to give possession of an apartment, plot or building,—

(a)

in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or

(b)

due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,

he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act:

Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.

(2)

The promoter shall compensate the allottees in case of any loss caused to him due to defective title of the land, on which the project is being developed or has been developed, in the manner as provided under this Act, and the claim for compensation under this sub-section shall not be barred by limitation provided under any law for the time being in force.

(3)

If the promoter fails to discharge any other obligations imposed on him under this Act or the rules or regulations made thereunder or in accordance with the terms and conditions of the agreement for sale, he shall be liable to pay such compensation to the allottees, in the manner as provided under this Act.‖

32.

Section 11(4) (a) of the Act, inter alia, states that the promoter shall be responsible for all the obligations, responsibilities and functions under the provisions of the Act. The Act mandates every promoter to give a timeline for completion of the project and to handover possession after obtaining the Occupancy and Completion certificate. In the present case the advertisement brochure issued by the Respondents/DDA mention how and when possession would be given to successful allottees. Clause 17(i) of the brochure says that allottee shall be entitled to take possession only after completion of all the formalities, payment of all dues and execution of all the documents as mentioned in the Demand-cum-Allotment Letter. A digitally signed Possession Letter will be issued online only. Clause 17(ii) says that after issuance of Possession Letter, allottee may reserve a date for physical possession through Online mode. As per Clause 10(i) Demand-cum-Allotment Letter will be issued three months prior to likely date of handing over of possession of flat after all clearances.

33.

The Complainant has submitted that the Allotment-cum-Demand Letter was issued on 30.03.2021 and he made payment as per this letter on 29.06.2021 and uploaded all the requisite documents on 30.06.2021. The possession letter was issued on 27.10.2021. However, he could not find link for fixing date for taking physical possession as per the mandate of Clause 17(ii) of the brochure. After enquiry from DDA the possession slip was deposited with E.E., DPD-2 on 03.11.2021. He was allowed inspection of the flat on 17.11.2021. On the same day he wrote a letter (Annexure J) informing the EE, DPD-2 about the condition of the flat and that it was a 2BHK/MIG flat though he was allotted a 3BHK/HIG flat. The Complainant was informed that tender for removal of deficiencies was floated on 23.06.2022. He wrote letter to Director (Housing) and Member (Engineering) on 22.09.2022 and 26.09.2022 respectively (Annexure I). On receipt of grievance letter dated 26.09.2022 a meeting was convened and held by EM, DDA on 28/10/2022. The Minutes of this meeting are placed on record by the Respondents/DDA (Annexure -2) which are as under:

1.

“Discrepancy with regard to the category/details of subject flat as per the housing scheme documents/actual site conditions, along with financial implications, if any, may be corrected/amended for which allottee may furnish fresh voluntary application to Housing Department.

2.

Engineering Department needs an authenticated possession letter from Housing Department to proceed further in respect of its obligations towards the allottee.

3.

The ongoing repair works of the subject flat shall be kept in abeyance till authenticated possession letter of the subject flat is issued by the Housing Department of DDA and the copy of the same is made available either online/offline to the JE/AE in the office EE/DPD-2.

4.

The subject flat shall be made habitable after requisite repair for possession at the earliest after receipt of fresh possession letter of the flat from the Housing Department.”

34.

From the Minutes of this meeting, it can be deciphered that the flat in question was not habitable. It has been recorded in the Minutes that, “The subject flat shall be made habitable after requisite repairs for possession at the earliest possible after receipt of fresh possession letter of the flat from Housing Department”. The EE/DPD-2 was to take action on this resolution of the meeting. The Housing Department was to correct/amend discrepancy with regard to category of flat and send authenticated possession letter to Engineering Department. In the meantime, even the ongoing repair work was also kept in abeyance.

35.

During the course of proceedings of the case the Complainant has placed on record a letter dated 31.08.2023 sent by Dy. Director (SFS) H to EE, DPD-2 regarding release of possession letter for the flat. The Respondents/DDA have not shown any communication to the Complainant regarding delivery of possession, subsequent thereto. The Complainant has still not received the possession of his flat.

36.

The Complainant has right to seek possession of a habitable dwelling for which he has paid huge amount after availing loan from Bank. A dwelling house which he should have received in 2021 itself is still far from his reach. The Respondents/DDA have miserably failed to show any default of the Complainant in taking possession of the flat in question. They are oblivious to the suffering of the allottee who has arranged finance from his savings and taken Bank loan to purchase a house in Delhi. The Respondents are under an obligation to work in a transparent manner and comply with the provisions of the Act.

37.

In the above facts and circumstances, we hold that the Respondents have failed to fulfill its obligations as a promoter under the Act and failed to deliver the possession of the flat to the Complainant in terms of the Advertisement Brochure within the prescribed time. As per clause 17(ii) of the brochure an allottee has to take possession within three months from the date of issue of possession letter. This conversely would mean that the Respondents/DDA were also under an obligation to hand over possession within three months from the date of possession letter. The Possession Letter (Annexure G) was issued on 27.10.2021 therefore the Respondents/DDA were to deliver the possession latest by 27.01.2022. We accordingly hold the Respondents/DDA liable to pay interest for every month of delay in possession with effect from 27.01.2022 till the date of possession to the Complainant as per the prescribed rate of interest.

38.

In view of the above, we issue following directions:

(1)

The Respondents are directed to handover physical possession of the flat in habitable condition, to the Complainant within 45 days from the date of this order and also pay interest on the amount deposited for every month of delay in delivery of possession, at the rate of 10.75% (i.e MCLAR plus two percent) as per rule 15 of the NCT of Delhi Real Estate (Regulation and Development) (General) Rules, 2016 from 27.01.2022 till the date of possession under the Proviso to Section 18(1) of the RE(RD),Act.

(2)

For violation of Section 3 of the RE(RD)Act, by way of advertisement, auction and sale of flats/units in the project ―DDA Housing Scheme, 2021‖ without registering the project, we impose a penalty of Rs. 50,00,000/- (Rs. Fifty Lakh only) on the Respondents/DDA, under Section 59(1) of RE(RD) Act and direct the Respondents to deposit the amount in Bharat Kosh within 45 days of the order.

(3)

The Respondents/DDA shall register the project ―DDA Housing Scheme,2021‖ with the Authority within 45 days from date of this order failing which proceeding under Section 59(2) of the RE(RD) Act will be initiated.

39.

For the compensation under Section 12 of the RE(RD) Act we reserve the right of the Complainant to approach the Adjudicating Officer, RERA, NCT of Delhi as per law.

40.

Ordered accordingly.