Tribunals and CommissionsFull Bench(2022) 11 NGT CK 0018

Siddhartha Attri vs Uttar Pradesh Pollution Control Board

National Green Tribunal · Decided on 11 November 2022

HON’BLE JUDGES
Adarsh Kumar Goel, CP · Sudhir Agarwal, JM · Arun Kumar Tyagi, JM · Dr. Afroz Ahmad, EM
RESULT
Disposed Of
CASE NUMBER
Execution Application No. 35 Of 2022 In Original Application No. 374 Of 2021

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

7 paragraphs · 212 words
1.

This application seeks execution of order of this Tribunal dated 04.01.2022 in O.A No. 374/2021 for compliance of norms relating to installing requisite Chimneys on Diesel Generators, resulting in violation of provisions of the Air (Prevention and Control of Pollution) Act, 1981. The Tribunal directed the State PCB to take remedial action. Operative part of the order is reproduced below:-

2.

In view of above, we direct the State PCB to take further remedial action in terms of stack height, control of emissions and noise and operation as per GRAP and conclude the same as far as possible within one month from today.”

3.

According to the applicant, no action has been taken on the ground and the violations are continuing.

4.

In view of above, let the State PCB look into the matter and take remedial action as already directed. We also direct that a copy of the order dated 04.01.2022 in O.A No. 374/2021 be forwarded to the District Judge, Ghaziabad for being entrusted to the jurisdictional Civil Court for execution under Section 25 of the NGT Act, 2010.

The Application is disposed of.

A copy of this order be forwarded to the State PCB, and the Project Proponent-M/s KDP Infra Pvt. Ltd. Ghaziabad by email for compliance.