This is a complaint filed in Form ‘M’ on 9 December 2019 by Shri Sunny Sapen (the Complainant) against M/s. Revanta Multistate Cooperative Group Housing Society Ltd. (the Respondent) seeking a refund of Rs.13,27,500/- (Rupees thirteen lakh twenty seven thousand and five hundred only) paid by him to the Respondent Society towards booking and other costs relating to a 3 BHK flat (admeasuring 1475 sq. ft.) in the Smart Residency project, along with applicable interest as per RERA Rules.
The brief facts of the case are that in May 2015 the Complainant booked a 3 BHK apartment with a built up area of 1475 sq. ft. in a project called ‘Smart Residency’ situated in Nirmal Dham (near Chhawla village) location of L zone under the Delhi Masters Plan, 2021, developed by the Respondent Society M/s. Revanta Multistate Cooperative Group Housing Society Ltd.; that the total cost of the apartment as per Plan 2 selected by the Complainant was mentioned as Rs.48,46,250/- including a payment towards land cost amounting to Rs.19,91,250/-; that the Complainant paid a total amount of Rs.13,27,500/-by way of three cheques dated 30 May 2015, 1 June 2015 and 10 July 2015; that at the time of booking the apartment in May 2015 he was assured that the construction work relating to the project would start within the next six months i.e. by December 2015; that there was no progress in commencement of work for the next two years, nor was there any positive response from the Respondent Society to the repeated calls and emails; that the Complainant accordingly demanded a refund of his deposit by surrendering his membership in May 2017, to which demand again there was no response despite repeated follow-ups; that in February 2019 the Respondent Society circulated minutes of its meeting held on 17 February 2017 and asking the members to make a choice among three options namely, reduction in the size of the dwelling unit; or payment of additional land-cost of Rs.400 per sq. ft., or giving a written consent authorizing the society to dispose off the land and to distribute the money received from the sale of land.
The Complainant further submitted that the communications from the Society including the minutes of the meeting did not specifically mention the exact location of the proposed project and upon inquiry it was communicated informally that the project may be located in Ujwa village (which is 13 kilometers away from Chhawla village); and that the Respondent Society appeared to have taken a number of decisions relating to purchase of land etc. that were not in the interest of members who had opted for Plan 2 and consequently more than three hundred members had already filed for withdrawal from the Society, and that owing to a number of incorrect and false informations and uncertainty about the future of the project, the Complainant had filed the present complaint for refund of his entire amount along with interest.
After hearing the Authorized Representative (AR) of the Complainant on 9 January 2020, a notice was issued to the Respondent Society returnable on 4 February 2020 on which day the AR for the Respondent appeared and requested for a short adjournment of one week to file a detailed reply. However, a reply was not filed by the next date of hearing held on 11 February 2020 when another request for adjournment for two weeks was made. On the next date of hearing held on 4 March 2020, the Respondent Society yet again requested for another adjournment on the plea that the President and the Secretary of the Respondent Society had been arrested by the Economic Offences Wing; that they had been released on bail just the previous day; and that he (the AR) needed some time to seek instructions regarding filing of the reply. The request was allowed and the case was adjourned to 19 March 2020, but the same could not be heard for the next several months owing to disruptions caused by Covid-19 pandemic.
The case was next heard after a gap of several months on 4 August 2020 via video conference when the Counsel for the Respondent Society appeared and requested for some time to file a reply which could not be done in the interim, owing to disruptions caused by Covid-19 pandemic. One last opportunity was given to the Respondent Society to file its reply within two weeks and liberty was given to the Complainant to file a rejoinder, if he so wishes. The Respondent Society filed its reply to the complaint on 15 September 2020 and a rejoinder was filed by the Complainant, with a copy to the Respondent Society, on 24 September 2020. Arguments of both sides were heard on 5 November 2020 and the case was reserved for orders.
In its response filed on 15 September 2020 via email, the Respondent Society raised some preliminary submissions namely, that the complaint was not filed in proper format; that the complaint did not seek any interim relief; that in the absence of a specific prayer seeking relief the complaint was liable to be dismissed; and that the lines spacing and the font size is not as per the standard legal procedure. On the merits of the case, the Respondent Society submitted that it had not violated any of the provisions of the Real Estate (Regulation and Development) Act, 2016; that for this reason the complaint is not maintainable before this Authority; that the complaint in form M for refund of the amount, compensation or interest is not maintainable before this Authority as per the provisions of Rule 33 of the NCT of Delhi RERA (General) Rules 2016; that the Complainant has not provided an exact date when the cause of action rose; that the Respondent is a society registered on 2 June 2014 by the Department of Agriculture & Cooperation, Ministry of Agriculture, Government of India; that the Respondent Society was under mandatory obligation to procure land as per the conditions stipulated in the registration certificate (a copy of which registration certificate was also submitted); that the Complainant has tried to mislead this Authority by not providing full facts including the application made by the Complainant for membership of the society in the prescribed forms and the terms and conditions mentioned in such application form; that the payments made by the Complainant were towards land cost and not for the flat or apartment; that the land pooling policy is under active consideration of DDA; that during the course of hearing on 4 March 2020, the Respondent Society had offered to settle the matters amicably but the situation had changed subsequently with the accounts of the Society having been frozen; and that the Respondent Society ‘reserves the right’ to make additional reply once they are allowed to operate the bank accounts. Further, the Respondent Society sought the dismissal of the complaint with exemplary cost.
In the rejoinder filed by the Complainant on 24 September 2020, the Complainant submitted his rebuttals to the averments made by the Respondent Society in its reply and submitted that his complaint filed in form M along with prescribed fee of Rs.1000/- was accepted by the Authority for adjudication and that no issues were pointed out relating to the format or standards; that a relief in terms of a ‘refund’ was sought in the prescribed column of Form M as also in the text relating to the fact description; that the Complainant has demanded a refund from the Respondent Society repeatedly and initially the Respondent denied the refund on the plea that such a request could be made only after completion of two years and subsequently the Respondent Society stated that the request of the Complainant for refund had been placed at serial no. 82 in the waiting list of members seeking such refunds; that the Respondent Society did not offer any amicable settlement towards refund of the Complainant’s money despite repeated phone calls, emails and physical meetings; that it becomes clear from the Respondent’s actions that it does not intend to return the Complainant’s money nor is it interested in any amicable settlement; that more than five years have elapsed since the payments were made to the Respondent Society from the hard earned money of the Complainant; and that in view of the above, the Complainant seeks a full refund of the amounts paid along with fifteen percent interest from the date of payment made to the Respondent.
During the last hearing held on 5 November 2020, arguments of both sides were heard. The Complainant in person contended that he had already placed all facts of the case before the Authority; that it was a open and shut case as the Respondent Society had admitted the receipt of his deposits and had further admitted that the refund was due by stating that the Respondent Society wishes to settle the matter amicably with the Complainant. He further contended that the provisions of the Real Estate (Regulation and Development) Act, 2016 were applicable to the operations of the Respondent Society and that the Respondent Society was in violation of such provisions.
The Counsel for the Respondent Society contended that the complaint in its present format is not maintainable under the provisions of the Real Estate (Regulation and Development) Act, 2016 read with Rule 33 and 34 of the National Capital Territory of Delhi RERA (General) Rules, 2016.
The Counsel for the Respondent Society further contended that the refund and interest sought in the complaint filed in form M is not maintainable before this Authority. He further contended that the Complainant had given his consent and expression of interest for participation in land pooling policy of DDA; and claimed that these documents had already been placed on record.
The Counsel for the Respondent Society further contended that in adjudication of this case, the NCT of Delhi RERA Rules, 2016 are applicable and not the rules pertaining to RERA of other States where he referred to another case with regard to registration of real estate agents.
The Counsel for the Respondent Society further contended that the Complainant had paid only a partial cost of the land and membership fee of the society and that the Complainant had not paid any amount towards the construction of the flat; and that the present complaint lies within the jurisdiction of Registrar of Societies under the Multi State CGHS Act, 2002 and not maintainable before this Authority.
M/s. Revanta Multistate Cooperative Group Housing Society Ltd. is a society registered under Section 7 of the Multi State Cooperative Societies Act, 2002 and it has been granted a registration certificate No. MSCS/CR/1049/2014 by a Joint Secretary in the Department of Agriculture & Cooperation, Ministry of Agriculture, Government of India acting in his capacity as the Central Registrar of Cooperative Societies under the Multi State Cooperative Societies Act, 2002. The registration is valid for the NCT of Delhi and the state of Haryana subject to the terms and conditions laid down in the MSCS Act, 2002.
The Respondent Society appears to have floated a number of projects in different areas of NCT of Delhi including the project under the name ‘Smart Residency’ in which the Complainant Shri Sunny Sapen has booked a flat. The Respondent Society has prepared a common Membership Application Form for all its members. While the membership application form duly filled in by the Complainant has not been placed on record by either side, it has been brought to notice that such application forms bears the stamp and signature on behalf of the Respondent Company and provides details of the units booked by the members along with other details such as the payment schedule and annual operation charges etc. The application form used in such cases in recent times includes a “Declaration cum Expression of Interest” containing 27 clauses, clause 1 of which reads as under:-
“That this dwelling unit option scheme shall be applicable up on all necessary approvals sanctions by Real Estate Regulatory Authority established under sub-section 1 of Section 20 of the Real Estate (Regulation and Development) Act, 2016”.
Since the application form and the ‘Declaration cum Expression of Interest’ above referred are part of the documents prepared and printed by the Respondent Society and the application form duly filled in by the members bears the stamp and signature on behalf of the Respondent Society, it becomes abundantly clear that the Respondent Society is aware of the applicability of the Real Estate (Regulation and Development) Act, 2016 to its project; and that its contentions to the contrary are quite futile.
The Plan-2 and the related payment schedule annexed to the documents provided by the Respondent Society to the Complainant clearly state that the unit booked by him will have a built-up area of 1475 sq. ft. and break-up of the cost of the flat. Any payment made by the members would accordingly be counted towards the cost of the flat and the various components are integral to the total cost of the flat and have no existence or meaning as individual components. The contention of the Respondent Society that the Complainant has paid only towards land cost and not towards the cost of the flat has accordingly to be rejected squarely.
Further, from the reading of the Act, it becomes abundantly clear that the Respondent Society is covered within the meaning of the term ‘Promoter’ as defined in Section 2(zk) of the Real Estate (Regulation and Development) Act, 2016, sub-clause (iv) of which reads as under:-
2(zk) “…….. (iv) an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or ………..”
The contention of the Respondent Society, that the complaint of the Complainant in form M is not maintainable with this Authority, is accordingly not acceptable as the Respondent Society has itself placed a condition upon the members in the Declaration cum Expression of Interest that the project is subject to the provisions of the Real Estate (Regulation and Development) Act, 2016. Similarly, its contention that the adjudication of this case should not be with reference to Rules pertaining to RERAs of other States appears out of place as the Complainant has not sought any dispensation that is not covered by the Real Estate (Regulation and Development) Act, 2016 and the NCT of Delhi RERA (General) Rules, 2016.
The Respondent Society has not contested the claim made by the Complainant that he repeatedly demanded a refund of the deposits since May 2017; that the Respondent Society initially informed that such request could not be considered in the first two years; and that the Respondent Society later informed the Complainant that his request for refund had been placed at serial no. 82 in the waiting list of members demanding such refunds. The Respondent Society has also not contested the claim of refund made by the Complainant; and that even after more than five years of receiving the deposit, it has not provided any correct and updated information as to current state of the project and the likely date by which the project will be completed. The Respondent Society is duty bound to provide to all its members including the Complainant, correct and updated information with regard to the project in a transparent manner and failure to discharge these obligations attracts the provisions of Section 12 of the Act, which reads as under:-
Section 12. Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.
Further, the Respondent Society has admitted its liability and intention to settle the case with the Complainant on an amicable basis and some efforts in this direction were made but it is not clear whether the Respondent Society genuinely intended to settle the case or was making that a ploy for gaining time. Be that as it may, the admission of the Respondent Society towards the liability of the refund is sufficient to proceed with the case.
In view of the above, we are of the considered opinion that M/s. Revanta Multistate Cooperative Group Housing Society Ltd. (the Respondent) must return the entire amount of Rs.13,27,500/- (Rupees thirteen lakh twenty seven thousand and five hundred only) to Shri Sunny Sapen (the Complainant) within forty five days of issuance of this order, along with interest calculated at the rate of 9.30 per cent per annum (MCLR + 2%) from the date of payment of each amount until the date of its actual return.
Ordered accordingly.