Tribunals and CommissionsDivision Bench(2021) 11 RERA CK 0557

Ms. Shivangi Upadhyay vs M/s. Revanta Multistate Cooperative Group Housing Society Ltd.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 10 November 2021

CASE NUMBER
Complaint No. 33 of 2020
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

35 paragraphs · 2,437 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

The present complaint has been filed in Form‘M’on 22 June, 2020 by Ms. Shivangi Upadhyay (the Complainant) against M/s. Revanta Multistate Cooperative Group Housing Society Ltd.(the Respondent) seeking a refund of Rs.5,36,900/- (Rupees five lakh thirty six thousand and nine hundred only) paid by her to the Respondent Society towards booking and othercostsrelatingtoaType-1 Unit (1 BHK, LIG admeasuring 450sq.ft.) in their Adhikari Awas Yojna Project along with applicable interest as per RERA Rules.

2.

The brief facts of the case are that in November, 2019 the Complainant booked a Type-1 Unit(admeasuring450sq.ft.)in the Adhikari Awas Yojna Project situated on L- Zone under Land Pooling Policy (LPP) as per Delhi Master Plan,2021 near Nirmal Dham, Chhawla Village, New Delhi being developed by the Respondent Society M/s. Revanta Multistate Cooperative Group Housing Society Ltd.; that the total cost of the Unit as per payment plan conveyed by the Respondent Society vide their letter dated 20 November, 2019 to the Complainant was Rs.19,86,000/- including a payment towards land cost amounting to Rs.10,70,000/-;that the Complainant paid a total amount of Rs.5,36,900/-towards land cost and membership fee etc.by way of two cheques dated 28 November, 2019 and 24 December, 2019.

3.

At the time of booking the apartment in November, 2019 she was assured that the construction work relating to the project would start within the next six months; that there was no progress in commencement of work and seeing the fraud going on, she demanded refund of her deposits by surrender of her membership in April, 2020. However, the Respondent kept on dragging it in spite of calling them, going to their office and emailing them again and again. In response, they simply said that we do not have your replacement member and their accounts are freeze as such they cannot refund the money.

4.

The Complainant thereafter filed the present complaint in June, 2020 and also sent another email on 19 November, 2020 to the Respondent for refund of her amount along with interest.

5.

The main grievance of the complainant is the non-execution of the Project by the Respondent and despite persuasionRespondent is not refunding the amount deposited by her.

6.

Notice was issued to the Respondent on 18.8.2020, Reply was filed by Respondent on 31.10.2020 and Rejoinder was filed by Complainant on 21.02.2021 with a copy to the Respondent.

7.

The Respondent in their reply denied that they are a project promoter and submitted that the Respondent is a society registered under Section 7 of the Multi State Cooperative Societies Act, 2002 and it has been granted a registration certificate No. MSCS/CR/1049/2014 on 02 June,2014 by a Joint Secretary in the Department of Agriculture & Cooperation, Ministry of Agriculture, Government of India acting in his capacity as the Central Registrar of Cooperative Societies under the Multi State Cooperative Societies Act, 2002.The registration is valid for the NCT of Delhi and the state of Haryana subject to the terms and conditions laid down in the MSCS Act,2002.

8.

It is submitted by the Respondent that as per the condition under the certificate of registration the society was required to procure the land within six months from the date of registration. The Respondent and its members, including the complainant were required to comply with the conditions as stipulated in the certificate of registration. It is further submitted that all the details of land procured by the Respondent Society are already uploaded on the DDA portal for participation in Land Pooling Policy of DDA and the action can only be taken after DDA moves forward. The Respondent submits that on cursory look of the copies of receipts enclosed by the Complainant, a logical inference can be drawn that payment was received only for land cost and not for flat cost as it was an obligation on the Respondent to procure land within six months.

9.

While denying the violation of any provisions of the Real Estate (Regulation and Development) Act, 2016, it is contended by the Respondent the complaint is not maintainable, Respondent submits that the complaint filed in Form-M for refund, interest & compensation is not maintainable as per Rule 33 of the NCT of Delhi RERA (General) Rules 2016 as the said Rule has limited jurisdiction and does not cover refund, interest and compensation and the same are under the purview of Adjudicating Officer’s jurisdiction (Rule 34, Form N). Hence, in the light of afore-said reasons and submission, the Respondent prayed for the dismissal of the complaint.

10.

In rejoinder, the Complainant has denied each and every allegation, submission and contention of the Respondent and stated that Respondent by making false submissions are trying to escape from the liability as a builder/developer of project “Adhikari AwasYojna” in the name of Revanta Multi-State Cooperative Group Housing Society which is not just a Society but the Respondent is a builder/developer whose promoter is Mr. Pradeep Sehrawat.

11.

The Complainant further stated that the Respondent was to procure the land within six months otherwise registration of the society shall stand cancelled. The Respondent had not given the particulars of land acquired by them i.e. Khasra No., place and Zone etc. As such it appears that no land was procured by the Respondent within six months as such the registration certificate stands cancelled/expired in the month of December,2014 itselfand the society has not been in existence.

12.

The Complainant further submitted that at the time of signing of Declaration cum Expression of Interest, the registration certificate of the society was already expired hence the complainant is not bound by the term of the Declaration cum Expression of Interest and the same shall be liable to dismissed on the ground of fraud, misrepresentation and suppression of the facts.

13.

Further Complainant stated that Respondent never submitted the details of the land and Respondent is very much aware that DDA shall not move forward in near future and there is no time frame in the DDA Land Pooling Policy.; the Complainant submitted that the complaint under Form-M for refund, interest and compensation is maintainable under Rule 33 before the Authority;the Complainant repeatedly submitted that the Respondent is nothing like a Society but just a builder and cheated the Complainant by taking money without the procurement of land.

14.

It was submitted by the Complainant that several attempts were made by the Complainant via mail as well as by visiting the office regarding the status of project and refund but Respondent never cooperated with the Complainant for resolving the matter amicably.

15.

In the light of the above mentioned submission Complainant prayed to dismiss the Respondent’s submission with exemplary cost and be pleased to pass an order for refund along with interest and penalty in favour of the Complainant and against the Respondent. Complainant also prayed for Pendente Lite Interest during the pendency of the complainant.

16.

The submissions/arguments made by Shri Anil Kumar Goel, Ld. Counsel for the complainant and Shri DhirajBidhuri, Ld. Counsel for the Respondent were heard and the matter was reserved for orders on 12.8.2021 with a direction to both the parties to file their written submissions not exceeding 4 pages within 2 weeks.

17.

Written submissions from the Complainant were received on 27.08.2021. The submissions made by the Complainant are summarized as under:

a. Respondent is a Body Corporate under Section-9 of the Multi-State Cooperative Societies Act, 2002 by the name “M/s Revanta Multi-State Cooperative Group Housing Society Limited”, Respondent is a Builder/Promoter and a Body Corporate who has separate entity from its members and having perpetual succession and common seal. The Respondent is trying to escape from the liability as a Builder/ Promoter. All the submissions of Respondent are untrue. Respondent is Promoter under Section- 2(zk) under sub-section (iv) of the Real Estate (Regulation &Development) Act, 2016.

b. The Complainant reiterated that she had applied for the type 1 LIG Unit (1 BHK) for the built up area 450 Sq.ft. For a total cost of Rs. 19,80,000/- including cost of land as Rs. 10,80,000/- and have deposited Rs. 5,36,900/-.

c. Respondent had violated the provisions of Section 12 and Section 13 of the RERD Act, 2016. as the Respondent had taken Rs. 5,36,900/- as an advance which is more than 10% of cost of the apartment without first entering into a written agreement for sale. Hence, the complaint is maintainable and complainant is entitled for refund along with interest and penalty.

d. The further submission was made by the Complainant that the Respondent had violated Section 12 and 13 of the RERD Act, 2016 and complaint for the violation of provisions u/s 13 could be filed u/s 34(f), 34(g) & 34(h) read with rule 33 with this Authority. In the light of above mentioned submission the Complainant prayed for refund along with interest and penalty and also for Pendente Lite Interest during the pendency of complaint.

18.

Written Submissions were filed by the Respondent on 27 September, 2021. The Respondent in their submissions have refuted all the allegations raised by the Complainant and have stated that the Respondent is a Society registered under Multi-State Cooperative Societies Act, 2002; the payment received from the Complainant is towards the land cost only and not for the cost of flat, all the details of land is already uploaded on the DDA portal for participation in Land Pooling Policy and the action can only be taken after DDA moves forward and hence the complaint is not maintainable.

19.

I have heard the Ld. Counsel for both the parties and perused the material available on record. It is evident from the records that the respondent had received a payment of Rs.5,36,900/- from the Complainant under their project titled as ‘Adhikari Awas Yojana’.; Apparently, it is not the case of the Respondent that it is a registered society as such it cannot be considered as a promoter under the purview of the RERD, Act 2016, the limited argument of the Respondent is that the payment received is towards land cost and not for the cost of flat/ apartment, hence the provisions of the Real Estate (Regulation & Development) Act, 2016 [RERDA] are not applicable.

20.

The submission of the Respondent denying the applicability of the RERDA is not only half-hearted but also lacks reasoning. Apart from stating the fact that the respondent is registered under the Multi-State Cooperative Societies Act, the Ld. Counsel for the Respondent has failed to place on record any provision of the said Act or any other applicable law which exempts the applicability of RERDA on such registered society.

21.

A similar issue has already been decided by this Authority in Complaint No. 64/2019 titled as Shri Sunny Sapen v/s M/s. Revanta Multi State CGH Society Ltd. vide order dated 22.1.2021.

22.

Further, from the reading of the Act, it becomes abundantly clear that the Respondent Society is covered within the meaning of the term ‘Promoter’ as defined in Section 2(zk) of the Real Estate (Regulation and Development) Act, 2016, sub-clause (iv) of which reads as under:-

2(zk) “…….. (iv) an apex State level co-operative housing finance society and a primary cooperative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or ………..”.

23.

The contention of the Respondent Society, that the complaint of the Complainant in Form M is not maintainable with this Authority, is accordingly not acceptable as the Respondent Society has itself placed a condition upon the members in the Declaration cum Expression of Interest that the project is subject to the provisions of the Real Estate (Regulation and Development) Act, 2016. Similarly, its contention that the adjudication of this case is not covered by the Real Estate (Regulation and Development) Act, 2016 and the NCT of Delhi RERA (General) Rules, 2016 is far-fetched.

24.

The Respondent Society has not contested the claim made by the Complainant that he repeatedly demanded a refund of the deposits since April, 2020; that the Respondent Society has not provided any correct and updated information as to current status of the project and the likely date by which the project will be completed. The Respondent Society is duty bound to provide to all its members including the Complainant, correct and updated information with regard to the project in a transparent manner and failure to discharge these obligations attracts the provisions of Section 12 of the Act, which reads as under:-

Section12. Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act: Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.

25.

The Respondent Society appears to have floated a number of projects in different areas of NCT of Delhi including the project under the name ‘Adhikari Awas Yojna’ in which the Complainant Ms. Shivagi Upadhyay has booked a flat. The Respondent Society has prepared a common Membership Application Form for all its members. Themembership application form duly filled in by the Complainant and bearing thestamp and signature on behalf of the Respondent Company has been filed by the Complainant which also provides details of theunitsbookedbythemembersalongwithotherdetailssuchasthepaymentscheduleandann ualoperationcharges etc.

26.

On an overall reading of the contentions/submissions of the parties, the facts and circumstances of the case, I am of the considered opinion that the present case is squarely covered by the legal position held in the order dated 22.1.2021 of this Authority in Complaint no. 64/2019 Sunny Sapen vs. Revanta Multi State CGH Society Ltd .

27.

In view of the above, I am of the considered opinion that M/s.Revanta Multistate Cooperative Group Housing Society Ltd. (the Respondent) must return the entire amount of Rs.5,36,900/- (Rupees five lakh thirty six thousand and nine hundred only) to Ms. Shivagi Upadhyay (the Complainant) within forty five days of issuance of this order, along with interest calculated at the rate of 9.00 (nine) per cent per annum (MCLR +2%) from the date of payment of each amount until the date of its actual return.

28.

Ordered accordingly.

29.

No orders as to costs.