Tribunals and CommissionsFull Bench(2019) 01 RERA CK 0630

Shri Aashish Sethi vs M/s Umang Real Tech Private Limited

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 13 January 2019

RESULT
Disposed Of
CASE NUMBER
Complaint No. 24 of 2018
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

47 paragraphs · 3,872 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

The present complaint has been filed by Shri Aashish Sethi with a prayer to withdraw from the project "Winter Hills DwarkaMorh", and for refund of the amount paid to the Respondent "Umang Real Tech Private Limited" (a joint venture of Uppal Group & Indus Partners (USA), CIN-U45400DL2007PTC163070), along with interest.

2.

The Complainant states that he had booked an apartment bearing No. F-1002, with a super area ad-measuring 1653 sq.ft in the project Winter Hills Dwarka Morh for a total amount of Rs.1,38,16,145 (Rupees one crore thirty eight lakh sixteen thousand one hundred and forty five) by initially paying an amount of Rs.10 lakh on 13 April 2012. Subsequently, M/s Umang Real Tech Private Limited (in its capacity as the Power of Attorney holder of M/s. Uppal Housing Private Limited) allotted the above said flat to the Complainant Shri Aashish Sethi on 29 May 2012, and the two parties entered into a Builder-Buyer Agreement on 28 September 2012. The Complainant further states that under the Builder-Buyer Agreement, the project was to be completed by 31 March 2014 and that the possession of the apartment was to be delivered to him by the Respondent after obtaining the requisite completion certificate from the concerned authorities.

3.

The Complainant avers that he obtained a loan from the ICICI Bank for a total sum of Rs.1,06,99,000 (Rupees one crore six lakh and ninety nine thousand) for a period of 20 years and has regularly been paying an equated monthly installment (EMI) of Rs.1,08,620 (Rupees one lakh eight thousand six hundred and twenty). In addition to the above, the Complainant has informed that he has paid the Respondent other sums of money bringing the total to Rs.1,31,10,994 (Rupees one crore thirty one lakh ten thousand nine hundred and ninety four) as on date. The Complainant further states that the Respondent did not complete the project within the agreed period ending on 31 March 2014, nor within the grace period of six months thereafter i.e., until 30 September 2014. The Complainant states that since his apartment was not delivered in time, he had to arrange for a rented accommodation at a monthly rental of Rs.50,000 per month and has already incurred a huge sum of money on rentals since June 2015, when he first communicated to the Respondent his intention to withdraw from the project and demanded the return of his money with interest.

4.

The Complainant contends that the Respondent has tried to offer incomplete, non-habitable apartment to the Complainant on several occasions instead of taking actions to complete the project; that the project is still incomplete; that the Respondent has obtained an Occupancy Certificate (OC) fraudulently which OC is under challenge in Hon'ble High Court of Delhi. He asserts that since he did not get any positive response from the Respondent, he was left with no option but to approach this Authority for the refund of the amount with interest, and that the Respondent is liable for refund of the amount with interest as well as for payment of penalty/compensation.

5.

Notices were issued to the Respondent and in its reply the Respondent disputed the averments made by the Complainant and took the plea that there was no cause of action to file the present complaint; that the present complaint, which was filed without invoking the Arbitration Clause in the Builder-Buyer Agreement was liable to be dismissed; that the Respondent was entitled for reasonable extension of time for handing over the possession in terms of the Agreement and therefore there was no delay; that some material facts had been concealed by the Complainant relating to status of the project and payment of penalties by the Respondent; that the Complainant should have availed alternative civil remedies instead of approaching this Authority; and that the Complainant is not entitled to seek any remedies beyond the terms of the Builder-Buyer Agreement. The Respondent further contended that it had already obtained an Occupancy Certificate from the competent authority on 26 October 2017 and had subsequently issued a final call letter on 28 October 2017 to the Complainant mentioning about the Occupancy Certificate and offering him the delivery of possession of the apartment.

6.

The Respondent further contends that he had intended to complete the project well in time but was prevented from doing so due to compelling circumstances that were beyond its control, which may be termed as 'force majeure'. In his reply filed on 28/08/2018 he mentions the reasons for delay as the lack of adequate sources of finance, shortage of labour, manpower and material cost, the provisions and procedural difficulties, the shortage of water in the region, the restriction imposed by the Ministry of Environment and Forest on the scheme and unexpected demonetization and also recession in the economy and shortage of labour due to MGNREGA and JNNURAM Schemes. The Respondent further stated that the Complainant has failed to settle the balance amount as payable by him under the Builder-Buyer Agreement and has not taken heed to Respondent's letter for taking over the possession of the apartment that was offered to him. Finally, the Respondent contends that any dispute raised by the Complainant has to be resolved in accordance with arbitration clause contained in the Builder-Buyer Agreement and that the present complaint is not maintainable and is liable to be dismissed.

7.

With a view to striking a balance between the rights and obligations of Respondent as a Promoter and the Complainant/Allottee, the Authority gave the two sides ample opportunities to settle the matter amicably. The Authority directed the parties on 18 December 2018 to carry out a joint inspection of the building and in particular the apartment No. F-1002 to jointly ascertain the status of the completion of work and also to file photograph of the joint visit before the Authority. On perusal and consideration of the photographs so filed, the Authority gave further opportunity to the Respondent to complete the remaining work and also directed that the two sides may discuss the remaining matters between themselves and arrive at a mutual understanding. Despite providing them opportunities, the Authority noted that the Respondent did not demonstrate an inclination to settle the matter amicably and raise an unsubstantiated and one-sided demand of a further Rupees 22 lakhs to be paid by the Complainant without providing the break-up of how this amount had been arrived at.

8.

We have heard the Complainant Shri Aashish Sethi in person along with his Counsel Shri Nitin Kumar; and Shri Vineet Sinha Counsel for the Respondent at length and considered the documents, pleadings and written submissions filed by both the sides. The following issues arose for our consideration and decision:

(1)

whether the parties are so inextricably joined by the arbitrations clause contained in the Builder-Buyer Agreement that this Authority has no jurisdiction to entertain or decide this complaint;

(2)

whether the reasons for the delay in completing the project were beyond the control of the Respondent and governed within the meaning of the term 'force majeure' and whether a delay of several years in completion of the project can be considered reasonable;

(3)

whether an earlier order passed by this Authority in another case pertaining to the same project was to be treated as a good precedent and therefore binding.

9.

We now proceed to consider the above issues on the basis of material documents, pleadings/arguments made by the two sides.

Issue No.1:

10.

The Builder-Buyer Agreement entered into between the two sides on 28 September 2012 contains a Clause 16.10 relating to resolution of disputes between the two sides. The clause reads as under:

Clause 16.10

All the disputes, differences arising out of, in connection with or in relation to this transaction, which cannot be settled amicably, shall be finally decided by the arbitration to be preferred to three arbitrators, whereby one arbitrator each shall be appointed by the company and the buyer and the third/presiding arbitrator shall be appointed by the two arbitrators so appointed. The arbitration proceedings shall be conducted in accordance with the provisions of the Arbitration and Conciliation Act, 1996 or any modification and amendment made therein.

11.

The Complainant admitted to the above said clause but contended that the entire Builder-Buyer Agreement was one-sided in favour of the builder, and that at the time of booking there was no option for the Complainant but to sign the Agreement on dotted line and that he had approached this Authority by filing an application under a beneficial Act.

12.

There is a catena of judgments of the Hon'ble Supreme Court regarding maintainability of a complaint under a beneficial act such as the Consumer Protection Act even in cases where a clause dealing with arbitration may exist in the Builder-Buyer Agreement. We could however not lay our hands on any judgment in which the Hon'ble Court may have consider this in this specific context of the Real Estate (Regulation and Development) Act, 2016 on this issue. It would be appropriate to consider the objects and reasons of the Act; the Preamble of the Act states as under:

"An Act to establish the Real Estate Regulatory Authority for regulation and promotion of real estate sector and to ensure sale of plot, apartment or building, as the case may be, or sale of real estate project, in an efficient and transparent manner and to protect the interest of consumers in the Real Estate Sector and to establish an adjudicating mechanism for speedy dispute redressal and also to establish the appellate tribunal to hear appeals from the decisions, directions or orders of the Real Estate Regulatory Authority and the Adjudicating Officer and for matters connected therewith or incidental thereto."

13.

From the above preamble, the intention of the Legislature is quite clearly to protect the interests of the consumer in real estate sector and to provide a mechanism for a speedy dispute redressal system. It is also pertinent to note that the present Act is in addition to another law in force and not in derogation.

14.

It is also pertinent at this juncture to note the provisions of Section 71 and section 79 of the Act of 2016 whereunder the jurisdiction of Civil Court is barred but not that of any Forum; and, the power to adjudicate has been entrusted to the Authority including the adjudicating officer appointed by it, while restraining the complainant from forum shopping. A proviso under Section 71 also permits a complainant to withdraw his complaint from Consumer Forum/Commission where such complaint may be pending as on the date of the commencement of this Act, and to file an application before the adjudicating officer of the Real Estate Regulatory Authority. These provisions provide the consumer with two clear, but mutually exclusive, options for redressal of his grievances: one, by filing the complaint under the Consumer Protection Act, and the other by filing a complaint before KERA.

15.

While considering the issue of maintainability of a complaint before a consumer forum/commission in the face of an existing arbitration clause in the builder/buyer agreement, the Hon'ble Supreme Court in revision petition 2629-30/2018 in Civil Appeal No.23512-13/2017 titled as M/s. Emmar MGF Vs. Aftab Singh observed as under:

"Hon'ble Supreme Court considered the provisions of the Consumer Protection Act as well as the Arbitration Act. in Skypak Couriers Ltd. v. Tata Chemicals, (2000) 5 SCC 294, this Court laid down the following:

Even complaint is made by the consumer, in relation to a certain deficiency of service, then the existence of an arbitration clause will not be a bar to the entertainment of the complaint by the Redressal Agency, constituted under the Consumer Protection Act, since the remedy provided under the Act is in addition to the provisions of any other law if there exists an arbitration clause in an agreement and a for the time being in force.

The Hon'ble Supreme Court also considered the above issues in Case of National Seeds Corporation Ltd. v. Madhusudhan Reddy and Anr. and Fair Air Engineers Ltd. versus N. K. Modi, the Hon'ble Supreme Court observed the following in Para No. 25 which is as under-

para 25. This Court in the series of judgments as noticed above considered the provisions of Consumer Protection Act, 1986 as well as Arbitration Act, 1996 and laid down that complaint under Consumer Protection Act being a special remedy, despite there being an arbitration agreement the proceedings before Consumer Forum have to go on and no error committed by Consumer Forum on rejecting the application. There is reason for not on the strength an arbitration agreement by Act, 1996. The remedy under Consumer Protection Act is a remedy provided to a consumer when there is a defect in any goods or services. The complaint means any allegation in writing made by a complainant has also been explained in Section 2(c) of the Act. The remedy under the Consumer Protection Act is confined to complaint by consumer as defined under the Act for defect or deficiencies caused by a service provider, the cheap and a quick remedy has been provided to the consumer which is the object and purpose of the Act as noticed above."

16.

In view of the above observations of Hon'ble Supreme Court, a Complainant is well within his rights to seek a special remedy available in a beneficial act such as the Consumer Protection Act (and the RERA Act, 2016) instead of going in for an arbitration; also that the Forums (and the Authorities under the RERA Act) may entertain such complaints and decide on issues.

17.

With the Legislature being well aware of the tendency of the builder/promoters to formulate one-sided agreements in their own favour, it was provided in Section 13(2) of the Act "...that the Agreement for Sale ... shall be in such form as may be prescribed ...". Further, the Clause 33 of the 'Agreement for sale' annexed to the National Capital Territory of Delhi Real Estate (Regulation and Development) (Agreement for Sale) Rules, 2016 omitted the arbitration clause and replaced it with a special provision for dispute redressal under the Act.

18.

In view of the above, and taking into account that the Real Estate Regulation and Development Act 2016 is a special Act and beneficial Act to the allottees/consumers, we have no hesitation in holding that this Authority has the requisite jurisdiction to entertain the complaint and that the dispute does not require to be referred to arbitration necessarily.

Issue No. 2:

19.

The Complainant booked an apartment in April 2012 and a Builder-Buyer Agreement was executed in September 2012. As per clause 8.1 of the agreement in was the obligation of the promoter to deliver the possession of the apartment by 31 March 2014 after obtaining the requisite completion certificate from the concerned authorities.

20.

Clause 8.1 of the agreement reads as under:

8.1

The company, subject to force majeure, undertakes to complete the construction work of the residential complex and will apply for the completion certificate by 3rd March 2014, subject to a grace period of 6 (six) months, and as and when the completion certificate is received, possession of the said Apartment to the buyer shall be offered.

If the completion of the construction of the Residential Complex is delayed by reason of civil completion or by reason of war or enemy action or earthquake or any Act of God or if non-delivery of possession is a result of any statute, notice, order, rule, notification or ban imposed by the judiciary/government and/or authority, delay in issue/grant of completion certificate by the concerned authorities to the Company (such delay not being caused due to default of the Company) scarcity or unavailability of any construction material or for any other reason beyond the control of the Company, then in any of the aforesaid events the Company shall be entitled to a reasonable extension of time for offering delivery of possession of the said Apartment.

21.

Since it was the Respondent who wrote the agreement with the full confidence that he could get the allottees to sign on the dotted line, he seems to have included all conceivable reasons and/or circumstances that could potentially delay the completion of the project as something that was 'reasonable'. The various reasons and circumstances mentioned in the same clause 8.1 clearly go far beyond the definition of 'force majeure' – the clause is completely one-sided and creates an imbalance between the rights and obligations of the two sides. For example, if an allottee fails to pay an agreed amount within the prescribed period he is liable to a penal charge of Rs.10 per sq. feet (of the apartment) along with an interest on such penalty @ 18% per annum but if the promoter delays completion of the project in handing over of the possession of the apartment, the penalty charges leviable is fixed at Rs.5 per sq. feet with no interest.

22.

The Hon'ble Supreme Court while considering the Builder-Buyer Agreement to the case of Pioneer Urban Land and Infrastructure Ltd. Vs. Govindan Raghavan in Civil Appeal No. 12238/2018 observed that the premises of the Builder-Buyer Agreement shall not be of final and binding if it is apparent that the purchaser had no option but to sign on the dotted line. The builder has to fulfil his contractual obligation for obtaining the occupancy certificate and offering the possession of the flat to the allottee in time. While considering the judgment of the NCDRC, and confirming the refund of entire amount deposited by the allottee with interest, the Hon'ble Supreme Court passed the order as under:

"9.

We see no illegality in the impugned Order dated 23.10.2018 passed by the National Commission The Appellant - Builder failed to fulfill his contractual obligation of obtaining the Occupancy Certificate and offering possession of the flat to, the Respondent Purchaser within the time stipulated in the Agreement, or within a reasonable time thereafter. The Respondent Flat Purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the Agreement expired: During this period, the Respondent Flat Purchaser had to service a loan that he had obtained for purchasing the flat, by paying Interest @10% to the Bank. In the meanwhile, the Respondent - Flat Purchaser also located an alternate property in Gurugram. In these circumstances, the, Respondent - Flat purchaser was entitled to be granted the relief prayed for i.e. refund of the entire amount deposited by him with interest."

23.

In this case, while considering the facts and the pleadings filed by the parties, it became evident that the Builder-Buyer Agreement is entirely one-sided in favor of the builder. The apartment is not ready and is not in a habitable condition. This Authority has given ample opportunity to the respondent to complete the apartment and to arrive at an amicable solution but the respondent has not responded in the right direction and has instead slapped a demand of Rs. 22 lakh as a condition before giving the possession to the allottee and completing the flat. It is also pertinent to mention that Shri Gaurav Verma, Authorized representative of the respondents, during course of hearing filed details of the total payment demanded from the complainant but could not provide break-up of the details of demands. The respondent in their reply admitted that the following works is still to be carried out:

i)

Electrical Equipments (which was to be finalized by the Complainant as per the choice given in annexure to the Apartment Buyer Agreement); ii) Flooring of bedrooms (the complainant has to intimate his choice of flooring whether wooden or tile flooring via a snag list); iii) Final Coat of paint (of his choice at the time of taking over possession).

24.

Even after providing the opportunity, respondent has neither completed the apartment nor shown any intention to complete, leaving no room open for this Authority except to conclude that the respondent is delaying handing over the possession of the apartment and that the letters issued by him were only to cover up his own faults. Their occupancy certificate is also under challenge before Hon'ble High Court of Delhi as informed by the complainant. The project is not complete even after a lapse of almost five years from the date given in the agreement, and the plea of respondent that other families are living there cannot be taken as a ground that complainant be also forced to live in an incomplete apartment at his own risk or may be asked to wait indefinitely for completion of project.

25.

In case of Pioneer Urban Land and Infrastructure Ltd. V. GovindanRaghavan, the delay on behalf of the builders was considered by the Hon'ble Supreme Court and it was held by the Hon'ble court that the delay is delay and the allottee cannot be compelled to wait for a longer period. In the present case also, there is a delay of about 5 years after agreed date and since the delay has been caused by the respondent he may not be allowed to take advantage of his own wrong.

26.

The counsel for the respondent argued that the delay caused was beyond their control as the other Government agencies were involved. The reasons mentioned by the respondent in their reply filed on 28/08/2018 that the lack of adequate sources of finance, shortage of labour, manpower and material cost, the provisions and procedural difficulties, the shortage of water in the region, the restriction imposed by the Ministry of Environment and Forest on the scheme and unexpected demonetization and also recession in the economy and shortage of labour due to MGNREGA and JNNURAM Schemes. By no stretch of imagination, can the grounds mentioned by the respondents be covered within the definition of "FORCE MEJEURE", nor can these be considered as reasonable.

Issue no. 3

27.

Counsel for respondent contented that the Interim Regulator prior to the constitution of this Authority dismissed the Complaint No.11 of 2017 in Shikha Bansal and Gaurav Bansal versus the respondent, and held that if the complainant wished to withdraw from the project, he could do so as per provision mentioned in Builder-Buyer Agreement related to withdrawal and refund of the amount.

28.

The order of our learned predecessor was considered. Taking into account our findings on the above issues nos. 1 and 2, we are not in agreement with the Order of then learned Authority that the balance of convenience is towards the respondent and the agreement between the parties is binding.

29.

On the issue of interest, we are of the firm view that the interest part should be as per Act.

30.

In view of above, the complaint is disposed of with the direction that the respondent shall refund the amount of Rs.1,31,10,994 (Rupees one crore thirty one lakh ten thousand nine hundred and ninety four) received from the complainant along with interest @ 8.15% as per existing MCLR of SBI+2% as per provisions of Real Estate (Regulation & Development) Act, 2016 within a period of 45 days from the date of the order. It is clarified that the interest shall be payable from the dates on which the specific amount was paid to the Respondent by the Complainant.