Judgment
The case was taken up by the single bench in terms of the Order No. F-4(138)Admn/Bench/RERA/2022/1573-89 dated 19.03.2025.
Adv. Hanu Parashar, Proxy Counsel appeared on behalf of the Complainant.
None appeared on behalf of the Respondents.
The Ld. Counsel for the Complainant has placed on record the copy of the amended Form M. However, it is noted that no amendment has been made in Form M as per the order dated 15.07.2025. The Complainant was to amend the name of Respondents as “Delhi Infratech Limited.
The Ld. Counsel for the Complainant submitted that the amendments shall be made within 3 days and seek the liberty to make necessary amendments with edit mode.
Office is directed to provide edit mode to the Complainant.
An application has been moved for permission to place on record copy of the Agreement dated 21.10.2018.
The office has noted the discrepancy in the amount claimed by the Complainant in Form M. The discrepancy with regard to the payment of Rs. 5,47,750/-, the Complainant has filed copy of Memorandum of Understanding dated 21.10.2018 which shows that the Respondents received payment of Rs. 5,47,750/- in cash. As per the submission of the Ld. Counsel no receipt was issued by the Respondents with regard to this payment received in cash. The Application is allowed, the document is taken on record.
The Complainant shall carry out the necessary amendments within a weeks’ time from today thereafter a notice of the complaint be issued to the Respondents through all permissible modes with direction to file reply by 30.09.2025 with copy served on the Complainant.
The Complainant may file rejoinder, if any, by 10.10.2025 with copy served on the Respondents.
Matter be listed for hearing on 16.10.2025 at 11:30 am.