Tribunals and CommissionsDivision Bench(2023) 08 RERA CK 1002

Sh. Nabharanjan Pattnaik vs M/s Platinum Multistate Co-operative Housing Society Limited

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 23 August 2023

RESULT
Disposed Of
CASE NUMBER
Com/Dec/21/2021, 134/2021
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

43 paragraphs · 1,753 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

By this common order we decide both the complaints titled as above, filed in FORM ‘M’ before this Authority under section 31 of the Real Estate (Regulation and Development) Act, 2016 [hereinafter referred as “RE (RD) Act, 2016 or Act”] as common questions of facts and law are involved and they are filed against common Respondents i.e., “M/s Platinum Multistate Co-operative Housing Society Limited”.

2.

The Complainants in the above referred matters are allottees in the project, namely, “Co-operative Housing Society” proposed to be developed by the Respondents. The fulcrum of the issue involved in these complaints pertains to failure on the part of the Respondents to deliver timely possession of the booked units. Thus, the Complainants are seeking refund of the amounts deposited by them with interest.

3.

The details of the complaints, dates of notice & hearings, unit details , dates of welcome letter, name of project, amount paid by the Complainants are mentioned in the table below:

S.

no.

Case no. and Name of ComplainantsDates of notices, hearings andDates of reply and rejoinderDetails of unit as indicated in Form ‘M’Dates of membership application form and name of projectAmounts paid by the Complainants
1.

Com/ Dec/21/2021

Sh. Nabharanjan Pattnaik

09.03.2022, 27.04.2022, 19.07.2022, 04.10.2022, 07.12.2022, 28.02.2023, 10.05.2023 28.06.2022Reply was filed on 28.06.2022 and Rejoinder on 04.05.2022

Unit Type- Super

HIG admeasuring

1390 sq. ft.

14.11.2019 “Platinum Multistate Co-operative Housing Society”Rs.8,40,063/-
3.

134/2021

Sh. Kulwant Singh Bhalla

01.02.2022 31.03.2022, 04.05.2022, 14.07.2022, 04.10.2022, 07.12.2022, 28.02.2023, 10.05.2023Reply was filed on 16.02.2022 and Rejoinder on 04.05.2022Unit Type - A, 1 BHK admeasuring 415 sq. ft.12.12.2019 “Platinum Multistate Co-operative Housing Society”Rs.4,97,000/-
4.

The Complainants have sought refund of monies deposited by them with the Respondents along with interest as the project has yet not started in spite of lapse of considerable time.

5.

These cases were reserved for orders on 10.05.2023. The Complainant filed written submissions on 29.05.2023 in both cases.

6.

We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of Respondents are summarized as under:

i.

The Authority cannot adjudicate in the matter as the Respondent Society is registered under the Multi State Co-operative Societies Act, 2002 and does not come under the purview of the RE (RD) Act, 2016.

ii.

The money taken from the Complainant was for land to be submitted to DDA under the Land Pooling Policy and not for providing flats and apartments.

Analysis and Consideration:

7.

The RE (RD) Act, 2016 has been enacted to induct professionalism and standardization in the real estate sector, paving way catalyzing investments and accelerating growth of sector in long run. The Respondents are a multi state co-operative society and thus amenable to the provisions of Multi State Co-operative Societies Act, 2002. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. All disputes between homebuyers/allottees and promoters/developers relating to any real estate project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered under the Act to determine. Moreover, section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force. Thus, Multi State Co-operative Societies Act, 2002 cannot put fetters on the jurisdiction of this Authority to decide disputes between promoters and homebuyers.

8.

Further, in the RE (RD) Act 2016, an exhaustive definition of "promoter" is provided section 2. The sub-clause (iv) of clause (zk) of section 2 defines “promoter” as:

“an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or”

9.

The Respondent Society is a Multi-State Co-operative Society, which advertised membership, made members for their housing project namely “Co-operative Housing Society” and collected monies from them. The Respondents thus, fall within the definition of “promoter” as defined in the RE (RD) Act, 2016. Therefore, the Authority has jurisdiction to adjudicate the matter and pass appropriate orders on the complaint.

10.

The Ld. Counsel for Respondents have submitted that the monies collected were for purchase of land under the Land Pooling Policy of DDA and not for any flat or apartment. This argument is not tenable. The Respondents collected monies for housing project and purchase of land was a part of the housing project. The Demand Letters issued to the Complainants by the Respondents clearly mention the project “Co-operative Housing Society” promoted by the society. The aim and objective of the Respondent Society, thus, was to raise housing project and the Complainants invested money and became members of the Society for a flat in the housing project and not for purchase of land only. Therefore, the Respondents cannot shirk away from their obligation cast upon them by RE (RD) Act, 2016.

11.

The statement of objects and reasons of the RE (RD) Act, 2016 attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.

12.

An allottee/house buyer can seek refund of amount invested/deposited with the promoter under section 18 of RE (RD) Act, 2016, if the promoter fails to complete project by the date specified in agreement to sale with interest including compensation and also under section 12 of RE (RD) Act, 2016 if he/she was misled by any information furnished by promoter with regard to the project either through advertisement or otherwise.

13.

In the present complaint, the Complainants intend to withdraw from the projects on the ground of delay and are seeking refund of the amount paid to the Respondents in respect of above-mentioned units under section 18 (1) of the RE (RD) Act, 2016 which reads as under:

“Section 18. Return of amount and compensation.-

18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —

(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or

(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”

14.

Section 12 of the RE (RD) Act, 2016 casts a duty upon the promoter to provide correct and updated information to allottees regarding the project. It reads as under:

“Section 12. Obligations of promoter regarding veracity of the advertisement or prospectus.-

Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:

Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”

15.

The Respondents, in complete disregard to their duties, not only failed to furnish correct information to the Complainants but also misled them at the time of allotment itself by concealing information that they do not have any license or approval from the concerned authorities for construction of project and that no housing project can be developed on agricultural land proposed to be purchased by them. They also did not disclose the risks associated with the project to the society members including the Complainants. It is a pure simple case of giving part information and cheating the members of public at large.

16.

On perusal of the documents on record and submissions made by the parties, the Authority is of view that the Respondents are in contravention of the sections 18 and 12 of RE (RD) Act, 2016. And, therefore, the Complainants are entitled to get the refund of the amount paid by them alongwith interest at prescribed rate @ 10.75% p.a. (i.e., MCLR plus 2%) as per provisions of sections 18 and 12 of RE (RD) Act, 2016 read with rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016.

17.

The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors., Civil Appeal Nos. 6745-6749 of 2019).

18.

In the light of the aforesaid, we direct the Respondents, M/s Platinum Multistate Co-operative Housing Society Limited to refund the entire amount paid by each Complainant as enumerated in the table in para no. 3 of this order within 45 days of issuance of this order along with interest at the rate of 10.75% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.

19.

All cases are disposed of accordingly.

20.

No orders as to costs.