Judgment
By this common order we decide both the complaints titled as above, each filed separately in FORM ‘M’ before this Authority under section 31 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred as “RE (RD) Act”) as common questions of facts and law are involved and they are filed against common Respondents i.e., “M/s Revanta Multi State CGHS Ltd.” (hereinafter referred as “Respondents or Respondent Society”).
The Complainants in the above-referred matters are allottees in the project, namely, “Smart Residency” which were to be developed by the Respondents. The fulcrum of the issue involved in both these complaints pertains to failure on the part of the Respondents to deliver timely possession of the booked units. Thus, the Complainants are seeking refund of the amount sdeposited by them with interest.
The details of the complaints, dates of their filing, dates of notices & preliminary hearing, unit details, dates of issue of welcome letters, name of projects, amount paid by the allottees are mentioned in the table below:
S. no. | Case no. and Name of Complainant(s) | Dates of filing, notice and preliminary hearing | Unit details | Dates of Welcome Letters and project name | Amount paid by the Complainant(s) as per receipts |
|---|---|---|---|---|---|
| 1. | Com/09/03/2022 Ms. Asha Pandey | 25.03.2022, 09.06.2022 | 3 BHK, 137 sqm. | 14.09.2015 “Smart Residency” | Rs. 17,80,900/- |
| 2. | Com/08/03/2022 Sh. Harsh Chauhan | 06.01.2022, 09.06.2022 | 2 BHK, 1175 sq. ft. | 26.06.2015 “Smart Residency” | Rs.9,50,900/- |
The matters were heard in several hearings dated 02.03.2022, 28.03.2022, 17.05.2022, 12.07.2022, 15.09.2022, 16.11.2022 and 14.02.2023. The Respondents filed replies in two cases on 19.04.2022 and 22.04.2022. The Complainants filed written submission on 14.07.2022 and the Respondents on 04.08.2022 in all cases. All Complainants have sought refund of monies deposited by them with the Respondents along with interest as their project is yet to start in spite of lapse of considerable time.
We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of the Respondents are summarized as under:
The Authority cannot adjudicate in the matter as the Respondent Society is registered under the Multi State Co-operative Societies Act, 2002 and does not come under the purview of the RE (RD) Act, 2016 and further disputes between the parties should be referred to arbitration under section 84(1) of the Multi State Co-operative Societies Act, 2002.
The money taken from the Complainants was for land to be submitted to DDA under the Land Pooling Policy and not for providing flats and apartments.
Analysis and Consideration:
The RE (RD) Act, 2016 was enacted to induct professionalism and standardization in the real estate sector, thus paving way for accelerated growth and investments in the long run. The submission of Ld. Counsel of Respondents that RE (RD) Act, 2016 is not applicable in this case as Respondents are a Multistate Cooperative Group Housing Society registered under the Multi State Co-operative Societies Act, 2002, cannot be accepted. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. All dispute between homebuyers/allottees and promoters/developers relating to any real estate project, covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars the jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which this Authority is empowered by or under the Act to determine. Moreover, Section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force. Section 84(1) of Multi State Co-operative Societies Act, 2002 cannot put fetters on the jurisdiction of Authority to decide disputes between promoters and homebuyers.
Further, in the RE (RD) Act 2016, an exhaustive definition of "promoter" is provided under section 2. The sub clause (iv) of clause (zk) of Section 2 defines “promoter” as:
“an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or ”
The Respondent Society is a Multi State Co-operative Society, which advertised membership, made members for their housing project and collected monies from them. The Respondents thus, fall within the definition of “promoter” as defined in the RE (RD) Act, 2016. Therefore, the Authority has jurisdiction to adjudicate the matter and pass appropriate orders on the complaints.
The Ld. Counsel for Respondents have submitted that the monies collected were for purchase of land under the Land Pooling Policy of DDA and not for providing flats or apartments. This argument is not tenable. The Respondents collected monies for the housing project and purchase of land was a part of the housing project. The Welcome Letters issued to the Complainants by the Respondents clearly mention the project namely, “Smart Residency” promoted by the Respondent Society. The aim and objective of Respondent Society, thus, was to raise housing project and the Complainants invested money and became members of Society for housing project and not for the purchase of land only. Therefore, the Respondents cannot shirk from the obligation cast upon them by RE (RD) Act, 2016.
The statement of objects and reasons of the RE (RD) Act, 2016 attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoters and purchasers, transparency of contractual conditions, sets minimum standards of accountability and a fast-track dispute resolution mechanism.
An allottee/house buyer can seek refund of amount invested with promoter under section 18 of RE (RD) Act, 2016, if the promoter fails to complete project by the date specified in agreement to sale with interest and compensation and also under section 12 of RE (RD) Act, 2016 if he/she was misled by any information furnished by promoter with regard to the project either through advertisement or otherwise.
In the present complaints, the Complainants intend to withdraw from their respective projects on the ground of delay and are seeking refund of the amount paid to the Respondents in respect of subject units under Section 18(1) of the RE (RD) Act, 2016 which reads as under:
“Section 18: - Return of amount and compensation
18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —
(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,
he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”
Section 12 of the RE (RD) Act, 2016 cast a duty upon the promoter to provide correct and updated information to allottees regarding the current status of the project and the likely date by which the project will be completed. It reads as under:
“Section 12:- Obligations of promoter regarding veracity of the advertisement or prospectus
Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
The Respondents, in complete disregard to their duties, not only failed to furnish correct information to the Complainants but also misled the Complainants by concealing information that the housing project cannot be developed on agricultural land proposed to be purchased by them. They also did not disclose the risks associated with the projects to the society members including the Complainants. It is a pure simple case of giving part information and cheating the members of public.
On perusal of the documents on record and submissions made by both the parties, the Authority is of view that the Respondents are in contravention of the sections 18 and 12 of RE (RD) Act, 2016. As such, the Complainants are entitled to get the refund of the amount paid by them alongwith interest at prescribed rate @ 10% p.a. (i.e., MCLR plus 2%) as per provisions of section 18 and section 12 of RE (RD) Act, 2016 read with rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016.
The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors., Civil Appeal Nos. 6745-6749 of 2019).
In the light of the aforesaid, we consider it appropriate to direct the Respondents M/s Revanta Multistate CGHS Ltd. to refund the entire amount paid by each of the Complainant as enumerated in the table in para no. 3 of this order within 45 days of issuance of this order along with interest at the rate of 10.75% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.
The case is disposed of accordingly.
No orders as to costs.