AI Structured Summary
Not yet generated for this judgment
Judgment
Sh. Anand Yadav, Complainant appeared in person.
Adv. Deeptanshu Jain appeared on behalf of the Respondents.
Complainants have filed rejoinder and have supplied copy to the Ld. Counsel for the Respondents. Be taken on record.
Ld. Counsel for the Respondents has filed a copy of the Arbitral Award passed by the Arbitral Tribunal on 24.02.2024.
Ld. Counsel submitted that the Arbitral Award has held that the Promoter is not accountable for delay in the construction.
Let copy of this Arbitral Tribunal Award be given to the Complainants.
Pleadings are complete.
Matter be listed for final arguments on 28.03.2024 at 11:30 am.