Grievance in this application is against pollution of rivers Varuna and Assi in Varanasi by discharge of untreated sewage and unauthorized constructions. Case set out in the application is that the above rivers are tributaries of river Ganga and cleaning of river Ganga cannot be imagined without first ensuring prevention of pollution of the said rivers. The pollution of the said rivers is subject matter of various media reports. Water quality of river Ganga at Varanasi is in bad condition. Fecal coliform bacteria count at Varun-Ganga confluence is 71 million per 100ML of water (Ganga Jal) and fecal coliform count at Assi River and Ganga confluence is 52 Million per 100ML of water and on Assi Ghat fecal coliform is 1 lakh 40 thousand per 100ML of Ganga Jal. Permissible limit of fecal coliform bacteria should not exceed 500 per 100ML of water. Reference has been made to a report on water quality prepared by Sankat Mochan Foundation in Varanasi. It is further stated that there is concrete construction inside Ganga water channel at Lalita Ghat.
Vide order dated 17.06.2021, considering the seriousness of the issue and in the light of judgment of the Hon'ble Supreme Court in Paryavaran Suraksha case (2017) 5 SCC 326 and orders of this Tribunal in O.A. No. 593/2017, Paryavaran Suraksha Samiti & Anr. v. Union of India & Ors., O.A. No. 673/2018, In Re: News item published in "The Hindu" authored by Shri Jacob Koshy, titled "More river stretches are now critically polluted: CPCB" and O.A. No. 200/2014, M.C. Mehta v. UOI & Ors. (relating to river Ganga), the Tribunal constituted an independent Monitoring Committee comprising of Central Pollution Control Board (CPCB), State PCB, National Mission for Clean Ganga (NMCG) and District Magistrate, Varanasi to ascertain the factual status and take remedial action. NMCG was directed to file an action taken report in OA No. 200/2014, relating to rejuvenation of River Ganga, inter alia covering status on water quality of Assi and Varuna, action taken on diversion and treatment of sewage, water quality of upstream and downstream of confluence of Assi and Varuna to River Ganga, demarcation of Flood Plain Zones of Assi, Varuna and Ganga (in the said area), in accordance with the River Ganga (Rejuvenation, Protection and Management) Authorities Order, 2016.
Accordingly, an action taken report has been filed on 18.08.2021 by the U.P. State PCB on behalf of the joint Committee. The report mentions the minutes of meeting held on 30.06.2021 at CPCB attended by Dr. A. K. Vidyarthi, Additional Director & DH, WQM-II representing CPCB, Sh. Kalika Singh, RO, UPPCB, Varanasi representing State PCB, Sh. Rajat Gupta, SWM Specialist representing National Mission for Clean Ganga (NMCG) and Sh. Gulab Chand, ADM representing District Magistrate, Varanasi. In the said meeting action plan for river Varuna, prepared in pursuance of orders of this Tribunal in OA No. 673/2018, was discussed and revised. Issues of prevention of river water pollution, river ecosystem study and groundwater recharge, sewage and surface runoff management and encroachment were identified and addressing of gaps was planned. Thereafter, water quality was monitored and river restoration plan updated. Survey of all the concerned drains, tributaries was also undertaken. The revised action plan covering Restoration and rejuvenation of Varuna River and Restoration and rejuvenation of Assi River has been proposed which includes steps like de-silting, remediation of waste, development of floodplain, bio-diversity parks, sewage management, sludge management, industrial pollution management, solid waste management, removal of encroachments and monitoring mechanism.
The action plan proposed is reproduced below:
"Chapter 4. Action Plan
Action Plan, Work Plan, Timelines and Implementing Agencies for restoration and rejuvenation of Varuna and Assi Rivers, Varanasi
Riverscape restoration and rejuvenation of Varuna and Assi
A. Restoration and rejuvenation of Varuna River
Action Plan 1: Restoration of catchment wetlands located at the origin and downstream from the origin before joining Basuhi river (in this stretch the river is not polluted and does not have water in dry season).
Table 4.1 Action Plan for Restoration and rejuvenation of Varuna River
S. No
Work Plan
Timeline
Implementing Agency
1.
Desilting of wetlands upto the bed level and developing embankments with inlets from the catchment
10 - 12
months
UP Irrigation and Water Resource Department under the guidance of CEMDE
Location:
i) Mailhan,
Phulpur, Prayagr aj (25.599 571N,
82.1073
91E)
2.
Development of Biotic Communities (at both the above locations and other sites including embankments.
CEMDE, University of Delhi
Action Plan 2: Restoration of Basuhi and Morwa tributaries. Both the tributaries have clean water. However, two drains meet Morwa having small quantity of discharge which get diluted and carry clean water from their catchments and irrigation canal water to Varuna.
Table 4.2 Action Plan for Restoration of Basuhi and Morwa tributaries
S. No
Work Plan
Timeline
Implementing Agency
i.
Desilting of channels if it is not done during last 10 year
6 months
Irrigation and Water Resource Department
Location:
I. Upardaha Taal/Wetland in Handia of Prayagraj district
II. Kaitihawa, Tara (a small Pond) nearby Jigna Taal area in Handia, District Prayagraj (U.P) (25.38836 and 82.29644)
ii.
Vegetation development along the embankments and restoration riparian zone
2 years
CEMDE
Action Plan 3: Remediation of waste water that is discharged into Morwa (from two drains) and three major drains Dhoraira drain, Durga drain, Basti/ Naya Bazar drain that discharge sewage and industrial waste water into Varuna.
Table 4.3 Remediation of waste water that is discharged into Morwa
S. No
Work Plan
Timeline
Implementing Agency
i.
Remediation of waste water using
Constructed Wetland System. A schematic Constructed Wetland System (CWS) is attached. These CWS are set up at the confluence of the drain with the tributary/river and extend upto 100 m in the upstream from the confluence point. The length of CWS and number of units depends on theflow of water, the BoD, CoD, TSS and DO levels of water and width of the drain.
Locations: i) Dhoraira drain on Varuna at Bhadohi (25.417900N, 82.567600E)
ii) Basti/ Naya Bazar drain on Varuna at Bhadohi (25.415251N, 82.576675E)
iii)Durga drain on Varuna at Danyalpur, Varanasi (25.320033N,82.955642E)
iv) Burbuspur drain on Morwa at Rampura, Bhadohi (25.409475 N, 82.556622 E)
v) Chauri Drain on Morwa at Kom, Bhadohi
(25.369723N, 82.606431E
1-2years
Designed by CEMDE and Implemented by Irrigation and water Resource Department under guidance of CEMDE, water quality will be monitored by UPPCB
ii.
Desilting of drains upto bed level and strengthening of bunds with desilted material if not done during the last 5 year
1 year
Irrigation and Water Resource Department
iii.
Vegetation development on embankments of restored drain
CEMDE
Action Plan 4: Development of Floodplain Biodiversity Park at Adikeshwar Ghat where Varuna joins Ganga not only to enhance the water quality in Ganga in the stretch but also further enhance the quality of water of Varuna before discharged into Ganga by passing through treatment wetlands. The Biodiversity also help in restoring of riparian ecosystems and in stream community and also provide aesthetic and recreation value to Ganga.
Table 4.4 Development of Floodplain Biodiversity Park
S.
No
Work Plan
Timeline
Implementing Agency
i.
Plan, Design and Development of Biodiversity Park. A schematic layout of a typical floodplains Biodiversity Park is
attached.
5 years
CEMDE
Irrigation and Water Resource Department (supporting structure)
UPPCB (monitoring water quality)
Action Plan 5: Desilting of river Varuna in stretches where heavy sedimentation has taken place.
Table 4.5 Desilting of river Varuna
S. No
Work Plan
Timeline
Implementing Agency
i.
Desilting of river and Strengthening of embankments using desilted material
2 years
Irrigation and Water Resource Department
ii.
Vegetation Development on embankments
5 years
CEMDE
Action Plan 6: Monitoring of water quality at different sampling sites to assess the health of river ecosystems.
Table 4.6 Monitoring of water quality
S. No
Work Plan
Timeline
Implementing Agency
i.
Monitoring of water quality as per CPCB norms for river water before, during and after restoration
5 years
UPPCB
B. Restoration and rejuvenation of Assi River
Action Plan 1: Restoration of catchment wetlands at the point of origin and other wetland in the downstream to enhance the flow rates of water in the river.
Table 4.7 Restoration and rejuvenation of Assi River
S. No
Work Plan
Timeline
Implementing Agency
i.
Desilting of catchment wetlands and use of desilted material for making embankments with inlets
Kandwa wetland at Varanasi point of origin (25.273258 N, 82.962083 E)
and other wetland located in the downstream from the point of origin.
6 months
Irrigation and Water Resource Department
ii.
Remediation of sewage water that enters into catchment wetland using CWS at the mouth of the inlets before the confluence point. The length of wetland depends upon the flow of sewage and depth of water. A schematic layout of a typical CWS is attached.
1 year
CEMDE and
Irrigation and Water Resource Department
iii.
Vegetation Development on the embankment and development of aquatic communities in the wetland.
2-3 years
CEMDE
Action Plan 2: Remediation of sewage + household industrial waste water using Constructed Wetlands at stretches in the river where width is maximum with one largest CWS at 100 m away from the confluence of river with Ganga.
Table 4.8 Remediation of sewage and household industrial waste water using Constructed Wetlands
S. No
Work Plan
Timeline
Implementing Agency
i.
Setting up of CWS at 4 locations where width of river is maximum. The length of CWS depends upon the volume of water, quality of water, width of river. The riparian zones will also be restored.
2 years
CEMDE and Irrigation and Water Resource Department
Action Plan 3: Desiltation of river, if not desilted during the last 5 years and use of desilted material for strengthening of embankments wherever possible.
Table 4.9 Desiltation of river
S. No
Work Plan
Timeline
Implementing Agency
i.
Desilting of river up to the bed level and strengthening of embankment with desilted material
1 year
Irrigation and Water Resource Department
ii.
Development of vegetation on embankment wherever possible and restoration of riparian zone.
2-3 years
CEMDE
Action Plan 4: Development of Floodplain Biodiversity Parks at the Assi Ghat, from the historical confluence of Assi with Ganga, to the point where diverted. About 25 years ago the Assi River was diverted towards Ravidas Park from Nagwa road and it passes through Nagwa Colony and known as Nagwa drain before confluence with River Ganga. The old route of River Assi which is about 700 meters (from the point of interception Udupi Shri Krishna Madhav Temple to Sant Ravidas Park) carries household sewage and discharge into Nagwa drain. This may help in restoring the original Ghat where Assi used to confluence with Ganga and also enhance the quality of Ganga water.
Table 4.10 Development of Floodplain Biodiversity Parks
S. No
Work Plan
Timeline
Implementing Agency
i.
Plan, design and develop Biodiversity Park
5 years
CEMDE, Irrigation and Water Resource Department
Action Plan 5: Monitoring quality of water for sustaining the health of restored river ecosystem.
Table 4.11 Monitoring of water Quality
S. No
Work Plan
Timeline
Implementing Agency
i.
Monitoring of water quality as per CPCB norms before and after restoration
5 years
UPPCB
Figure 4.1 Schematic Diagram of Constructed Wetland
Figure 4.2 Schematic Diagram of Biodiversity Park
Sewage Management
A. Introduction
Varanasi city is presently divided into four sewerage districts located within current municipal corporation limits. Under the present sewerage master plan the existing districts are re-aggregated into 4 Districts to correspond roughly with natural drainage catchments. These Districts are described as follows:
District 1: District 1 is the Central City Sewerage District draining to 80 MLD Dinapur STP via 6 no. sewerage pumping stations. This area includes the old city, about 1km in breadth and 5km along the Ganga river from Assi to Raj Ghat. Density in this area is very high.
District 2: District 2 is further bifurcated in 3 zones name 2A,2B,2C & Future Sewerage Area 1 (FSA1). Zone 2A is the Sub-Central District on the cis-Varuna side west of the city centre and zone 2B is a slice of the trans-Varuna district along the Varuna river up to the ridge line defined by the Jaunpur road. Wastewater in these two zones will be collected at 140 MLD Chauka ghat MPS and finally treated in 140 MLD STP at Dinapur
District 2 Zone 2C: Zone 2C is the trans-Varuna District north of the Jaunpur road. Wastewater in this area generally falls to the north and to the east. FSA1 is north of the trans-Varuna District just outside the current Municipal Corporation limit. Wastewater generated in this area tends to flow north and east towards 120 MLD STP Goithaha.
District 3: District 3 is the BHU/Assi District south of the city including FSA 4. At present this area is mainly the Banares Hindu University campus which is fully sewered. Wastewater discharged in this area follows natural drains flowing into river Assi nala and Nakkhi nala. FSA4 is outside the current Municipal Corporation limit and surrounds the area occupied by BHU campus. Wastewater in this area drains to Assi river and Nakkhi nala which discharge to Ganga river upstream of the water supply intake and Ghats.currently 2 STP namely 50 MLD Ramana STP and 8 MLD Bhagwanpur STP are in service in district 3.
District 4: District 4 include FSA-2 and FSA-3 area which is outside the current Municipal Corporation limit. FSA2 is west of the current Municipal Corporation limit, and bounded by North-eastern railway. FSA3 is west of FSA2 and bounded by the Northern railway line. Currently there is no sewage treatment facility available in district 4.
Figure 4.3 Schematic representation of sewerage district of Varanasi city
Non-Sewerage Areas (NSA)
Non-serviced areas are identified as follows:
NWA1: NSA1 is within current Municipal Corporation limits to the east of the Trans-Varuna district. It includes the local community of Sarnath. Wastewater generated in this area drains naturally into Narokar nala which is now diverted to 120 MLD Goithaha via Intermediate Pumping Station.
NSA2: NSA2 is within current Municipal Corporation limits to the extreme north west of the trans-Varuna District. Sewage generation will be diverted to 120 MLD GoithahaVaranasi
B. Sewerage master plan- 2005 (JAPAN INTERNATIONAL COOPERATION AGENCY-JICA)
JICA formulated sewerage masterplan in 2005. The plan for 2015 is explained in (Figure 1)
Figure 4.4: JICA Sewerage Plan for 2015
As per JICA masterplan-2005 (figure 1) the projected population in Assi catchment area for the year 2015 is 78335 + 214570 = 292,905. The projected sewage generation was 14.5 + 39.7 = 54.2 MLD. To cater 54.2 MLD, 8.0 MLD is to be treated by 8.0 MLD existing Bhagwanpur STP and new proposed 37 MLD at Ramna.
The plan for 2030 is explained in Figure 2
Figure 4.5: JICA Sewerage Plan for 2030
As per JICA masterplan-2005 (above) the projected population for the year 2030 is 182781 + 291188 = 476969. The projected sewage generation was 28.3 + 39.7 = 73.4 MLD. To cater 73.4 MLD, new 37 (2015) + 38 (2030) = 75 MLD was proposed.
However, in 2014 situation, JICA relooked into the sewerage masterplan and revised the capacity of 75 MLD to 59.8 MLD (50 MLD new Ramana STP + Existing 9.8 MLD Bhagwanpur).
Action plan for Varuna catchment
Trans Varuna Catchment
It consists of sewage District 2 B and 2 C.A new STP of 120 MLD is constructed at Goitha and working efficiently. Around 40 MLD flow is treated. The STP capacity is sufficient for next 15 years. No new STP or upgradation of existing STP is proposed.
Cis Varuna Catchment
It consists of District 2 A. The present sewage flow from district 2 A is 80 MILD, which is being pumped from Chauka ghat pumping station and treated at Dinapur new 140 MILD STP.
In addition, new 140 MILD STP shall also treat 40 MILD flow diverted from Shahi Nala.
Recommendations
· 140 MLD Dinapur need to be upgraded to meet discharge standard.
· A new STP is needed to cater the future population for District 2 A.
· Action plan to treat wastewater from Durga drain discharging to Varuna River should be prepared.
· Interceptor drain plan is under execution by UP Irrigation Department. All designs should be checked by expert authorities.
Figure 4.9: Interceptor drain plan of Varuna River
Existing condition in Assi catchment
At present, as per CPCB measurement (12-15th July 2021), the flow in Assi River is around 92 MLD. In addition, STP at Bhagwanpur alsotreat 8.0 MLD flow and discharges into River Ganga via Nakha drain. Hence total discharge in Assi catchment is 92 + 8 = 100 MLD. However, water supply in municipal area of Assi catchment isonly 26 MLD.
The pumping capacity at Nagwa Pumping Station to cater 50 MLD Ramana STP is only 50 MLD, 8 MLD is treated at Bhagwanpur STP and rest 92-50 = 42 MLD discharges directly into the River Ganga.
Figure 4.12 Present sewerage Situation of Varanasi City
This rapid increase in flow to Assi River is due to:
Unprecedented residential/commercial growth is due to large no. of developmental projects during last 4-5 years owing to VIP constituency, which seems convincing.
The growth within the city is limited due to constraint of land availability. Assi -BHU area and Trans Varuna area is vast open for development. Hence, increment significantly in migratory/floating population.
Untreated wastewater from Sewerage District 2 & 4.
Much higher water consumption than prescribed 135 lpcd because of unregulated water usage i.e., personnel source of water-submersible pumps etc, which has no control of water usage.
Recommendations
A. Short Term plan
Presently actual discharge is mixed with rainfall. Actual dry weather flow can only be ascertained after rainy season. Detailed assessment of excess discharge is required to be done and hence future forecasting is to be done accordingly.
There should be 24-h proper flow measurement of Assi River by both Area velocity and V notch method after the monsoon season.
Controlling wastewater from other sewerage districts.
There should be check and control on non-revenue water (NRW). NRW is defined as loss of water through leakages and illegal usage.
Based on the flow measurement, water supply and population projection, a new STP need to be proposed either at Ravinder Puri Culvert (on the bank of Assi River around 1km upstream of confluence) or at Ramana existing 50 MLD STP site wherever found feasible. The DPR for additional STP is to be prepared after flow assessment and population projection.
B. Long Term Plan
Wastewater generation is very high, hence proper 24 x 7 water supply with metering is needed to control wastewater generation and non-revenue water. A JICA project is underway to control non-revenue water
Laying of complete sewerage system for the entire city.
9.8 MLD Bhagwanpur STP need to be decommissioned and new STP for higher capacity for future projections with new standards need to be constructed.
Banaras Locomotive Works STP should be upgraded to meet discharge standard.
Action plan for Ganga catchment
The sewage from District 1 (Old Varanasi) is treated in old 80 Dinapur STP. It is pumped from Konia Pumping station.
Recommendations
Old Dinapur STP (80 MLD) need to be decommissioned and new STP for higher capacity for future projections (as well as Shahi Nala Flow) with new standards need to be constructed.
Action plan for trans- Ganga
One new 10 MLD STP is constructed and treating around 8.0 MLD flow.
Recommendations
It is recommended that due to recent infrastructural development, there shall be rapid increase in population in near future.
It is assumed that 10 MLD full flow shall be reached within next 1-2 years. Hence, authorities should start planning for the next phase so that no untreated wastewater discharge from the trans Ganga in near future.
Table 4.12: Action Plan for sewage management in catchment of river Varuna, Assi and Ganga in Varanasi
Sl No
Sewerage District
Estimated Sewage Generation 2030
(MLD)
Pumping Station
River catchm ent
Existing Sewage Treatment Facility
Key issues
Proposed Action Plan
Implementing Agencies
Timeline for Action
1
District 1
93.7
Konia MPS,
Saraiya
P.S. 3.7 MLD
Cis Varuna
80 MLD STP Dinapur
· District 1 covers the old part of the city Varanasi including most of the markets and tourist destinations
· The district has very less scope of further escalation in sewage generation in near future
· Approx.80 MLD sewage Generated inthis district currently reaches 80 MLD Dinapur STP for treatment through Konia and Saraiya Pumping station via Old Trunk Sewer
· The rest of the sewage from old trunk sewer is discharged into river Ganga through
closed conduit at Shahi Nala Outfall, Rajghat
· Dinpaur 80 MLD STP has completed the design life and it was designed as per old discharge standards resulting in non-compliance of STP to norms prescribed by NGT
New STP of higher capacity for future projections with new standard to be constructed after decommissioning of
80 MLD STP at Dinapur.
UttarPradesh
Jal Nigam & National
Mission for Clean Ganga
Preparation of DPR - 3 Month Approval of DPR - 3 Months
Award of Work - 6 Months Completion of Work - 2 years Total Time required - 36 months
Management of rest of the sewage from old trunk sewer, presently discharging at Shahi Nala outfall through pumping to
140 MLD STP Dinapur.
Uttar Pradesh Jal Nigam
Work to be completed - 3 months
District 2A
225.3
(including NSA 1&2 & FSA-1
Chauka Ghat MPS (140 MLD),
Phulwaria MPS (7.6 MLD)
Cis Varuna
140 MLD STP Dinapur
· Chaukaghat pumping station is currently pumping only 70- 80 MLD to Dinapur 140 MLD STP.
· The interception and diversion of Shahi Nala outfall at Rajghat to Chaukaghat pumping station through a new rescue trunk sewer is proposed and work is underway
· The Cis-interceptor line at Varuna bank will also intercept the untapped drains on the cis Varuna bank to Chauka Ghat pumping station for pumping to Dinapur 140 MLD STP
· ASP technology based 140 MLD Dinapur STP without tertiary filtration
· No Biological nutrient removal (BNR) system
· Under capacity utilization
· I&D of drains (mainly Shahi Nala) is not completed
· Damaged & non-functional I&D structure
The 140 MLD STP
requires upgradation to meet the norms prescribed by Hon'ble NGT including nutrient removal
Uttar Pradesh Jal Nigam & National Mission for Clean Ganga
Preparation of DPR for upgradation
- 3 months
Approval of Work - 3 months
Award of Work for upgradation - 3 months Completion of upgradation
- 6 months
Total time required - 12- 14 months
·Design of
interceptor plan needs to be checked by expert agency and tapping shall be executed completely
· I&D work of drains falling into Varuna in Cis-Varuna area shall (mainly Shahi Nala) to be
completed and tapped to STPs for treatment
Irrigation Department, Uttar Pradesh Jal Nigam & subject expert
Design finalization - 1 month
I&D work completion with final tapping and pumping provisions - 2 months
Total time required- 3 months
District 2B
Narokhar IPS (7.6 MLD)
Trans Varuna
120 MLD STP Goitaha
· Trans Varuna area contains zone 2B & 2C sewage districts which has its sewage reaching partially for treatment at Goithaha STP through 7.6 MLD Narokhar pumping station and rest quantity by gravity.
· An interceptor line is under commissioning in trans Varuna river bank for interception of 7 drains in the area discharging into Varuna currently and other small minor outfalls from lanes
· The interceptor line has not been connected with pumping station currently and the interceptor system is open to flow
· This interceptor line will pump the sewage to 140 MLD Dinapur STP for treatment through Chauka Ghat MPS as an interim measure
· The Goithaha STP is currently functioning at around 30-40 MLD treatment (Under capacity utilization)
· Currently the catchment area of Goithaha STP has less population density so the capacity utilization is
less and it is targeted to achieve future utilization
· Design of interceptor plan needs to be checked by expert.
· Interception and diversion have to be completed at the earliest by the executing agencies
Irrigation Department, Uttar Pradesh Jal Nigam & subject expert
Design finalization - 1 month
I&D work completion with final tapping and pumping provisions - 2 months
Total time required- 3 months
District 2C
· I&D of the Trans Varuna area is not completed.
· Damaged & non-functional I&D structure meant for intercepting the Trans Varuna bank drains.
A new comprehensive sewage management plan for trans Varuna needs to be developed which can cater all the drains of trans Varuna area in Varanasi.
Uttar Pradesh Jal Nigam, Varanasi Municipal Corporation, Irrigation Department and Urban Development Department
Preparation of DPR - 6 months Approval of Work - 6 months Award of work - 6 months
Execution of work - 2 years
Total time required- 36-42 months
District 3
73.5
Nagwa MPS (50 MLD)
Assi River
50 MLD STP Ramana, 8 MLD STP Bhagwanp ur
· Estimated much higher water consumption/discharge than prescribed
· Unregulated water uses and flow of freshwater from Kanchanpur talab and other water bodies in the low-lying areas joining river Assi shall be identified and fresh water channels shall be separated from the sewerage line/drain
· Estimated approximately 50% Non -revenue water (NRW) is consumed of total freshwater usags
· Excess wastewater around 40- 45 MLD goes directly to Ganga River from the bypass point of Nagwa 50 MLD pumping station
· Bhagwanpur STP treats the sewage from Banaras Hindu University campus and treated sewage discharged through the Nakha drain which also carries untreated sewage from the Bhagwanpur local area and nearby areas of district 3.
· Detailed assessment of excess discharge in dry weather
· Control on NRW
Varanasi Municipal Corporation, Urban Development Department and Uttar Pradesh Jal Nigam
· A new STP of adequate capacity to treat the excess approx. 50 MLD flow from the Assi river outfall.
Uttar Pradesh Jal Nigam & National Mission for Clean Ganga
Preparation of DPR - 3 Month Approval of DPR - 3 Months Award of Work - 6 Months Execution of work - 2 years
· New STP at
Bhagwanpur of requisite capacity to be constructed as per new norms & flow data to cater the needs of BHU
· and nearby municipal areas.
Uttar Pradesh Jal Nigam & National Mission for Clean Ganga
Preparation of DPR - 3Months Approval of DPR - 3 Months
Award of Work - 6 Months Completion of Work - 2 years
Total Time required - 32- 34 months
· The Bhagwanpur STP is designed to treat 9.8 MLD sewage (8 + 1.8) but currently only 8 MLD plant is operated and 1.8 MLD unit is nonoperational
· The Bhagwanpur STP treats around 10 MLD sewage working overcapacity
· The Bhagwanpur STP has completed its designed life
· Large areas in adjoining district 4 and district 4 has recently been added in Municipal area and has no sewage management system existing which contributes to excess flow from district 2 & 4 reaching river Assi.
· Restoration of origin & stretches of river Assi (with land availability) through constructed wetlands.
· Separation of freshwater channels/storm water drains and sewerage system
Irrigation Department, Varanasi Municipal Corporation, Urban Development Department and Uttar Pradesh Jal Nigam
Within 6 months
6
District 4
45.1
None
Cis Varuna
Not available
· Most part of the Sewerage district 4 has recently been included in the Varanasi Municpal Area and estimation and planning for the newly added areas is underway
· Currently no dedicated treatment facility available
· No sewerage networks
· 'Untreated sewage directly discharges in R. Varuna.
· The Durga (Lohta) drain is the major drain discharging to River Varuna from the district
In-situ treatment at Durga Drain through Constructed Wetland as interim measure.
CEMDE Delhi University, Irrigation Department, Varanasi Municipal Corporation.
Preparation of feasibility reports & DPR - 02 Months
Approval of Work - 3 Months Award of work and implementation
- 3 Months
Total Time required - 8- 12 months
New STP of requisite capacity to be constructed as per
Uttar Pradesh Jal Nigam & National Mission for Clean Ganga.
Preparation of DPR - 01 Month Approval of DPR - 3 Months
Award of Work - 6 Months
· Actual discharge status is unknown
· Lohta STP (50 MLD) is proposed by 2030 (JICA report)
new norms & flow data.
Detailed assessment of excess discharge in dry weather
Irrigation Department, Uttar Pradesh Jal Nigam, Urban Development
department
Completion of Work - 2 years Total Time required - 32- 34 months
Within 2 months
7
Banaras Locomoti ve Work (BLW)
50 Staff colonies
Cis Varuna
12 MLD
· The BLW campus has a STP of 12 MLD installed inside campus to treat the sewage generated in the campus.
· The BLW campus lies in the Assi river catchment.
· At least one drain originates from the campus and two drains passes near the BLW campus and ultimately discharges into river Assi
· DLW-1 originates from the campus and carries treated sewage and storm water from the BLW campus
· DLW-2 originates from the Manduwadih area and flows near the BLW campus
· DLW-1 and DLW-2 ultimately meets river Assi near Sunderpur Chauraha DLW-3 originates from the Kanchanpur taal area and carries pond water and waste water from nearby low-lying areas
· DLW 3 meets river Assi near the DLW campus trans of DLW-Chunar Road.
· Around 2-3 MLD wastewater from this drain is treated at BLW STP for sometime
·BLW STP has outlived its designed life
·BLW STP shall be upgraded/new STP to be installed to meet norms prescribed by NGT including for coliform count
BLW Engineering Department, UP Jal Nigam, National Mission for Clean Ganga
Preparation of DPR - 01 Month Approval of DPR - 3 Months Award of Work - 6 Months Completion of Work - 2 years Total Time required
- 32- 34 months
· The Bhagwanpur STP is designed to treat 9.8 MLD sewage (8 + 1.8) but currently only 8 MLD plant is operated and 1.8 MLD unit is nonoperational
· The Bhagwanpur STP treats around 10 MLD sewage working overcapacity
· The Bhagwanpur STP has completed its designed life
· Large areas in adjoining district 4 and district 4 has recently been added in Municipal area and has no sewage management system existing which contributes to excess flow from district 2 & 4 reaching river Assi.
· Restoration of origin & stretches of river Assi (with land availability) through constructed wetlands.
· Separation of freshwater channels/storm water drains and sewerage system
Irrigation Department, Varanasi Municipal Corporation, Urban Development Department and Uttar Pradesh Jal Nigam
Within 6 months
6
District 4
45.1
None
Cis Varuna
Not available
· Most part of the Sewerage district 4 has recently been included in the Varanasi Municpal Area and estimation and planning for the newly added areas is underway
· Currently no dedicated treatment facility available
· No sewerage networks
· 'Untreated sewage directly discharges in R. Varuna.
· The Durga (Lohta) drain is the major drain discharging to River Varuna from the district
In-situ treatment at Durga Drain through Constructed Wetland as interim measure.
CEMDE Delhi University, Irrigation Department, Varanasi Municipal Corporation.
Preparation of feasibility reports & DPR - 02 Months
Approval of Work - 3 Months Award of work and implementation
- 3 Months
Total Time required - 8- 12 months
New STP of requisite capacity to be constructed as per
Uttar Pradesh Jal Nigam & National Mission for Clean Ganga.
Preparation of DPR - 01 Month Approval of DPR - 3 Months
Award of Work - 6 Months
· Actual discharge status is unknown
· Lohta STP (50 MLD) is proposed by 2030 (JICA report)
new norms & flow data.
Detailed assessment of excess discharge in dry weather
Irrigation Department, Uttar Pradesh Jal Nigam, Urban Development
department
Completion of Work - 2 years Total Time required - 32- 34 months
Within 2 months
7
Banaras Locomoti ve Work (BLW)
50 Staff colonies
Cis Varuna
12 MLD
· The BLW campus has a STP of 12 MLD installed inside campus to treat the sewage generated in the campus.
· The BLW campus lies in the Assi river catchment.
· At least one drain originates from the campus and two drains passes near the BLW campus and ultimately discharges into river Assi
· DLW-1 originates from the campus and carries treated sewage and storm water from the BLW campus
· DLW-2 originates from the Manduwadih area and flows near the BLW campus
· DLW-1 and DLW-2 ultimately meets river Assi near Sunderpur Chauraha DLW-3 originates from the Kanchanpur taal area and carries pond water and waste water from nearby low-lying areas
· DLW 3 meets river Assi near the DLW campus trans of DLW-Chunar Road.
· Around 2-3 MLD wastewater from this drain is treated at BLW STP for sometime
·BLW STP has outlived its designed life
·BLW STP shall be upgraded/new STP to be installed to meet norms prescribed by NGT including for coliform count
BLW Engineering Department, UP Jal Nigam, National Mission for Clean Ganga
Preparation of DPR - 01 Month Approval of DPR - 3 Months Award of Work - 6 Months Completion of Work - 2 years Total Time required
- 32- 34 months
· The 12 MLD STP at DLW operates at around 4 MLD only and the inlet raw sewage shows weak sewage characteristics with low organic load
· STP has no disinfection system to control Coliform count in treated sewage
·Reason for weak organic load characteristics of sewage at inlet of BLW STP shall be explored
· Water audit of water usage and discharge from BLW campus may be done
BLW Engineering Department, UP Jal Nigam, Uttar Pradesh Pollution Control Board
Within 1-2 Month
Sources of sewage and freshwater in the drains near the BLW campus ultimately discharging into Assi river shall be
identified and separated for reducing the flow in Assi river at interception point
BLW Engineering Department, Irirgation Department, Urban Development Department, UP Jal Nigam, Uttar Pradesh Pollution Control Board
·Identification of sources of waste and freshwater - 1 Months
·Preparation of action plan for separation of freshwater channels/storm water and waste water carrying drains- 6 Months
Table 4.13: Road map for execution of proposed action Plan for restoration of Varuna & Assi river
Sr.
No.
Sewerage District
/region
Existing Sewage Treatment
Facility
Proposed Action/remedial measure
Project Activity
Work Plan
Time line
Implementation Agency
80 MLD STP
Decommissioning of existing STP and construction
Condition assessment & feasibility report (CAFR)
1 Month
UP Jal Nigam/ Other government organization
Approval of CAFR
1 month
NMCG
1.
District 1
Dinapur
of new STP of higher capacity for future projections with new standard
Submission of DPR
2 Months
UP Jal Nigam/ Other government organization
Administrative approval &
estimated sanctioned
2 months
NMCG
Tendering & award of project
2 months
NMCG
Basic Engineering Package (BEP) submission
3 months
UP Jal Nigam/ Other government
organization /EPC
Design & Engineering approval
2 months
IIT/MNIT/Deemed university
Construction &
Commissioning
2 years
UP Jal Nigam/ EPC
contractor/others
2.
District 2A
140 MLD STP
Dinapur
Upgradation of STP as per new NGT norms.
Submission of DPR
2 Months
UP Jal Nigam/ Other government organization
Approval & Tendering
3 months
NMCG
Design & Engineering approval
2 months
IIT/MNIT/Deemed university
Construction & Commissioning
1-2 years
UP Jal Nigam/ EPC
contractor/ Other government
Design of interceptor plan
Submission of existing drawing & review proposal
1 month
UP Irrigation department
Approval & Tendering
3 months
NMCG
Design assessment of interceptor plan
2 months
IIT/MNIT/Deemed university
Approval, Tendering and project award
3-4 month
NMCG
needs to be checked by expert
Construction &
commissioning
3-4 month
UP Irrigation
I&D work of Shahi Nala
Tapping and diversion of Sahi nala to 140 MLD STP
1-2 months
Project is under execution by UP Jal Nigam
I&D work of drains in cis Varuna region
I&D work of drains up to 140 MLD MPS Chaukaghat
1-2 months
Project is under execution by UP irrigation department
3.
District
2B
120 MLD STP
Goitaha
I&D work of drains in trans
Varuna region
I&D work of drains up to 140 MLD MPS Chaukaghat
as an interim measure
1-2 months
Project is under execution by UP irrigation department
4.
District 2C
Development of new comprehensive sewage
Condition assessment & feasibility report (CAFR)
1 Month
UP Jal Nigam/ Other government organization
Approval of CAFR
1 month
NMCG
Submission of DPR
2 Months
UP Jal Nigam/ Other government organization
management plan for trans Varuna
Administrative approval &
estimated sanctioned
2 months
NMCG
Tendering & award of project
2 months
NMCG
BEP submission
3 months
UP Jal Nigam/ Other
government organization /EPC
Design & Engineering
approval
2 months
IIT/MNIT/Deemed
university
Construction & Commissioning
1-2 years
UP Jal Nigam/ EPC contractor/others
50 MLD STP
Assessment of excess discharge of
Assi River
Detailed assessment of excess discharge of Assi River in dry weather &
3-4 months
UP Jal Nigam
5.
District 3
Ramana,
8 MLD STP
Bhagwanpur
Design, construction and commissioning of new tapping arrangement
MPS, rising main & STP of requisite capacity as per new norms & flow data.
Condition assessment & feasibility report (CAFR)
1 Month
UP Jal Nigam/ Other government organization
Approval of CAFR
1 month
NMCG
Submission of DPR
2 Months
UP Jal Nigam/ Other government organization
Administrative approval & estimated sanctioned
2 months
NMCG
Tendering & award of project
2 months
NMCG
BEP submission
3 months
UP Jal Nigam/ Other government organization
/EPC contractor
Design & Engineering approval
2 months
IIT/MNIT/Deemed university
Construction &
Commissioning
1-2 years
UP Jal Nigam/ EPC
contractor/others
Restoration of Origin & stretches through constructed wetlands
Submission of design details & drawing of CWS
1 month
CEMDE
Submission of DPR for desilting, civil work etc.
2 months
Irrigation and water
resources department/
Approval, Tendering and project award
3-4 month
NMCG
Desilting and civil construction
3-4 months
Irrigation and water
resources department/
Vegetation development &
commissioning
1-2 years
CEMDE
Decommission of 8 MLD STP
Bhagwanpur And Design, Construction and
Condition assessment & feasibility report (CAFR)
1 Month
UP Jal Nigam/ Other government organization
Approval of CAFR
1 month
NMCG
Submission of DPR
2 Months
UP Jal Nigam/ Other
government organization
commission of new STP as per new norms and flow data
Administrative approval & estimated sanctioned
2 months
NMCG
Tendering & award of project
2 months
NMCG
BEP submission
3 months
UP Jal Nigam/ Other government organization
/EPC contractor
Design & Engineering approval
2 months
IIT/MNIT/Deemed university
Construction &
Commissioning
1-2 years
UP Jal Nigam/ EPC
contractor/others
Not
In-situ development of Constructed Wetland System in Durga Drain as interim measure
Submission of design details & drawing of CWS
1 month
CEMDE
Submission of DPR for desilting, civil work etc.
2 months
Irrigation and water resources department/ Other government organization
Approval, Tendering and project award
3-4 month
NMCG
Desilting and civil construction
3-4 months
Irrigation and water
resources department/ Other government
Vegetation development & commissioning
1-2 years
CEMDE
Design & construction of new STP of
Condition assessment &
feasibility report (CAFR)
1 Month
UP Jal Nigam/ Other
government organization
Approval of CAFR
1 month
NMCG
6.
District 4
available
requisite capacity as per new norms & flow data
Submission of DPR
2 Months
UP Jal Nigam/ Other government organization
Administrative approval &
estimated sanctioned
2 months
NMCG
Tendering & award of project
2 months
NMCG
BEP submission
3 months
UP Jal Nigam/ Other government organization
/EPC contractor
Design & Engineering
approval
2 months
IIT/MNIT/Deemed
university
Construction &
Commissioning
1-2 years
UP Jal Nigam/ EPC
contractor/others
7.
Varuna origin
Not available
Restoration of catchment origin of R. Varuna
Submission of design details
& drawing
1 month
CEMDE
Submission of DPR for desilting, channeling etc.
2 months
Irrigation and water
resources department/
Approval, Tendering and project award
3-4 month
NMCG
Desilting, channeling and other construction work
10-12 months
Irrigation and water
resources department/
Biotic community
1-2 years
CEMDE
Not
Desilting of R Varuna & In-situ development of Constructed Wetland System in Dhoraira, Naya
Submission of design details
& drawing of CWS
1 month
CEMDE
Submission of DPR for
desilting, civil work etc.
2 months
Irrigation and water
resources department
Approval, Tendering and
project award
3-4 month
NMCG
Desilting and civil
construction
3-4 months
Irrigation and water
resources department
8.
Along R. Varuna
available
Bazar, Bubuspur and Chauri drains
Vegetation development & commissioning
1-2 years
CEMDE
9.
Varuna confluence
Not available
Development of flood plain Biodiversity Park
Demarcation of flood plain of
R. Vruna at confluence
3-4 months
Irrigation and water
resources department
Submission of DPR for planning, design & development of Biodiversity
park
3-4 months
CEMDE
Approval, Tendering and
project award
3-4 month
NMCG
Development of Biodiversity park
4-5 years
CEMDE
Performance assessment of STPs and requirement for upgradation /augmentation
The estimated sewage generation of Varanasi (including Ramnagar) is approximately 330 MLD (201718) (as per data received from UPPCB). Total 7 STPs (5 commissioned and 2 under trial) with total capacity of 421.8 MLD (361 MLD for commissioned STPs and 60 MLD for under trial STPs) have been installed for the treatment of the generated sewage. Utilized capacity of the commissioned and operational STPs is approximately 210 MLD.
Characteristics of raw sewage received at inlet of STPs located in Varanasi have BOD ranging from 10.5 mg/l to 52.4 mg/l, COD ranging from 45.7 mg/l to 193 mg/l indicating weak sewage as compared to typical municipal wastewater (BOD: 200-250 mg/l, COD: 350-500 mg/l); is received at inlet of the STPs. The weak sewage strength could be due to dilution of the sewage from septic tanks and addition of grey water from households etc.
As per inspections conducted in last 2 years, the treated sewage from STPs is found non- complying with respect to the discharge norms. As per inspection dated 23.06.2021, reduction in BOD was found in range 38% to and 85%. Similarly, reduction in the COD was found in range 39% to 81%. STPs meet the prescribed norm for Total Nitrogen (10 mg/l) only when raw sewage with low Total Nitrogen (around 10 mg/l) is received. This necessitates upgradation and augmentation of these STPs. The measure suggested for the upgradation and augmentation of STPs are mentioned in the table below.
Discharge norm for Fecal coliform (230MPN/100ml) is not achieved in all STPs. Hence to achieve the norms there is requirement of upgradation/optimization of the existing disinfection system or installation of new disinfection system (if no disinfection system is present). The inflow at STP at Bhagwanpur is ranging from 8-14 MLD which is above the designed capacity (9.8 MLD). This STP needs capacity enhancement after detailed study for capacity requirement. STPs at Dinapur and Goithaha are underutilized. The reason for less inflow into STPs should be studied and areas without sewerage network should be provided with sewerage network and connected to respective STP.
Online continuous Effluent System (OCEMS) is installed at 12 MLD STP, BLW only. OCEMS should be installed at remaining 6 (4 operational and 2 under trial) STPs and connected to CPCB/ SPCB server at the earliest for on-line monitoring of the STPs.
Table 4.14: Performance assessment of STPs of Varanasi and requirement for their upgradation and augmentation.
Sr. No
STPs
Technol ogy & Process used
Designated Capacity (MLD)
Maximum Utilised Capacity (inspection date)
Inlet characteristics (mg/l)
Discharge to river
Operational/ Non- operational/ Non- functional
Compliance with respect to discharge standards (2021)
1
Dinapur (Old) STP
TF
followed by ASP
80
70
(23.06.2021)
BOD - 46.4,
COD - 160,
TSS - 169
TN - 7.02
(23.06.2021)
Ganga through open channel
Operational
Mostly found non-complying for FC
2
Dinapur (New) STP
ASP
140
125
(23.02.2021)
BOD-52.4 COD-161 TSS- 138
Varuna river through pipeline
Operational
Mostly found non-complying for TN and FC
TN-16.5 (23.06.2021)
3
Bhagwanpur BHU STP
ASP
9.8
14
(23.06.2021)
BOD-24.9 COD-92.2 TSS- 1242
TN- 8.83
(23.06.2021)
River Ganga through Nakkhi Nala
Operational
Mostly found non-complying for TN and FC
4
Goithaha STP
SBR
120
55
(23.06.2021)
BOD-56.3, COD-193 TSS- 491
River Ganga via Sharda Canal
Operational
Mostly found non-complying for FC
TN- 6.49
(23.06.2021)
5
BLW
(formerly DLW) STP
ASP
12
5
(23.02.2021)
BOD-10.5,
COD-45.7, TSS- 19.1
TN- 6.13
(23.06.2021)
Reused (may reach Ganga through Assi river)
Operational
Mostly found Non-Complying for FC
Note: Compliance status as per Hon'ble NGT order dated 30.04.2019. (pH: 5.5- 9.0; BOD: 10 mg/l; TSS: 20 mg/L; COD: 50 mg/L; Total Nitrogen (TN): 10 mg/L; Total Phosphorus (for discharge into ponds and lakes): 01 mg/L; Faecal Coliform: Desirable limit 100 MPN/100 ml, Permissible limit 230 MPN/100ml)
Sludge Management Plan
Treatment and disposal of sewage sludge are major factors in the design and operation of all wastewater treatment plants. Two basic goals of treating sludge before final disposal are to reduce its volume and to stabilize the organic materials. Stabilized sludge does not have an offensive odour and can be handled without causing a nuisance or health hazard. Sludge management is an issue of great concern due to its potential threat to human health and the environment with necessitated explicit regulations to organize their production and use. Currently adopted sludge management plan practices as provided by UP Jal Nigam for management of generated sludge is tabled below;
Table 4.15: Sludge management plan for generated STPs sludge
Sr No.
Name of STP
Capacity (MLD)
Approximate Generation of Sludge (Tonnes/Yr.)
Disposal of sludge
Remarks
1
Dinapur
80
8250
Being used as ingredient of Fertilizer by local farmers/manufact
ures
Since, removal of Nitrogen and Phosphorous is not part of the design process, hence the sludge has nutritional value and is being used as an ingredient of fertilizer.
2
Dinapur
140
6500
3
Bhagwan pur
9.8
275
Being used in Horticulture.
4
Goithaha
120
4350
Being used in land fill at various
locations.
Process design of STPs contains provision for removal of Nitrogen and Phosphorous, hence generated sludge doesn't have nutrients.
5
Ramana
50
5200
Proposed to be used in land fill at STP site itself.
6
Ramnagar
10
740
Proposed to be used in land fill at STP site itself.
Industrial Pollution Control
Industrial Pollution Management
During recent survey, 118 water polluting industries located in Varanasi and Bhadohi having potential to discharge into river Ganga and its tributary Varuna were inventoried which comprised Textile/Yarn (54 units), Sari Printing (33 units), Metal surface treatment (23 units), slaughter houses & meat processing (03 units), food & beverage (03 units) and Heavy engineering & Loco (02). Out of 118, 87 units are from textile/yarn and Sari printing sector.
Action Plan for prevention of pollution from Textile Cluster
Central Pollution Control Board (CPCB) has formulated the 'Charter for Water Recycling and Pollution Prevention in Textile industries" in consultation with experts from the departments of Chemical Engineering & Technology, IIT (BHU), Textile Engineering Department, IIT Delhi, Polymer and Fiber Technology, IIT Delhi, Fibre and Textile Processing, ICT, Mumbai, UP Textile Technology Institute, Kanpur and Textile industries (Annexure-V).
Charter is based on participatory approach and one of the important objectives of charter is to setup a bench mark for water consumption & optimize the use of water & chemicals in processing. Charter is formulated, with a view to envisage upgradation of the status of textile industries in sustainable manner in terms of process technology upgradation, adoption of best practices, improved environmental performance, substantial reduction in the fresh water consumption and waste water generation, improvement in effluent treatment including tertiary treatment and optimize water recycling. Compliance with the prescribed standards is mandatory. There will be no compromise with regard to the industry not meeting the prescribed standards.
Charter prepared for textile industries was launched in the workshop with the textile units at Kanpur on 05.04.2019. For implementation of Textile Charter to all River Ganga Main Stem GPIs, UPPCB issued direction under section 33A of Water (Prevention and control of Pollution), 1974 on 08.05.2019.
Charter was discussed with textile mills and experts at a workshop organized by Carpet Export Promotion Council at Bhadohi on 6th August, 2018. A workshop was also organized by UPPCB on implementation of "Charter for water recycling and pollution prevention in Textile industry" was held on 15th Oct, 2019 at Bhadohi.
As per data available with CPCB, during 2020, there were 31 textile sector GPIs in Bhadohi cluster and out of 31, 22 Textile units have prepared their individual action plan which were reviewed and the suggestions has been communicated to individual unit in the month of March-April, 2020 for implementation of recommendations as per charter.
However, during recent survey 54 yarn/textile and 33 sari printing units have been inventoried in Bhadohi, Jaunpur and Varanasi region in catchment of river Ganga and Varuna. Therefore, it is suggested that charter should be implemented in textile industrial cluster located in catchment of river Ganga and its tributaries in Uttar Pradesh in effective manner which will results in reduction in the fresh water consumption and waste water generation, optimize water recycling and overall improved environmental performance of industrial unit in sustainable manner. A monitoring committee may also be constituted to monitor the implementation status of charter in textile sector in a prescribed time frame.
Solid waste management
Proper Solid waste treatment system based on Indore or Goa model need to be prepared along with Waste to Energy system.
The un-segregated solid waste dumped in open plots or ponds/low lying areas within 500 meter of river Varuna in Varanasi contribute air and ground water pollution. The estimated quantity of legacy waste in this dumping site is approximately 30000 MT.
Management of legacy waste having adequate capacities for collecting, transporting and disposing of the municipal solid waste produced on a day-to-day basis as well as legacy waste trapped in the dumpsites is proposed to be done.
Illegal disposal of Construction and demolition waste in floodplain zone of river Varuna and Assi shall be prohibited.
Solid waste management plan of Varanasi City
Varanasi city has an estimated population of 15, 31,458 in 2020 based on projections for population taking 2011 population as base. Owing to its rich tourism potential, the estimated daily flow of tourists and pilgrims to the city is 25,000. The total area within Varanasi Nagar Nigam (VNN) is 82.1 km square for 90 wards and 86 more Villages have been merged with VNN area of 195 Sq km. The average waste generation of Varanasi is 0.400 kg per capita per day. The city at present generates 600 MT (Approx.) of waste per day at the rate of 0.400 Kg per capita per day and decadal population growth of 2.67 per Year (as per trend of rate of population growth in last 10 year: 2001-2011)
Table 4.16: Population Projection and waste generation for Varanasi City
Year
House Hold
Population
Waste generation MT/Day (approx) @ 400 gm per capita per day
2011
191278
11,98,491
479.39
2021 (for 90 Wards)
248300
15,31,458
612.58
2021 (For 86 Newly merged villages-20 wards)
151759
4,76,779
190.71
2035 (for 110 Wards)
512012
29,64,678
1185.87
2050 (for 110 wards)
655375
40,93,136
1637.25
The Government of India published the Solid Waste Management Rules, 2016, the Rules are now applicable beyond Municipal areas and extend to urban agglomerations, census towns, notified industrial townships, etc.
Administrative setup for MSW Management in Varanasi
The area falling under Varanasi Municipal Corporation is currently divided into 5 zones and 14 Subzone and 90 wards for administrative purposes and 86 newly merged villages. The details are annexed as Annexure VII.
Table 4.17: Manpower Engaged in Varanasi Nagar Nigam (VNN) for MSW Management
Designation
No
Municipal Commissioner
1
Additional Municipal Commissioner
1
Municipal Health officer
1
Executive Engineer's. (Transport & Processing-SWM)
2
Zonal Officers
5
Zonal Health officers
1
Sanitary & Food Inspector
14
Account Clerk
01
Account Officer
02
Safai Supervisors
93 (VNN-38 and Varanasi Waste Solution-40)
Safai Mitra's and drivers
5784 (VNN Safai Mitra's = 4171, VWSPL Safai Mitra-850, VNN drivers = 331, VWSPL Drivers195, Rag Pickers = 237)
· Currently there are no 100% door to door collections in 90 wards of Varanasi. Most of the households, shops, and establishments throw their waste just outside their premises, on streets, in drains, in open spaces, in water bodies, and in other inappropriate places.
· These litters swept away by street sweeping and lifted by means of handcart or rickshaw trolley by Sweepers and waste collectors of VNN, this led to unsanitary condition across the city.
· Varanasi Nagar Nigam outsourced M/s Varanasi Waste solution Pvt. Ltd. For door to door collection in 90 wards, mechanized road Sweeping approx.. 22.1 km. daily basis (Sant. Athulananda to BHU) and toilet cleaning work of Varanasi.
· Apart from door to door collection three Ngo's named Anthill Services Pvt. Ltd; career consulting pvt. Ltd, Jan Vikas Kalyan Samiti; Engage for IEC activities for sanitation awareness in their respective wards.
· The length of roads, streets, lanes, bye-lens in the city is approximately 1200 km in the total and approx. length of drains 2400 km area within Varanasi Nagar Nigam of 82.1 km square. Street sweeping starts between 8:00 AM and continues up to 2:00 PM.
The detailed action plan for MSW management in Varanasi city is enclosed as Annexure-VII
Encroachment
Removal of encroachment from lower floodplain zone of river Varuna and Assi. Demarcation and notification of floodplain zone by introducing pillars to further prevent encroachment in River Varuna and Assi.
Monitoring Committee
a. Supervisory Committee - It may supervise the implementation of proposed action plan for restoration and rejuvenation of River Varuna and Assi. The committee may consist of representative from District Magistrate, Varanasi Vikash Pradhikaran, Irrigation Department, Forest Department, Municipal Corporation, UP Jal Nigam, Urban Development Department, NMCG, UPPCB and CPCB under the chairmanship of Commissioner of Varanasi division, meeting to be held on quarterly basis.
b. Execution Committee - The committee may responsible for execution of proposed action plan for restoration and rejuvenation of River Varuna and Assi. The committee may consist Varanasi Vikash Pradhikaran, Irrigation Department, Forest Department, Municipal Corporation, UP Jal Nigam, Urban Development Department, SMCG and SPCB under the chairmanship of District Magistrate of concerned district, meeting to be held on monthly basis."
The report shows that there are serious issues adversely affecting rivers Varuna and Assi calling for remedial action in the form of desilting, remediation of waste water, development of constructed wetland systems and bio-diversity parks, apart from management of sewage, industrial pollution and solid waste which requires concerted and continuing steps and monitoring.
Since the issues and remedial steps have been identified by the joint Committee and exhaustive recommendations for remedial action made, there is need for execution of the action plan at the ground level in the light of above report. This requires coordination among the concerned departments including the Local Bodies, District Administration and State Government.
Accordingly, the Supervisory and Execution Committees suggested in the report may take further action. In terms of suggestions of the Committee, problem of chocking at the origin point of said rivers may be remedied by taking restoration measures. The execution Committee may meet atleast once in a month under the Chairmanship of District Magistrate, Varanasi and the Supervisory Committee may meet on quarterly basis under the Chairmanship of Commissioner, Varanasi Division, as suggested. The District Magistrate as well as Commissioner, Varanasi Division may have full time environmental coordinators attached to them directly for this purpose either out of the existing incumbents or by specially engaging a suitable person for the task. It will be appropriate that minutes of the meeting of the District Magistrate as well as Commissioner, Varanasi are placed on their respective websites, which may enable public information and participation. Having regard to the significance of the issue and need for prompt action for keeping the important rivers pollution free, the timelines need to be shortened which aspect may be considered by the Execution and the Supervisory Committees. We request the Oversight Committee constituted by this Tribunal headed by Justice S.V.S. Rathore, former Judge of the Allahabad High Court to oversee the steps taken in the matter, if necessary, by periodically interacting with the Execution and Supervisory Committees.
We further direct the NMCG and CPCB to monitor progress of implementation of action plan in accordance with the Namami Gange project.
The action plan may be placed on the website of CPCB and also circulated by CPCB to the River Rejuvenation Committees of all the States/UTs through respective State PCBs/PCCs, for appropriate consideration of their respective action plans to the extent found necessary.
The issue of funding of the projects proposed may be worked by the NMCG and the Chief Secretary, UP and wherever Namami Gange funds are found inadequate, it will be the responsibility of the State of UP to provide the same.
The application is disposed of.
A copy of this order be forwarded to CPCB, NMCG, Chief Secretary, UP, Additional Chief Secretary, Irrigation Department, UP, State PCB and District Magistrate and Commissioner, Varanasi Division by e-mail for compliance.
A copy of this order be also provided to all other concerned departments by the Additional Chief Secretary, Irrigation Department, UP.
A copy of this order be also forwarded to Justice S.V.S. Rathore, former Judge of the Allahabad High Court by e-mail.