Tribunals and CommissionsFull Bench(2019) 10 RERA CK 0843

P.P. City

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 18 October 2019

CASE NUMBER
No.F.1(14)/PR/RERA/2017

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

7 paragraphs · 685 words

M/s Puri Buildwell Private Limited hereinafter referred to as the Promoter has applied for registration of their Project - P.P. City Centre at Plot No.3, Road No.44, Pitampura, Delhi. After examination and considering the documents filed by the Promoter in relation to the Project, the Project Registration No.DLRERA2018P0003 was allotted and accordingly Form-C dt.08.02.2018 was issued. The Registration was valid upto 31.12.2018. The registration was granted subject to condition that promoter shall comply with the provisions of Act and Rules and also shall not act in contravention of any of the provisions of the law for the time being in force applicable to the Project. As per the declaration given by the Promoter, he was bound to complete the Project by 31.12.2018.

The Promoter did not file any quarterly report after getting the project registered. Accordingly, a Show Cause Notice dt.14.06.2019 was issued as he had failed to comply with the conditions laid down in the Registration Certificate. In reply to the Show Cause Notice, the Promoter-Puri Buildwell Private Limited submitted that they have received the Completion Certificate from D.D.A. on 16.02.2019. They have further stated no approval was pending as they have already completed the Project well within the time stipulated in the registration before 31.12.2018 and also applied for Completion Certificate to D.D.A. on 30.10.2018. They have also clarified that the Completion Certificate dated 16.02.2019 was issued in the name of Mr. Saurabh Puri and that due correction of name in the Completion Certificate, the Promoter applied for a revision of the Completion Certificate and the revised certificate was issued on 23.05.2019.

We have gone through the submissions of the promoter and it shows that it has applied for Completion Certificate well within the stipulated time of Registration, i.e., before 31.12.2018 but he could get the certificate only on 16.02.2019 from D.D.A. though in the name of Sh. Saurabh Puri and not M/s Puri Buildwell Pvt. Ltd. The Act provides that it is duty of the promoter to obtain the Completion Certificate from the Authority concerned in relation to rules related to Delhi. There is no such provision that if a promoter has applied for Completion Certificate within the period of registration of Project, there will be no need to get the extension of registration. The Project will be the as on-going if Completion Certificate is not obtained.

From the above, it is apparent that the promoter should have applied for extension of registration time within three months of the date of expiry, i.e., month of September, 2018 itself as per provisions of the Real Estate (Regulation & Development) Act, 2016 but he failed to do so and chose not to apply for extension of the Project. Though he has completed the Project and applied for registration on 30.10.2018 but after 31.12.2018 and till he got the Completion Certificate in relation to the Project on 16.02.2019, there was a violation of the provisions of the rules as during this period he should have got the extension which he chose not to do so. The Completion Certificates which the Promoter indicates are dated 16.02.2019 in the name of Sh. Saurabh Puri and dated 23.05.2019 in the name of M/s Puri Buildwell Pvt. Ltd. related to the same Project.

In view of the fact, even if it is considered that promoter got the Completion Certificate on 16.02.2019 there was still a violation of about 47 days under which the Project was neither registered nor the Completion Certificate was obtained.

In view of the above fact, considering that there is a violation of provisions of the Act and taking a lenient view that the Promoter should have applied for the extension of registration of the Project, it will be appropriate that a penalty of sum of Rs.1,00,200/- (Rupees One Lakh Two Hundred only) which is equivalent to the two times of registration fee is imposed over and above the usual fee that the Promoter would have paid at the time of renewal of registration of its project.

M/s Puri Buildwell Pvt. Limited is directed to deposit the above said amount within a period of 45 days.