Tribunals and CommissionsDivision Bench(2026) 08 NGT CK 7117

Nitin Anand vs Ministry of Railways & Ors.

National Green Tribunal, Principal Bench, New Delhi · Decided on 18 August 2026

RESULT
Disposed Of
CASE NUMBER
Original Application No. 590/2025 (IA No 619/2026) with Execution Application No. 21/2026 In Original Application No. 590/2025
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

26 paragraphs · 1,446 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

In this original application, the Applicant had raised the grievance against illegal dumping of solid waste in a stretch of 2.6 km of unused meter gauge railway track adjacent to new-leased Shyamganj railway station. The Applicant had alleged that this stretch of the railway track was not used for last 30-35 years and it had become an illegal open dumping ground of the solid waste.

2.

In the OA, the Tribunal by the order dated 19.02.2026 had issued the interim direction to the Respondent No. 1 to clean the entire solid waste lying dumped at the site within two weeks. The Applicant had filed EA No. 21/2026 seeking compliance of the said order.

3.

The Respondents No. 1 and 2 has filed the compliance affidavit dated 13.08.2026 disclosing the action which has been taken for removal of the garbage. The said affidavit discloses as under:

“xxx ……………………………………..xxx………………………………..xxx

4.

That in strict and immediate compliance with the specific directions contained in the aforesaid order dated 19.02.2026, Respondent No. 1, 2 has already taken multiple effective and concrete steps for removal of encroachments and prevention of further dumping, as detailed in the subsequent paragraphs of this affidavit.

5.

That a joint anti-encroachment operation was successfully carried out on 03.02.2026 in close coordination with the local police administration, Bareilly, and the Railway Protection Force (RPF), wherein 55 illegal encroachments comprising temporary huts, jhuggis, tin sheds and other unauthorized structures spread over approximately 500 meters length (from the level crossing near Shyamganj Yard towards Izzatnagar) were completely removed, resulting in reclamation of approximately 20,000 square meters of valuable railway land, and the operation was conducted peacefully with deployment of 02 JCBs, 02 tractor-trolleys, 01 pickup and more than 30 railway staff along with 22 RPF personnel. A copy of the Joint Note dated 03.02.2026 jointly signed by the officials of Railway, RPF and local police recording the complete details of the aforesaid operation have been annexed as ANNEXURE R-1 in short affidavit filed earlier.

6.

That immediately after removal of the said encroachments, the reclaimed railway land was thoroughly barricaded and secured by fixing railway pegs at regular intervals and digging deep trenches with the help of JCB machines so as to effectively prevent any re-encroachment and further unauthorized dumping of waste materials such as debris, soil, cow dung, hay, dairy waste and other solid waste by local residents or outsiders.

7.

That a detailed compliance report was prepared and sent on 04.02.2026 to the Chief Environmental Officer, Circle-7, Uttar Pradesh Pollution Control Board, Lucknow, fully narrating the actions taken on 03.02.2026 along with the joint note, photographs and newspaper clippings. A copy of the said compliance report/letter dated 04.02.2026 has been annexed as ANNEXURE R-2 in short affidavit filed earlier.

8.

That relevant colour photographs of the entire demolition drive conducted on 03.02.2026 showing JCB machines in operation, removal of structures, barricading work and cleared railway land, along with newspaper clippings from local dailies prominently reporting the successful removal of more than 150 illegal structures in the area, were collectively have been annexed as ANNEXURE R-3 in short affidavit filed earlier.

9.

That even prior to the major operation of 03.02.2026, multiple statutory notices were issued to all identified encroachers and repeated joint surveys were conducted with RPF teams to identify, mark and photograph the encroachments, thereby demonstrating the continuous and proactive efforts of Respondent No. 1, 2 to safeguard its land.

10.

That it is most respectfully submitted that the cleaning and removal of solid waste material already lying dumped at the site is not within the domain, expertise or statutory responsibility of Respondent No. 1 (Ministry of Railways).

11.

That under the Solid Waste Management Rules, 2016 notified by the Ministry of Environment, Forest and Climate Change, Government of India, and other applicable municipal laws and regulations, the primary, exclusive and statutory duty and responsibility for collection, transportation, processing, treatment and scientific disposal of all kinds of solid waste, including illegally dumped waste on any public or railway land falling within municipal limits, squarely and exclusively lies with the concerned Municipal Corporation, in this case the Bareilly Nagar Nigam.

xxx ………………………………..xxx……………………………….xxx

17.

That in response to the letter dated 24.02.2026, Incharge Officer (Solid Waste Management), Bareilly Nagar Nigam has informed the Respondent No. 1 and 2 vide letter dated 09.03.2026 that disposal of solid waste is being done by the Nagar Nigam on the basis of Pay & Use system at the rate of Rupees 1180/- per Metric Ton. A copy of the letter dated 09.03.2026 issued by Incharge Officer (Solid Waste Management), Bareilly Nagar Nigam is annexed hereto and marked as ANNEXURE R-1.

18.

That Respondent No. 1 and 2 vide letter dated 10.03.2026 have given their consent for the payment of requisite charges as informed in the letter dated 09.03.2026 for the disposal of solid waste lying on site. A copy of the letter dated 10.03.2026 is annexed hereto and marked as ANNEXURE R-2.

19.

That Health Department, Bareilly Nagar Nigam has inspected the site and found that approximately 418 Metric Ton Solid Waste was lying on the site. Municipal Commissioner, Bareilly Nagar Nigam vide letter dated 22.06.2026 has informed that as per inspection of Health Department, Bareilly Nagar Nigam total cost of disposal of Solid Waste lying at site will be approximately Rupees 4,93,240/- (418 MT @ Rupees 1180/-). A copy of the letter dated 22.06.2026 issued by Municipal Commissioner, Bareilly Nagar Nigam is annexed hereto and marked as ANNEXURE R-3.

20.

That there is a contradiction in calculation of solid waste found at the site between claim of UPPCB (Respondent No. 4) and calculation of Bareilly Nagar Nigam. UPPCB has calculated the same approximately 1500-2000 MT whereas Bareilly Nagar Nigam has calculated solid waste lying on site as 418 MT. Hence, Environmental Compensation has been calculated and levied found to be unreasonable and not sustainable and liable to be dismissed.

21.

That as per letter dated 22.06.2026 issued by Municipal Commissioner, Bareilly Nagar Nigam an amount of Rupees 4,93,240/- has been paid to the Nagar Nigam, Bareilly vide Memorandum dated 22.07.2026 and after meeting with Municipal Commissioner, Bareilly Nagar Nigam on 24.07.2026 removal and disposal of the solid waste lying on the site has been started from 25.07.2026. Copy of colour photographs and newspaper clippings from local dailies prominently reporting the successful removal and disposal of the solid waste is collectively annexed hereto and marked as ANNEXURE R-4.

22.

That a request vide letter dated 27.07.2026 The Regional Officer, Uttar Pradesh Pollution Control Board, Bareilly has been requested for the inspection and monitoring of the site. A copy of the letter dated 10.08.2026 issued by the Respondent No. 1 and 2 is annexed hereto and marked as ANNEXURE R-5.

23.

That removal and disposal of the solid waste lying on the site is in progress. Copy of colour photographs displaying the successful removal and disposal of the solid waste is collectively annexed hereto and marked as ANNEXURE R-6.”

4.

Learned Counsel for the Respondents No. 1 and 2 submits that the entire solid waste lying at the site in question has been cleared. He has pointed out that a sum of Rs. 4,93,240/- was paid by the respondent – railways to the Nagar Nigam Bareilly on 22.07.2026 for clearing of the solid waste and thereafter Nagar Nigam Bareilly has cleared the entire solid waste from the said stretch. On instructions, he has assured that the entire track will now be kept clean by the Respondents No. 1 and 2.

5.

In respect of the photographs filed by the Applicant alongwith the rejoinder on page 174, he has clarified that these photographs showing the solid waste in the area is dated 16.06.2026, whereas the action for clearing the solid waste by the Nagar Nigam Bareilly has been taken subsequently.

6.

In respect of the allegation of running of dairies close to the railway line, learned Counsel for the Respondents No. 1 and 2 has clarified that no such dairies are operating on the railway land.

7.

If the Applicant has any other grievance in respect of these dairies, he will be at liberty to approach the competent authority alongwith the supporting material.

8.

In view of the above, learned Counsel for the Respondents No. 1 and 2 submits that he is not processing IA No. 619/2026 which is an application for deletion of the Respondent No. 1. IA No. 619/2026 is accordingly dismissed as not pressed.

9.

Since the needful has been done by the Respondents No. 1 and 2, therefore, the compliance report submitted by the Respondents No. 1 and 2 is taken on record and OA and EA are disposed of.