Judgment
A complaint was filed in FORM ‘M’ on 01.03.2023 by Ms. Vinod Kohli (hereinafter referred to as “Complainant”) under section 31 r/w section 18 of RE (RD) Act, 20161 stating that she booked a commercial shop in 2006 in the proposed commercial project i.e. “RG City Centre” promoted by M/s Rajesh Projects (India) Pvt. Ltd. (hereinafter referred to as “Respondents”) in LSC, B-Block, Lawrence Road, New Delhi-110035.
In the present complaint, the complainant sought two primary remedies: first, a directive for the developer to provide possession of the unit and execute the conveyance deed, and second, the payment of delayed possession interest calculated from 36 months after the booking date until final offer of possession.
The preliminary hearings in the case were held on 08.05.2023, 29.05.2023 and 05.06.2023. The matter was subsequently heard on 23.08.2023, 21.09.2023, 21.11.2023, 30.01.2024, 13.03.2024, 08.05.2024, 30.05.2024, 03.09.2024 and 24.10.2024. The Respondents filed their reply on 13.03.2024.
For the sake of convenience, the main submissions and arguments of the complainant are as follows:
a. The complainant alleged that on 28.10.2006, she booked a commercial shop (Shop No. 101) in the RG City Mall project located at Lawrence Road, New Delhi, by paying a booking amount of Rs. 20,000/-. She subsequently paid a total amount of Rs. 27,00,000/- in cash towards the total sale consideration of Rs. 22,00,000/-.
b. The complainant submitted that despite making full payment, she has not received possession of the shop, and no conveyance deed has been executed. The developer failed to provide an allotment letter or enter into a builder-buyer agreement, even after receiving the complete payment.
c. The complainant made repeated requests for possession and execution of the conveyance deed, but the developer consistently ignored these requests. In an attempt to resolve the issue, the complainant paid outstanding maintenance dues of Rs. 2,91,528 in November 2015, with an understanding that the developer would then execute the conveyance deed. However, this promise was not fulfilled.
d. The complainant highlighted that the project remains ongoing, and the developer has breached its commitments by failing to provide possession of the unit for over 16 years since the initial booking. The complainant apprised the Authority that the project is unregistered.
The Respondents prayed for the dismissal of the complaint. For the sake of convenience, the main submissions and argument of the Respondents are as follows:
a. The Respondents primarily submitted that the complaint is not maintainable because the 'R G City Mall' project is not registered under RERA. They claimed that according to Section 3(2)(b) of the RE(RD) Act, 2016, they are exempt from RERA registration since the project was completed in 2008.
b. The Respondents contended that the project is not an ongoing project, but was completed and received an occupancy certificate on 29.07.2008. They asserted that the complainant's claim of a continuing project is false and that the complaint is being filed as a matter of convenience after many years of inaction.
c. The Respondents strongly denied the complainant's allegations of receiving full payment. They claimed that the complainant has not produced any receipts to prove the alleged payments and has failed to pay the entire sale consideration as agreed. As a result, they averred that the complainant cannot be considered a bonafide allottee.
d. They further contended that no builder-buyer agreement was ever executed between the parties. They attributed this to the complainant's failure to pay the full sale consideration, which led to the cancellation of the booking.
e. The Respondents also apprised the Authority that they have filed an application to keep the matter in abeyance due to Corporate Insolvency Resolution Process (CIRP) proceedings against the company. They acknowledged being under financial distress but maintained that the project was completed and delivered to genuine allottees.
On 23.08.2023, an application has been moved by the Ld. Counsel for the Respondents for keeping the matter in abeyance stating that moratorium has been issued by the NCLT, Delhi against the Respondent Company. The main contentions raised in the application are as follows:
a. The application was filed by the Insolvency Resolution Professional (IRP), Manoj Kulshreshtha, through authorized representative Sanjay Kumar Jha, seeking to keep the complaint in abeyance. The Respondent Company, Rajesh Projects (India) Pvt. Ltd., was undergoing Corporate Insolvency Resolution Process (CIRP) since 19.09.2019, which was pending before the National Company Law Tribunal (NCLT).
b. The Respondents/Applicant emphasized that the moratorium declared by NCLT in the matter of Babita Gupta & Ors. vs. Rajesh Projects (India) Private Limited in C.P. No. IB-710(PB)/2019 under Section 14 of the Insolvency and Bankruptcy Code, 2016. The Respondents submitted that this moratorium prohibited any legal proceedings, suits, or actions against the corporate debtor, including: institution or continuation of legal proceedings; transfer or disposal of company assets; enforcement of security interests and recovery of property.
c. The Respondents submitted that since the Respondent Company is now under the control of the Insolvency Resolution Professional and is unable to take any action regarding possessions or refunds for its projects.
Ld. Counsel for the Complainant has filed reply to the same application on 21.09.2023. He submitted that the Corporate Insolvency Resolution Process (CIRP) applies exclusively to the "RG Luxury Homes" project in Greater Noida and does not affect the entire company. To support this position, he cited a Supreme Court judgment of 11.05.2023 in CA NO. 1925 OF 2023 titled India Bulls Asset Reconstruction Company vs Ram Kishore Arora and Ors. which emphasized that insolvency proceedings should be confined to specific projects to avoid harming other homebuyers.
During the course of hearing, vide order dated 30.01.2024, the Authority formulated two primary issues for consideration which are as follows:
a. Whether in view of any moratorium issued by NCLT against the Respondent company, the proceedings before the Authority are liable to be suspended?
b. Whether the complaint is maintainable if it is shown that the Occupation Certificate and Completion Certificate of the project was obtained prior to the enactment of RE(RD) Act, 2016?
We have also heard the arguments of Ld. Counsels of both the parties and perused the records.
ANALYSIS AND CONSIDERATION:
Issue No. 1: Effect of NCLT Moratorium on Present Proceedings
The Respondents have sought to keep these proceedings in abeyance citing a moratorium declared by the National Company Law Tribunal (NCLT) under Section 14 of the Insolvency and Bankruptcy Code, 2016. They contend that this moratorium prohibits any legal proceedings against the corporate debtor.
However, upon careful consideration of the evidence presented, particularly the reply filed by the Complainant on 21.09.2023, it is evident that the Corporate Insolvency Resolution Process (CIRP) specifically pertains to the "RG Luxury Homes" project in Greater Noida and not to the entire operations of the Respondent company. This position is fortified by the Supreme Court's judgment dated 11.05.2023 in CA NO. 1925 OF 2023 in India Bulls Asset Reconstruction Company vs Ram Kishore Arora and Ors., which emphasizes that insolvency proceedings should be project-specific to protect the interests of homebuyers in other projects.
It is to be noted that the Hon’ble NCLAT has very well answered the intriguing question whether the insolvency proceedings with respect to one project can operate as moratorium in respect to another project irrespective of the location of the project, whether in the same jurisdiction/area or in jurisdiction of another state or territory. Para 21 of the order of Hon’ble NCLAT in Company Appeal (AT) Insolvency No. 926/2019 dated 04.02.2020 ‘Flat Buyer’s Association Winter Hills-77 Vs Umang Realtech’ clearly says that:
“21.In Corporate Insolvency Resolution Process against a real estate, if allottees (Financial Creditors) of Financial Institutions/ Banks (Other Financial Creditors) or Operational Creditors of one project initiated Corporate Insolvency Resolution Process against the Corporate Debtor (real estate company), it is confined to particular project, it cannot affect any other project(s) of the same real estate company (Corporate Debtor) in other places where separate plans are approved by different authorities, land and its owner may be different and mainly the allottees (financial creditors), financial institutions, financial creditors, operational creditors are different for such separate project”. Therefore, all the assets of the company (corporate debtor real estate) of that particular project is to be maximized for balancing the creditors of that particular project. Corporate Insolvency Resolution Process should be project basis, as per approved plan by competent authority”
Thus, it makes it crystal clear that insolvency proceedings with respect to real estate companies are ‘project centric’ and assets of one project cannot be merged or consolidated to overcome the losses of any other real estate project of the same real estate company.
Therefore, this Authority holds that since CIRP pertains to “RG Luxury Homes” in Greater Noida, the moratorium issued in those proceedings does not bar the present proceedings which relate to a distinct project, namely "RG City Centre" at Lawrence Road, New Delhi. Accordingly, these proceedings shall continue unhindered.
In view of the foregoing discussion and analysis, the application filed by the Respondents on 23.08.2023 seeking to keep these proceedings in abeyance is hereby dismissed.
Issue No. 2: Maintainability of Complaint Under RE(RD) Act, 2016
This issue requires examination of Section 3(2)(b) of the Real Estate (Regulation and Development) Act, 2016, which provides:
“3.(2) Notwithstanding anything contained in sub-section (1), no registration of the real estate project shall be required—
(b)where the promoter has received completion certificate for a real estate project prior to commencement of this Act;”
The definitions of ‘occupancy certificate’ and ‘completion certificate’ provided under Section 2 of the Act are pertinent to note for the matter in hand:
“2(zf)- ‘Occupancy certificate’ means the occupancy certificate, or such other certificate by whatever name called, issued by the competent authority permitting occupation of any building, as provided under local laws, which has provision for civic infrastructure such as water, sanitation and electricity;”
“2(q)- ‘Completion certificate’ means the completion certificate, or such other certificate by whatever name called, issued by the competent authority certifying that the real estate project has been developed according to the sanctioned plan, layout plan and specifications, as approved by the competent authority under the local laws.”
In the present matter, the Respondents have produced an occupancy certificate dated 07.11.2008 for the project and have argued that the completion certificate and occupancy certificate are in effect congruent with each other under Section 346 (2) of the Delhi Municipal Corporation Act, 1957 (hereinafter referred to as “DMC Act, 1957”).
For convenience, Section 346 of DMC Act, 1957 reads as follows:
“Completion Certificates- (1) Every person who employs a licensed architect or engineer or a person approved by the Commissioner to design or erect a building or execute any work shall, within one month after the completion of the erection of the building or execution of the work, deliver or send or cause to be delivered or sent to the Commissioner a notice in writing of such completion accompanied by a certificate in the form prescribed by bye-laws made in this behalf and shall give to the Commissioner all necessary facilities for the inspection of such building or work.
(2)No person shall occupy or permit to be occupied any such building or use or permit to be used any building or a part thereof effected by any such work until permission has been granted by the Commissioner in this behalf in accordance with bye-laws made under this Act:
Provided that if the Commissioner fails within a period of thirty days after the receipt of the notice of completion to communicate his refusal to grant such permission, such permission shall be deemed to have been granted.”
Regarding the notice of completion requirement, Section 346(1) of the DMC Act, 1957 mandates that upon completing a building or executing work, the person employing a licensed architect or engineer must submit a notice of completion to the Commissioner within one month. This notice must be accompanied by a prescribed certificate and facilitate inspection of the building or work.
Further, Sub-section 2 of Section 346 of DMC Act, 1957 mandates that no building can be occupied or used, either in full or in part, until a permission has been granted by the Commissioner in this behalf in accordance with the Bye Laws made under the DMC Act, 1957.
Respondents have produced an Occupancy Certificate dated 07.11.2008 issued by Assistant Engineer, Building Department, Delhi Development Authority for Vice Chairman, DDA. The certificate mentions that Respondents had given a notice of completion on 12.03.2008 and certifies that the building, whose description is given in the said Occupancy Certificate and whose plans were sanctioned vide No. 112 dated 15.12.2006, is declared fit for occupation.
The issuance of the Occupancy Certificate serves dual functionality - it not only certifies the project's completion but also grants occupancy permission. The legal framework treats the Occupancy Certificate to confirm that the project was fully completed and ready for use.
Therefore, in the case at hand, the Respondents have demonstrated their compliance by submitting the notice of completion on 12.03.2008, following which DDA issued an Occupancy Certificate dated 07.11.2008. Moreover, obtaining this certificate prior to 2017, coupled with actual occupancy, establishes full compliance with statutory requirements.
This certification, issued in response to the Respondents' notice of completion, validates that the project was complete with all necessary infrastructure and compliant with sanctioned plans. This fact combined with the project's pre-RERA completion fundamentally undermines complainant’s claims.
The legislative intent behind Section 3(2)(b) of the RE(RD) Act, 2016 was to exempt completed projects from the registration requirements of the RE(RD) Act, 2016. To interpret the provision as requiring both an occupancy certificate and a completion certificate would defeat this purpose and create unnecessary procedural hurdles for projects completed well before the Act's commencement.
Given that the project received its occupancy certificate in 2008, nearly eight years before the Act's commencement, and this certificate substantively certifies the project's completion, we cannot classify it as an "ongoing project" merely based on nomenclature. The Act's primary objective is protecting future homebuyers and regulating ongoing real estate developments, not reopening settled transactions from the pre-RERA period.
The Authority thus finds that the project was completed in 2008, well before the RE(RD) Act. 2016 implementation.
Furthermore, the complainant's delay in pursuing the matter - filing a complaint nearly 14 years after the initial booking - raises questions about the bonafides of the claim. The legal maxim "Vigilantibus non dormientibus jura subveniunt" meaning thereby “the law helps those who are vigilant, not those who sleep on their rights" becomes particularly relevant in this context.
Conclusion
In light of the above discussion and findings, we order as follows:
a. This Authority holds that it has jurisdiction to hear the matter as the NCLT moratorium order is project-specific and does not apply to the present case.
b. For the above-stated reasons, we find that the project, having obtained its occupancy certificate on 07.11.2008, was completed well before the commencement of the RE(RD) Act, 2016. Therefore, the project falls outside the purview of an "ongoing project" under Section 3(2)(b) of the Act. Accordingly, the complaint is not maintainable under the RE(RD) Act, 2016.
In view of the above findings and analysis, the complaint is hereby dismissed as not being maintainable.
No orders as to costs.
Footnotes
- 1.The Real Estate (Regulation and Development) Act, 2016