A complaint under section 31 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as ‘RE (RD) Act, 2016’ or ‘the Act’) read with Rule 33 (1) of The National Capital Territory of Delhi Real estate (Regulation and Development) (General) Rules, 2016 (hereinafter referred to as ‘Rules’) in Form ‘M’ was filed on 13.03.2020 by Ms. Daphne Reita Rajan Sharma (hereinafter referred to as ‘Complainant’ in Complaint Case (CC) No. 19/2020’) against M/s Umang Realtech Private Limited (hereinafter referred to as ‘Respondent-1 in Complaint Case (CC) No. 19/2020’).
Another complaint under section 31 of the Act read with Rule 33(1) of the Rules was filed on 27.01.2022 by Sh. Manish Kumar Gupta, Interim Resolution Professional (IRP) appointed by the Hon’ble National Company Law Tribunal (hereinafter referred to as ‘NCLT’), Principal Bench, New Delhi, vide order dated 20.08.2019 in CP No. IB-1564(PB) of 2018 titled as “Rachna Singh & Anr. Vs Umang Realtech Private Limited” against Ms. Daphne Reita Rajan Sharma. This Complaint Case taken on file as Complaint Case (CC) no. 16.01.2022.
As CC no. 19/2020 and CC no. 16/01/2022 relate to same project, “Winter Hills Dwarka-Morh”, are between the same parties and have common facts, therefore, both these complaints, are being disposed of by this common order.
Brief Facts in CC no. 19/2020:
The Complainant has stated that vide application form dated 21.08.2012, she booked a 3 BHK apartment, bearing no.1203, having super area of 1653 sq. ft. (153.56 sq. mt.) on 12th floor of Tower ‘F’ of the project being developed by Respondent-1 by the name of ‘Winter Hills-Dwarka Morh’ (hereinafter referred to as ‘Project-1’). An amount of Rs. 12,95,950/- (Rupees Twelve Lakh Ninety-Five Thousand Nine Hundred Fifty only) was deposited by her with the Respondent-1 as sale consideration by way of one cheque dated 21.08.2012.
The allotment letter was issued to her by Respondent-1 on 27.08.2012 and a tripartite Apartment Buyer’s Agreement (hereinafter mentioned as ‘ABA’) was entered into between her and Respondent-1 & Respondent-2 on 28.08.2012 wherein Respondent-2 signed as confirming party.
A total sum of Rs. 1,42,39,088/- (Rupees One Crore Forty-Two Lakh Thirty-Nine Thousand Eighty-Eight only) with Respondent-1 was deposited by her as detailed below towards the consideration of flat;
One cheque dated 21.08.2012;
One cheque dated 06.10.2012;
Seven cheques dated 07.12.2012;
Two cheques dated 16.04.2013;
Three cheques dated 18.04.2013;
Two cheques dated 24.07.2013;
Two cheques dated 25.07.2013;
Two cheques dated 12.08.2013;
Two cheques dated 16.08.2013;
Two cheques dated 26.09.2013;
Two cheques dated 23.10.2013;
One cheque dated 11.12.2013;
Nine payments made through NEFT on 06.02.2013, 24.08.2013, 26.08.2013, 27.08.2013, 25.05.2014, 26.05.2014, 20.06.2014 and two payments on 22.05.2014;
Four payments made through RTGS on 25.02.2014, 27.02.2014, 16.06.2014 and 02.09.2014;
One payment was made via NET on 26.08.2014.
The Complainant has stated that as per clause 8.1 of ABA dated 28.08.2012, the due date of possession of her apartment was 31.09.2014, i.e., 18 months from the date of allotment letter including six months of grace period but Respondent-1 have not given possession of the apartment to her till date.
She also stated that vide email dated 17.03.2017, she asked Respondent-1 to cancel her booking of above mentioned flat but they did not pay any attention to her request. Therefore, vide email dated 26.08.2017, she asked for refund of the entire amount deposited by her with Respondent-1.
In March 2019, the Complainant inspected the flat booked by her and found cracks in the construction and sub-standard fittings.
With the above mentioned grievances, the Complainant approached this Authority seeking following reliefs:
refund of entire amount of Rs. 1,42,39,088/- (Rupees One Crore Forty-Two Lakh Thirty-Nine Thousand Eighty-Eight only) deposited by the her with Respondent-1 due to inordinate delay in the completion of the apartment booked by her;
interest @ 8.15% as per existing MCLR of SBI+2% as per the provisions of the RE (RD) Act, 2016.
The documents submitted by the Complainant in support of her claim are listed below:
Application form dated 21.087.2012;
Receipt dated 24.08.2012;
Provisional allotment letter dated 27.08.2012;
Apartment Buyer’s Agreement dated 28.08.2012;
Receipt dated 05.10.2012;
Receipts issued by Respondents 1 to the Complainant on several dates from 24.08.2012 to 24.09.2013 as proof of payment;
Copy of E mail dated 09.06.2014;
Copy of E mail dated 21.06.2014
A preliminary hearing in this case was held on 13.08.2020.
The matter was further heard on 15.09.2020, 14.10.2020, 10.11.2020, 23.12.2020, 19.01.2021, 27.04.2021, 26.08.2021, 23.09.2021, 07.10.2021, 01.11.2021, 23.12.2021, 22.02.2022, 23.06.2023, 30.06.2023, 10.07.2023, 24.07.2023 and 08.08.2023.
A notice of complaint was issued to Respondent-1 on 05.11.2020.
During the course of hearing on 14.10.2020, the Complainant requested this Authority to implead M/s Uppal Housing Pvt. Ltd. as necessary party. The Complainant filed an application under Order 1 Rule 10 of Civil Procedure Code, 1908 on 05.11.2020, which was allowed by this Authority vide its order dated 10.11.2020 and M/s Uppal Housing Pvt. Ltd. was impleaded as Respondent-2 in CC No. 19/2020.
A notice of complaint was issued to the Respondent-2 on 27.04.2021. A reply was filed by them on 25.08.2021.
On 25.11.2020, an application under section 14 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as ‘IB Code, 2016’) was filed by the IRP of Respondent-1 for stay of the complaint as Respondent-1, a Private Limited Company, was under Corporate Insolvency Resolution Process (hereinafter referred to as ‘CIRP’) and moratorium was issued qua M/s Umang Realtech Pvt. Ltd. The Complainant filed the reply to this application on 22.12.2020.
Ld. Counsel for Respondent-1 argued that NCLT, vide its order dated 20.09.2019, initiated CIRP against Respondent-1 and declared moratorium with respect to the entire company and therefore, the Authority may drop further proceedings.
Further, he stated that Hon’ble National Company Appellate Law Tribunal (hereinafter mentioned as NCLAT), New Delhi vide its order dated 04.02.2020 in Company Appeal (AT) Insolvency No. 926/2019 ‘Flat Buyer’s Association Winter Hills-77 Vs Umang Realtech’ ordered reverse CIRP of Respondent-1 Company and directed that all the steps should be taken to complete the project on priority basis. At this point, the Respondent-1 Company relied on the ratio laid down in Civil Appeal no. 2901 of 2021 titled ‘Rachna Singh & amp; Anr. Vs Umang Realtech Private Limited’, Civil Appeal bearing No.1792 of 2021 itiled ‘K.N. Rajkumar Vs Nagarjun & Anr. and ‘Ghanshyam Mishra & Sons Private Limited through Authorized Signatory Vs. Edelweiss Asset Reconstruction Company Limited through the Director and others, 2021 SCC Online SC 313.
It is true that in all the above-mentioned cases the reverse CIRP has been observed which means that if the insolvency proceedings are initiated against any company, which is engaged in real estate business, every possible measure should be taken by the IRP to revive the project and keep project going. Liquidation being the last resort. The Hon’ble NCLAT has very well answered the intriguing question whether the insolvency proceedings with respect to one project can operate as moratorium in respect to another project irrespective of the location of the project, whether in the same jurisdiction/area or in jurisdiction of another state or territory.
Para 21 of the order of Hon’ble NCLAT in Company Appeal (AT) Insolvency No. 926/2019 dated 04.02.2020 ‘Flat Buyer’s Association Winter Hills-77 Vs Umang Realtech’ clearly says that:
“In Corporate Insolvency Resolution Process against a real estate, if allottees (Financial Creditors) of Financial Institutions/ Banks (Other Financial Creditors) or Operational Creditors of one project initiated Corporate Insolvency Resolution Process against the Corporate Debtor (real estate company), it is confined to particular project, it cannot affect any other project(s) of the same real estate company (Corporate Debtor) in other places where separate plans are approved by different authorities, land and its owner may be different and mainly the allottees (financial creditors), financial institutions, financial creditors, operational creditors are different for such separate project”. Therefore, all the assets of the company (corporate debtor real estate) of that particular project is to be maximized for balancing the creditors of that particular project. Corporate Insolvency Resolution Process should be project basis, as per approved plan by competent authority”
Thus, it makes it crystal clear that insolvency proceedings with respect to real estate companies are ‘project centric’ and assets of one project cannot be merged or consolidated to overcome the losses of any other real estate project of the same real estate company. In the present case, the project ‘Winter Hills-77’ is situated in Gurgaon whereas subject project ‘Winter Hills, Dwarka Morh’ is situated in Dwarka, New Delhi (hereinafter referred as ‘Project-2’) and from the above laid ratio, the reverse CIRP being observed in ‘Winter Hills-77, Gurgaon’ cannot be merged with ‘Winter Hills-Dwarka Morh’. The assets of project in the present complaint cannot thus be used to complete an other project even if it is of the same real estate company. Therefore, the contention of the Respondent-1 that moratorium in insolvency proceedings are in respect of project in Gurgaon also operates in respect of project located in Delhi, cannot be accepted. We must say that the Respondent-1 have miserably failed to interpret the ratio laid down in the above-mentioned cases and is trying to hide behind the provisions of section 7 of IBC 2016.
The said application dated 25.11.2020 under section 14 of IBC, 2016, was dismissed by the Authority vide its order dated 23.06.2023.
A reply to the complaint was filed by Respondent-1 on 13.09.2021.
The summary of arguments and submissions made by Respondent-1 are as under:
That the Respondent-2 was granted leasehold rights on a plot of land admeasuring 21954.8 sq. mtrs. (5.05 acres), located at a distance of 200 meters form Dwarka Morh, Metro Station, near Dwarka City, New Delhi, for a period of 90 years on 19.05.2006 for the purpose of development of a residential complex by the Delhi Metro Rail Corporation (hereinafter mentioned as ‘DMRC’).
That the Respondent-2 started developing the residential complex under the name and style of ‘Uppal’s Metro Park’.
That on 13.01.2010 Respondent-2 obtained a “No Objection Certificate” (hereinafter mentioned as ‘NOC’) from DMRC and entered into a Collaboration Agreement with Respondent-1 on 18.01.2010 whereby Respondent-1 undertook to develop and construct the residential units along with accompanying access, ways, landscapes and green areas, utilities and services etc. on the project land.
That after entering into Collaboration Agreement, the project was re-launched under the name and style of ‘Winter Hills, Dwarka Morh’ by Respondent-1.
That the Hon’ble National Green Tribunal, New Delhi (hereinafter mentioned as NGT, New Delhi) vide their order dated 10.11.2016, in original application no. 21 of 2014 imposed ban on all construction work in NCT of Delhi which was lifted on 17.11.2017.
That the Respondent-1 have stated that on 09.06.2017, they applied to the South Delhi Municipal Corporation (hereinafter referred to as ‘SDMC’) for issuance of Completion Certificate which was granted on 16.10.2017.
That the Respondent-1 offered possession of the subject unit to the Complainant on 28.10.2017.
That the project was registered with RERA, Delhi as per Registration Certificate dated 03.05.2018.
That during implementation of project, they faced following challenges:
Extreme shortage of water;
Shortage of bricks due to restrictions imposed by the Ministry of Environment and Forest on bricks kilns; • Unexpected and sudden declaration of demonetization;
recession in economy resulting in scarcity of labour and raw material;
shortage of labour due to implementation of social schemes like National Rural Employment Guarantee Act, 2005 (hereinafter mentioned as ‘NREGA’) and Jawaharlal Nehru Urban Renewal Mission (hereinafter mentioned as JNNURM).
That on 20.08.2019, the Hon’ble NCLT, Principal Bench, New Delhi initiated Corporate Insolvency Resolution Process (hereinafter mentioned as ‘CIRP’) against Respondent-1 in CP no. IB-1564(PB) of 2018 titled as Rachna Singh & Anr. Vs Umang Realtech Private Limited as per order dated 20.08.2019. In pursuant thereof, Flat Buyer’s Association Winter Hills-77, Gurgaon preferred an appeal bearing Company Appeal (AT) (Insolvency) no. 926 of 2019, titled “Flat Buyer’s Association Winter Hills-77 Gurgaon Vs Umang Realtech Private Ltd.” (hereinafter mentioned as ‘project-2’), before the Hon’ble NCLAT against aforesaid judgment dated 20.08.2019. Hon’ble NCLAT vide its judgment dated 04.02.2020 directed the CIRP to complete Project-2 within a specific timeline.
That ABA is binding on both the parties;
That the compensation, if any, is payable in terms of clause 8.6 of ABA;
That they intimated the Complainant vide letter dated 16.04.2018 that they are willing to compensate her for the delay as stipulated in ABA and also send an updated statement of accounts inclusive of the calculated compensation as penalty.
That the Complainant had filed CC no. 18/2019, titled as ‘Daphne Reita Rajan Sharma Versus Umang Realtech Pvt. Ltd., before this Authority, which was withdrawn by her subsequent to the initiation of insolvency proceedings against the Respondent-1.
Despite repeated requests by Respondent-1, the Complainant did not visit the apartment and did not come forward for taking the possession of the apartment by paying the outstanding amount dues.
That apartment of the Complainant is complete in all respects and possession thereof can be handed over to the Complainant, subject to payment of outstanding amount of Rs.15,11,797/- (Rupees Fifteen Lakh Eleven Thousand Seven Hundred Ninety-Seven only).
That funds are needed /required for the completion of project-2 under CIRP.
Summary of arguments and submissions made by Respondent-2 in CC no. 19/2020 are as under:
That ABA dated 28.08.2012 was a tripartite agreement between the Complainant, Respondent-1 and Respondent-2;
That they are only a confirming party in the said agreement;
That they entered into Collaboration Agreement on 18.01.2010 with Respondent-1 only after obtaining NOC from the DMRC for further licensing of the project land;
That after the execution of the Collaboration Agreement, Respondent-1 became entitled to all and any amounts in the nature of sales revenue that Respondent-2 have already received with respect to project-1 from the prospective flat buyers/allottees as detailed in Schedule-E of the Collaboration Agreement;
As per clause 6.1.2, of the Collaboration Agreement the Respondent-1 agreed and undertook to develop the project in accordance with the lease deed and by taking all the required building approvals by civic authorities;
That as per clause 7.1 of the Collaboration Agreement, the Respondent-1 undertook to bear and pay the entire cost of development of the project and all funds required for purpose of execution of project-1 shall be borne and funded by Respondent-1;
That all rights and liabilities of Respondent-2 had been transferred to Respondent-1 and Respondent-2 are not liable for any monies taken by Respondent-1 for the apartment booked by the Complainant;
That they neither demanded nor received any money/sale consideration from the Complainants;
That the Occupancy Certificate with respect to project-1 was obtained on 16.10.2017 whereas the present complaint before this Hon’ble Authority was filed on 05.03.2020 i.e., after the expiry of almost two and half years;
That they do not fall within the definition of ‘promoter’ as per section 2(zk) of the Act as they have neither constructed nor booked any flat/apartment in subject/project. They are only land owners as per lease agreement dated 19.05.2006; xi. That the registration certificate of real estate project in terms of section 5 of the Act was also granted to Respondent-1 by RERA, NCT of Delhi.
After hearing both the parties at length, the case was reserved for orders on 08.08.2023
Brief facts in CC No. 16/01/2022:
A complaint under section 31 of the Act r/w Rule 33 (1) in Form M was filed on 13.09.2021 by Interim Resolution Professional, Sh. Manish Kumar Gupta (hereinafter mentioned as ‘IRP’), appointed by the Hon’ble NCLT, principal bench, New Delhi, vide order dated 20.08.2019 in CP No. IB-1564(PB) of 2018’ titled ‘Rachna Singh & Anr. Vs Umang Realtech Private Limited’ on behalf of M/s Umang Realtech Private Limited.
The Complainant in his complaint stated that the company is engaged in the business of construction and development of real estate projects and has carved a niche for itself in the real estate sector.
The Complainant in this complaint is Respondent-1 in CC no. 19/2020. For the sake of brevity, the summary of arguments and submissions contained in para 25 (i) to (xvi) may also be read as summary of arguments & submissions made by the Complainant.
The Respondent in CC no. 16/01/2022 is the Complainant in CC. no 19/2020. The arguments and submissions made in CC no. 19/2020 in paras 2 to 10 may be read as arguments & submissions made by the Respondent in this CC as no new facts have been brought on record by the Respondent.
The reliefs sought by the Complainant in this case are as under:
a. direct the Respondent to clear the outstanding dues payable towards the unit along with applicable interest as provided under the Rules;
b. direct the Respondent to take the possession of the unit and execute the sub-lease deed of the unit after paying the requisite stamp duty;
c. grant any other relief as may be deemed fit by this Hon’ble Authority.
A preliminary hearing was held on 15.03.2022. The case was further heard on 12.05.2022, 02.06.2022, 23.06.2023, 30.06.2023, 10.07.2023, 24.07.2023 and 08.08.2023.
Notice in the present complaint to the Respondent, Ms. Daphne Reita Rajan Sharma was issued on 14.02.2022, which was not delivered due to incorrect address. During the course of hearing on 15.03.2022, Ld. Counsel of the Complainant was asked to give the correct address of the Respondent. On same date it was noted that CC no. 19/2020 which is based on similar facts and between the same parties was pending adjudication before this Authority. Hence, the Authority ordered that both the complaints being cross suits be clubbed together in single hearing. After hearing the arguments of both the parties at length, the cases were reserved for orders on 08.08.2023.
Both the parties were directed to submit their respective written submissions by 30.06.2022. Final written submissions were made by M/s Umang Realtech Pvt. Ltd. (Respondent in CC no. 19/2020 and Complainant in CC no. 16.01/2022) on 30/06/2022 through email. Final written submissions were made by Ms. Daphne Reita Rajan Sharma (Complainant in CC no. 19/2020 and Respondent in CC no. 16/01/2022) on 04.07.2022.
The issues to be determined by this Authority are as under:
Whether the Respondent-1 is responsible for delay in completing the Project-1?
Whether Complainant in CC no. 19/2020 is entitled to get refund of Rs. 1,42,39,088/- (Rupees One Crore Forty-Two Lakh Thirty-Nine Thousand Eighty-Eight only) deposited by her with the Respondent-1 u/s 18 (1) (a) of the Act?
If the above-mentioned points are decided in affirmative, then who should be liable to pay the amount of refund to the Complainant, Ms. Daphne Reita Rajan Sharma?
Analysis and consideration of issues:
It is noted that issues no. i & ii stated above are, inter-related, hence both should be decided together.
It is the submission of the Respondent-1 in CC no. 19/2020 that the delay in the completion of the project was due to circumstances beyond their control. In order to analyse the said contention, the attention of the Authority was drawn to the clauses mentioned in the ABA signed between the Complainant and Respondent-1.
Clause 8.2 of the ABA states the force majeure conditions due which the Respondent-1 would get an extension to complete the project. The relevant portion of clause 8.2 of the ABA, inter alia, states as under:
“8.2If the completion of the construction of the Residential Complex is delayed by reason of …………. Or if the non-delivery of possession is a result of any statute notice, order, rule, notification or ban imposed by the judiciary/government and/or authority, delay in completion of grant of completion certificate by the concerned authority……. company shall be entitled to a reasonable extension of time for offering delivery of possession of the said Apartment.”
In the instant case, the provisional allotment letter was issued on 27.08.2012 and ABA was signed on 28.08.2012. In terms of clause 8.1 of the ABA, the Respondent-1 undertook to complete the project by 31.03.2014 subject to a grace period of 6 (six) months i.e., up to 31.09.2014. The Respondent-1 have taken the plea that the delay in completing the project was due to ban imposed by the Hon’ble National Green Tribunal (NGT), New Delhi vide its order dated 10.11.2016 which was vacated on 17.11.2017. This was force majeure in terms of clause 8.2 of ABA.
We note that the project was to be completed in 2014 whereas the ban was imposed in the year 2016 i.e., 2 years after the due date of completion. We fail to understand as to why the Respondent-1 could not complete the project by the due date or even by 10.11.2016 and obtain the completion certificate.
The Respondent-1 have failed to explain the reason as to why they applied for completion certificate in 2017 instead of 2014, the year in which the project should have been completed.
Considering the order of Hon’ble NGT, New Delhi, we can consider and condone the delay due to ban but cannot overlook the delay for which Respondent-1 is responsible.
The Complainant expressed her intention to cancel the booking on 17.03.2017 through email to the Respondent-1 as there was an inordinate delay in the completion of the project. In 2016 as well the Complainant had sent various mails inquiring about the completion and possession of the apartment booked by her. The Respondent-1 never gave a satisfactory reply to her. Finally, on 26.08.2017, the Complainant asked the Respondents 1 to cancel the booking and refund the entire amount deposited by her with them.
It is a fact that Respondent-1 received Completion Certificate on 16.10.2017 and offered possession to the Complainant on 28.10.2017. We are also aware that Respondent-1 registered the project with RERA, NCT of Delhi as on-going project as per Registration Certificate dated 03.05.2018.
The RE (RD) Act, 2016 was enacted to induct professionalism and standardization in the real estate sector, thus paving way for its accelerated growth and investments in the long run. This Act is a special law enacted to address issues in the real estate sector. All disputes between home buyers/allottees and promoters/developers of a real estate project, covered under the Act, can be raised before concerned Real Estate Regulatory Authority (RERA).
The statement of objects and reasons of the RE (RD) Act, 2016 clearly states that it attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoter and purchaser, being transparency in contractual conditions, set minimum standards of accountability and establish a fast-track dispute resolution mechanism. Section 18 (1) of the Act deals with the situation if the promoter fails to complete or give possession either in terms of the agreement for sale or complete the project by the date specified therein etc. Under this section the allottee/ homebuyer holds an unqualified right to seek refund of the amount with interest at such rate as may be prescribed. It also clearly states that in case the allottee/ home buyer does not wish to withdraw from the project he shall be paid interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.
The text of section 18(1) of RE(RD) Act, 2016 is reproduced below for the sake of convenience:
“Section 18: - Return of amount and compensation
18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —
(a)in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b)due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,
he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.
Provided that where an allottee does not intend to withdraw from the project, he shall be paid by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.
(2)If the promoter fails to discharge any other obligations imposed on him under this Act or the rules or regulations made thereunder or in accordance with the terms and conditions of the agreement to sale, he shall be liable to pay such compensation to the allottees, in the manner as provided under this Act.”
In the present case, the Complainant wants to withdraw from the project and seek refund of the entire amount deposited by her with the Respondent-1.
The tripartite agreement entered into between the Complainant, Respondent-1 and Respondent-2 forms a contract. It has been specifically mentioned under Clause 8.1 of ABA that promoter binds itself to complete the project by 31.03.2014 subject to the grace period of 6 (six) months i.e., up to 31.09.2014.
Section 12 of the RE (RD) Act, 2016 casts duty upon the developer/promoter to provide correct and updated information to allottees regarding the current status of the project and the likely date by which the project will be completed. It reads as under:
Section 12: - Obligations of promoter regarding veracity of the advertisement or prospectus
“Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
We note that the Complainant had made a request through email for refund of money deposited by her on 17.03.2017 i.e. before the Act came into being stating “forwarding again email which never received reply from your end. I want to know what is the status of my booked flat, if not handing over then would like to cancel it.”
Subsequently, she visited the property to inspect and take the possession of flat in 2019 after which she complained of poor quality of construction. The Complainant again wrote an email to the Respondent-1 on 25.05.2019 wherein her intention to withdraw from the project was conveyed. The email sent read “Having given enough time and enough warnings and having received no proof from your side, in this deal. Since you have delayed handing over of the apartment beyond all reasonable limits, I am exercising RERA rules and Regulations”.
The argument of the Respondent-1 that the visit of the Complainant to the project in 2019 amounts to taking away her right to seek refund under section 18 of the Act is not tenable, as she had requested for refund much earlier on 17.03.2017 and she never stated subsequently that she was interested in taking possession and not refund.
The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors., Civil Appeal Nos. 6745-6749 of 2019).
In Emaar MGF Land Ltd. & ors. Vs. Amit Puri [ II (2015) CPJ 568 NC], the Hon’ble NCDRC has held that:
“after the promised date of delivery, it is the discretion of the Complainant whether he/she wants to accept the offer of possession, if any, or seek refund of amount paid with reasonable interest”
Since, the project was not complete as on 01.05.2017, the day the Act came into being, the adjudication of present complaint comes well within the purview of present Authority. Further, since the project was not completed by the Respondent-1 by due date, the Complainant has an absolute right to seek refund under the RE(RD) Act, 2016.
In this case, the Complainant has suffered agony and harassment, as a result of carelessness and inaction on the part of the developer i.e., Respondent-1. It is evident from various letters written by the Complainant to Respondent-1 that she is concerned about the timely handing over of the possession of the apartment to her.
As Respondent-1 could not complete the project in stipulated time adhering to the terms and conditions of the ABA, they cannot be forced to take possession of her apartment. Since, the Completion Certificate for the project was obtained on a later date from the date of demand of refund made by the Complainant, she is well within her rights to seek refund of the entire amount deposited by her with the Respondent-1.
The Authority holds that there was no reason for delay which can be attributed to ‘force majure’. The Respondent can’t be exempted from the liability towards the Complainant. Hence, issue no. i and ii are decided in the favour of the Complainant in CC no.19/2020.
The Authority would now analyse the last issue i.e. who should be liable to pay the amount of refund to Complainant Ms. Daphne Reita Rajan Sharma?
A perusal of the documents available on record show that Respondent-1 have received Rs. 1,42,39,088/- (Rupees One Crore Forty-Two Lakh Thirty-Nine Thousand Eighty-Eight only) from the Complainant by way of various transactions mentioned in para 6 before.
The Respondent-2, stated in their reply that by entering into Collaboration Agreement, they transferred all rights to Respondent-1 with respect to construction, development, advertising, sale of the units and to enter into ABA with the prospective buyers and that they do not have any liability towards the allottees who entered into agreement with Respondent-1 and as remain only a confirming party. It was also argued that they neither approached the Complainant to buy an apartment in the subject project nor they collected any money from her and therefore, cannot be held liable to refund of money deposited by the Complainant with the Respondent-1.
To understand the exact intentions of the parties, it is necessary to read few clauses of the said Collaboration Agreement dated 18.01.2010 entered into between Respondent-1 and Respondent-2 which are as follows:
“3. OBJECTIVE
3.1That the subject matter of this Agreement is collaboration between Uppal and Umang for the execution of the project by Umang on the Land admeasuring 21954.8, Delhi sq. mt. Near Dwarka Morh Metro Station, more particularly described in the Schedule C, and the sharing of the revenue realized from the sale of the Developed Saleable area (defined herein below) in the ratio as provided hereinafter in clause 5.1.1 of this Agreement…”
“5.1.1- In consideration of the contribution of the land by Uppal for execution of the project and Umang bearing the costs, expenses and responsibility of execution of the project and on simultaneous payments to Uppal by way of nonrefundable security deposit, a sum of Rs. 75,00,00,000/- (‘Security Deposit”) and discharge of their respective obligations by the parties under this agreement, the parties shall share the proceeds from the lease sale, and/or transfer of developed saleable area under the project, in the ratio mentioned herein below:
•Uppal: 15 %
•Umang: 85 %”
From the combined reading of the above clauses 3.1 and 5.1.1 of the Collaboration Agreement, it is clear that the execution of the subject project by Respondent-1 and Respondent-2 was jointly undertaken and revenue generated from the said project was or to be divided in the decided ratio.
Further, clause 6.8 of the Collaboration Agreement, reads as under:
“6.8Uppal agrees to give General Power of Attorney to Umang and/or its nominee authorizing Umang and its nominated representatives to sign, submit and follow up all applications, forms, affidavits, undertakings, guarantees, etc. whatever may be required for grant of sanction, water, sewerage and electricity connections or any other facility or amenity for and in connection with the development of the project.” and Clause 8.1 of the Collaboration Agreement states as under:
“8.1All the proceeds and receipts from sale of developed saleable area, under the project shall be deposited by Umang in a separate designated bank account designated as ‘Metro Park Project Income Account’.”
The above two clauses reveal that the Respondent-2 gave a general power of Attorney to the Respondent-1 authorizing them to act on their behalf for the construction and development of the subject project.
Clauses 8.6 and 9.1.2 of the Collaboration Agreement, provide:
“8.6Uppal shall execute such documents as are required by Umang for the purpose of entering into flat buyers’ agreement, sale agreements, sub-lease deed, conveyance deed and other requisite documents….
9.1.2Uppal agrees to indemnify Umang on account of any loss, claims, costs and damages (whether general, special, absolute, accrued, conditional or otherwise and whether or not resulting from third party claims) …”
From the bare reading of the above clauses only one conclusion can be drawn that the Respondent-2 have indemnified Respondent-1, in case of any loss accruing, inter alia, from third party claims.
We note that the clause 9.8 on severability reads as under:
“9.8 SEVERABILITY
Each and every obligation under this Agreement shall be treated as a separate obligation and shall be severally enforceable as such…”
From the above-mentioned clauses of the Collaboration Agreement entered between the Respondent-I and Respondent-2 it is abundantly clear that Respondent-2 not only gave Respondent-1 the land for development but specifically agreed to indemnify them in case of any loss or claims.
It is after the Collaboration Agreement dated 18.01.2010, that a tripartite agreement was entered into between the Respondent-1, the Respondent-2 and the Complainant on 28.08.2012. It is relevant to bear in mind that in the tripartite agreement, the Respondent-2 have signed as the confirming party. It is also noticed that the Complainant is put to notice of the Collaboration Agreement and there is reference of the Power of Attorney executed between the Respondent-1 and the Respondent-2.
It was argued by the Respondent-2 that through the Collaboration Agreement, they have not undertaken any liability qua the allottees/ flat buyers. It was specifically argued by the Respondent-2 that a perusal of the Collaboration Agreement will make it clear that they are only the confirming party to the extent that the land was leased out to them by DMRC and further sub-leased by them to the Respondent-1 for the construction and development of the subject project.
Now we address to the above contentions made by the Respondent- 2 that they are only the owners of the land and the Collaboration Agreement entered into between the Respondent-1 and the Respondent-2 has transferred the rights to sell, transfer and receive payments to Respondent-1 and therefore they cannot be held liable to refund any amount received by the Respondent-1.
It was vehemently argued that the Respondent-2 being only the confirming party cannot be held liable for the transactions done by the Respondent-1 in their own capacity. A perusal of record would reveal that the earnest money as well as the part payment towards the purchase of the abovementioned apartment by the Complainant were made to the Respondent-1. Therefore, in terms of ABA, which is a tripartite agreement, the Respondent-2 cannot be held liable for any refund to the Complainant.
But, the fact remains that the Respondent-2 agreed to indemnify the Respondent-1 in case of any loss occurred even towards the third party which in the present case is the Complainant who did not get the possession of the apartment booked by her due to inordinate delay by the Respondent-1 in completing the project and thereby causing harassment, mental agony and financial loss to the Complainant.
Since the Respondent-2 (the impleaded party in CC no. 19/2020) in terms of clause 9.1.2 of the Collaboration Agreement dated 18.01.2010 have undertaken to indemnify the Respondent-1 for any losses, claims etc. including third party claims, they cannot escape from its liability towards the Respondent-1 for compensating third party, who in this case is the Complainant. In this regard, reference can be made to case Kavi Ghei & Anr V. M/s Uppal Housing Pvt. Ltd. & Anr., EA/251/2019, wherein the Respondent-2 paid entire amount to an allottee of the same project in execution proceedings on 06.08.2021. Accordingly, the Respondent-1 and Respondents 2 are jointly and severally liable under section 18(1)(a) to refund the deposited amount to the Complainant.
The delay in giving the possession to the allottees cannot be compromised. The Complainant invested her hard-earned money in the project for flat on time but due to inaction of Respondent-1 she could not enjoy the benefit of the same.
The intention of the legislature behind the Act is that the builders must provide possession of the flat to allottee within prescribed time and this time line should not be delayed except for the reasons beyond the control of promoter. Every allottee makes investment in the property considering their need and resources available at a particular time expecting the property would be delivered in time, if possession is delayed it is quite possible that it may not serve the purpose for which the allottee made the investment, as perhaps in this case.
The Respondent-1 are thus responsible for violating the terms and conditions of the tripartite agreement.
In view of the above discussion, we have no hesitation in saying that Respondent-1 have failed to hand over the possession of the apartment to the Complainant as per the agreed terms and conditions of the tripartite agreement dated 27.08.2012.
Therefore, in CC no. 19/2020 titled Daphne Reita Ranjan Vs M/s Umang Realtech Pvt. Ltd. &Anr. we order as follows:
Both the Respondent-1 and Respondent-2 are jointly and severally liable under section 18(1)(a) and are directed to refund the entire amount deposited by Complainant Ms. Daphne Reita Rajan Sharma, i.e., Rs. 1,42,39,088/- (Rupees One Crore Forty-Two Lakh Thirty-Nine Thousand Eighty-Eight only) within 45 days of issuance of this order along with interest at the rate of 10% per annum i.e. (MCLR+2%) per annum from the date of payment of each sum until the date of its actual return. It is ordered accordingly.
The Complainant will be free to make an application before the Adjudicating Officer for seeking compensation for inconvenience and mental harassment caused by Respondent-1.
and
in CC no. 16/01/2022 titled M/s Umang Realtech Pvt. Ltd. & Anr. Versus Daphne Reita Ranjan Sharma, we order as follows:
As the Complainant M/s Umang Realtech Pvt. Ltd. could not complete the subject project in accordance with the terms and conditions of the ABA, the Respondent, Ms. Daphne Reita Rajan Sharma is within her unqualified right to withdraw from the project and seek refund of amount deposited with M/s Umang Realtech Private Limited with interest. Therefore, no direction can be given to the Respondent Ms. Daphne Reita Rajan Sharma, for taking possession of the flat/apartment. Accordingly, the case of the Complainant in this complaint is dismissed.
Both the complaints are disposed of accordingly.
File may be consigned to record room.