Judgment
Facts in Brief:
A complaint was filed in FORM ‘M’ on 09.01.2018 by Mr. Yogender Sharma (hereinafter referred as “Complainant”). The Complainant submitted that he approached M/s Uppal Housing Private Limited (hereinafter referred as “Respondents-1”) and M/s Umang Realtech Private Limited (hereinafter referred as “Respondents-2”) for booking of a two-bedroom apartment in the Respondents-1 project namely “Winter Hills”, Dwarka, Delhi.
The Complainant booked two BHK apartment admeasuring 1457 sq. ft. along with one reserved car parking at a total consideration of Rs. 1,14,77,365/- (Rupees One Crore Fourteen Lakh Seventy Seven Thousand Three Hundred and Sixty Five Only).
For the purpose of development of “Winter Hills” residential complex, a lease deed was executed on 19.05.2006 between Respondents-1 and Delhi Metro Rail Corporation, granting leasehold rights on plot of land admeasuring 21,954.8 sq. mtr. located at Dwarka Mor, MRTS station, Near Dwarka City, New Delhi.
Thereafter on 18.01.2010, Respondents-1 and Respondents-2 entered into a collaboration agreement as per which Respondents-2 became entitled to construct & develop the housing complex and also to market, book, sell, transfer the flats with leasehold rights in favour of prospective buyers.
In terms of the Collaboration Agreement, an “Apartment Buyer Agreement” was executed on 03.10.2012 between the Complainant and Respondents-2, for a two bedroom flat and for which the Complainant paid a sum of Rs.1,09,31,134/- (Rupees One Crore Nine Lakh Thirty One Thousand One Hundred and Thirty Four Only) to the Respondents-2. We note that the “Apartment Buyer Agreement” has been signed by both the Respondents.
The Complainant has sought following reliefs:
Punish the Respondents for non-adherence to section 3 of the RE (RD) Act, 20161 with respect to the project in question and impose a penalty of 10% of the cost of the project;
Punish the respondents in terms of Section 61 for violation of other provisions of the Act as the Respondents have failed to provide the information to the Complainant as mandated by the Act and penalize the Respondents to an extent of 5% of the cost of the project;
Impose heavy penalty upon the Respondents under section 38 of the Act for breach of obligation cast upon the Respondents under the Act;
Notices were issued to both the Respondents. Both the Respondents filed their replies on 20.02.2018 and 26.02.2018 respectively.
We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of Respondents are summarized as under:
The complaint is not tenable as there has been no delay in handing over the possession.
As per Clauses 8.1 and 8.2 of the “Apartment Buyers Agreement”, the Respondents-2 are entitled to a reasonable extension of time for completion of the project. On account of reasons such as “global recession”, “shortage of labour due to implementation of social schemes by National Rural Employment Guarantee Act”, “lack of adequate finances”, “demonetization policy”, which were beyond the control of the Respondents, the possession could not be handed over earlier.
Without prejudice to the aforementioned factors, the Respondents-2 is willing to offer to the Complainant penalty for delay in handing over possession in terms of Clause 8.6 of the Apartment Buyer Agreement.
Analysis and consideration:
It is relevant to note that Respondents-2, M/s Umang Realtech Private Limited made an application before South Delhi Municipal Corporation (SDMC) for the issuance of the Completion and Occupancy Certificate on 09.06.2017. The Completion and Occupancy Certificate was issued by SDMC on 16.10.2017. The Respondents-2 have submitted a copy of Completion and Occupancy Certificate dated 16.10.2017. This information was not disclosed by the Respondents-2 to the Authority. The Interim Regulator had granted registration to the project “Winter Hills, Dwarka Mor” promoted by Respondents and after considering their registration application 31.07.2017 on 01.05.2018 with a validity upto 30.09.2018.
The fulcrum of the dispute for consideration before us is whether the Respondents by not registering their project under the RE (RD) Act, 2016 have violated the provisions of the said Act or not. Both the parties as well as a few other allottees have been at loggerheads and numerous civil disputes have been adjudged and pending between them before different judicial forums. For example, as could be seen from the records, Writ Petition (Civil) No. 1306/2018 titled Kamal Mangla vs South Delhi Municipal Corporation and Ors whereby the “Occupancy Certificate” dated 16.10.2017 issued by SDMC for this project is challenged and is pending before the Hon’ble High Court of Delhi.
Voluminous records have been produced before us by both the parties showing various directions, orders, observation passed by various judicial forums and pendency of disputes before them.
Having perused the material available on record, we are of the considered view that it would in the interest of both the parties that we limit ourselves to the reliefs sought in the complaint filed under Section 31 of the Act and refrain from any other issue.
As per the prayers in the complaint extracted at para 6 above, the main grievance of the Complainant is non-adherence to section 3 of the RE (RD)Act, 2016 by the Respondents, punish the Respondents for violation of other provisions of the Act under Sections 61 and 38 of the RE(RD) Act.
Section 3 (1) of the RE (RD) Act, 2016 provides that no promoter shall advertise, market, book, sell or offer for sale, or invite persons to purchase in any manner any plot, apartment or building, as the case may be, in any real estate project or part of it, in any planning area, without registering the real estate project with the Real Estate Regulatory Authority established under this Act. Further, as per the first proviso, projects that are ongoing on the date of commencement of this Act and for which the completion certificate has not been issued, the promoter shall make an application to the Authority for registration of the said project within a period of three months from the date of commencement of this Act.
The question that the RE (RD), Act 2016 is retroactive in its operation particularly with reference to the ongoing projects has been answered by the Hon’ble Supreme Court of India in its judgment Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors., LL 2021 SC 641. Thus, there is no doubt that the RE (RD) Act, 2016 will apply retrospectively to the on-going projects once they are registered.
As could be seen from record available in the office, the Respondents-2 had applied for registration of the project on 31.07.2017 with registration fee of Rs. 2,19,550/- (Rupees Two Lakh Nineteen Thousand Five Hundred and Fifty Only) was deposited in favour of Real Estate Regulatory Authority, NCT Delhi. The registration for the subject project was issued on 01.05.2018 with a validity upto 30.09.2018 as stated earlier.
Coming to the pleadings in the case, although, it is the contention of the Complainants that the Respondents have violated the provisions of Section 3 of the RE(RD)Act, 2016, no material/evidence or document has been placed on record to show or corroborate their allegation or substantiate the violation of provisions of Section 3 of the RE(RD)Act, 2016 as well as the other provisions of the RE(RD)Act, 2016.
Rather on facts, the case of the Complainant is that “Apartment Buyer Agreement” was executed on 03.10.2012 and the final call letter was issued on 28.10.2017 which allegedly amounts to delay in possession, but unfortunately, no relief qua the delay in possession has been sought before us.
We also take note of the fact that two similar complaints have been decided by the Interim Regulator vide Orders dated 20.04.2018 and 19.04.2018 in Complaint Case No.13/2017 and Complaint Case No.07/2017 respectively. Same view has been taken by the Interim Regulator in both abovementioned cases. The operative part of the judgments are reproduced below for ready reference:
Complaint Case No.07/2017:
“31.The prayer of the complainant to direct the respondent to furnish the details of expenses is not maintainable. After going through the entire records including pleadings, agreement, correspondence between the parties and joint inspection dated 27/02/2018, it is clear beyond doubt that the respondent has already obtained the completion certificate and therefore nothing survives in the present complaint. The complaint is accordingly dismissed.”
Complaint Case No.13/2017
“36.The prayer of the complainant to direct the respondent to furnish the details of expenses is not maintainable. After going through the entire records including pleadings, agreement, correspondence between the parties and it is clear beyond doubt that the respondent has already obtained the completion certificate and therefore nothing survives in the present complaint. The complaint is accordingly dismissed.”
From the facts produced before us it is clear that the Respondents-2 had already applied for registration of said project on 31.07.2017 and also obtained the Occupancy Certificate on 16.10.2017. Accordingly, the non-compliance of the mandate contained in Section 3 of the RE(RD)Act, 2016 on the part of the Respondents is not established. Therefore, we do not find any cogent reasons to entertain the present complaint. Thus, the complaint being untenable, is accordingly dismissed.
No orders as to costs.