A complaint was filed in Form ‘M’ on 03.12.2021 by Mr. WG CDR Adarsh Vir (hereinafter referred to as ‘Complainant’) stating that in the year 2015 he approached “M/s Antriksh Society” (hereinafter referred to as ‘Respondents’) for booking an apartment in their project “Victorian County” (hereinafter referred to as ‘project’) in L-Zone, Dwarka, Delhi.
The Respondents vide Welcome Letter dated 12.01.2015 allotted him a 3 BHK admeasuring 1300 sq. ft. built-up area, 4th floor, Tower-2 in their proposed project. The Respondents have acknowledged receipt of Rs.12,11,100/- (Rupees Twelve Lakh Eleven Thousand One Hundred only) deposited by the Complainant.
The Complainant submitted that the Respondents have failed to start the construction of the project and deliver the possession of the said flat even after lapse of more than 6 years from the date of booking. Therefore, he seeks refund of amount deposited by him with the Respondents along with interest.
A preliminary hearing in the case was held on 01.02.2022 and a notice to the Respondents was issued on the same date.
The matter was heard on 30.03.2022, 09.06.2022, 07.09.2022, 28.10.2022 and 24.01.2023. The Respondents filed their reply on 23.01.2023.
We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of the Respondents are summarized as under:
The Respondents have been in the business of the construction and development for more than a decade and have successfully delivered projects in the NCR region and are developing many projects which are near completion in accordance with law.
In the year 2015, the Respondents launched project namely ‘Victorian County’. The Complainant approached the Respondents for booking a residential apartment in the said project and accordingly he signed and executed booking application form out of his own free will.
The Respondents had every intention to develop the said project but owing to the government policies and procedural and administrative delays beyond the control of the Respondents, the Respondents could not obtain the Land Transfer Certificate, which is a prerequisite for developing the project. As soon as the Respondents realized that the project is delayed, they gave an option to its existing investors to either stay invested and await the requisite clearances from the competent authorities or, in an alternative opt for a refund. The Complainant opted for refund out of his own free will.
The Respondents are ready to refund the entire principal amount of Rs.12,11,100/- (Rupees Twelve Lakh Eleven Thousand One Hundred only) to the Complainant.
Analysis and Consideration:
A perusal of the documents available on record shows that the Respondents have issued five receipts dated 12.01.2015 and 17.04.2015 acknowledging deposits of Rs. 51,100/-, Rs. 2,98,000/-, Rs. 3,00,000/-, Rs. 3,00,000/- and Rs. 2,98,000/-respectively. Hence, payment of Rs.12,11,100/- (Rupees Twelve Lakh Eleven Thousand One Hundred only) by the Complainant to the Respondents is a recorded fact.
A perusal of record shows that the Respondent Society was registered under the Societies Registration Act, 1860 vide registration no. S/RS/SW/1171/2014 issued on 11.06.2014 by the Registrar of Societies, District South West, Govt. of NCT of Delhi and section 20 of the said Act does not permit such societies to undertake “housing” as an activity. Section 20 of the Societies Registration Act, 1860 is reproduced hereunder as:
20.“To what societies Act applies.—The following societies may be registered under this Act:— Charitable societies, the military orphan funds or societies established at the several presidencies of India, societies established for the promotion of science, literature, or the fine arts for instruction, the diffusion of useful knowledge, 1[the diffusion of political education], the foundation or maintenance of libraries or reading-rooms for general use among the members or open to the public, or public museums and galleries of paintings and other works of art, collections of natural history, mechanical and philosophical inventions, instruments, or designs.
State Amendments:
*Section 20 (Delhi) in The Societies Registration Act, 1860
“ —In section 20, for the words “promotion of science, literature, or the fine arts”, substitute the words “promotion of social welfare, activities conducive to the promotion and improvement of the natural environment (including forests, rivers and wild life), compassion for living creatures, literature, science, sports, games or the fine arts”. [Vide Act 26 of 1983, sec. 2(c) (w.r.e.f. 22-6-1983).]”
As per Section 2 (zk), a ‘promoter’ under the Real Estate (Regulation and Development) Act, 2016 [hereinafter referred as “RE (RD) Act, 2016 or Act”] means ;
“an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or”
In view of para 8, the Respondents, a society registered under Society Registration Act, 1860, though not authorized to undertake “housing” activity; advertised membership, misled the people, made members for their housing project and collected monies from them, would come under the purview of RE (RD) Act, 2016. The Respondents by collecting the monies in the name of housing project have, on the face of it, committed a fraud on the members and general public.
The Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as “RE (RD) Act, 2016”) was enacted to induct professionalism and standardization in the real estate sector, thus paving way for accelerated growth and investments in the long run. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. All dispute between homebuyers/allottees and promoters/developers relating to any real estate project, covered under the RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars the jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which this Authority is empowered by or under the Act to determine. Moreover, Section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.
The statement of objects and reasons of RE (RD) Act, 2016 attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoters and purchasers, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.
An allottee/home buyer can seek refund of amount invested with promoter under section 18 of RE (RD) Act, 2016, if the promoter fails to complete project by the date specified in agreement to sale with interest and compensation and also under section 12 of RE (RD) Act, 2016 if he/she was misled by any information furnished by promoter with regard to the project either through advertisement or otherwise.
In the present complaint, the Complainant intends to withdraw from the said project on the ground of delay and is seeking refund of the amount paid to Respondents in respect of subject unit under section 18(1) of the RE (RD) Act, 2016 which reads as under:
“Section 18. Return of amount and compensation. -
18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —
(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”
Section 12 of the RE (RD) Act, 2016 casts a duty upon the promoter to provide correct and updated information to allottees regarding the project, which reads as under:
“Section 12. Obligations of promoter regarding veracity of the advertisement or prospectus.-
Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
The Respondents, in complete disregard to their duties, not only failed to furnish correct information to the Complainant but also misled him by concealing information that their society cannot undertake housing activity. The Guidelines and Procedure for Registration of Societies under the Societies Registration Act, 1860 of the Govt. of NCT of Delhi, have specified the types of societies, which can be registered under the Act of 1860. As per these guidelines, no housing society can be registered under the Act of 1860. So by undertaking housing as an activity the Respondents have cheated the members by providing wrong interpretation.
On perusal of the documents on record and submissions made by the parties, the Authority is of view that the Respondents are in contravention of the sections 18 and 12 of RE (RD) Act, 2016. And, therefore, the Complainant is entitled to get the refund of the amount paid by him alongwith interest at prescribed rate @ 10% p.a. (i.e., MCLR plus 2%) as per provisions of sections 18 and 12 of RE (RD) Act, 2016 read with rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016.
The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors. LL 2021 SC 641).
In the light of aforesaid, we direct the Respondents, M/s Antrix Society to refund the entire principal amount, Rs.12,11,100/- (Rupees Twelve Lakh Eleven Thousand One Hundred only) to the Complainant within 45 days of issuance of this order along with interest at the rate of 10% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.
The case is disposed of accordingly.
No orders as to costs.