Judgment
A complaint was filed in FORM ‘M’ on 04.02.2025 by Mr. Pratik Kumar (hereinafter referred to as “Complainant”) under Section 31 r/w Section 18 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter, referred to as ‘RE (RD) Act, 2016’ or ‘The Act’) stating that he booked a 3BHK apartment in 2018 in the housing project, ‘Delhi Gate’ (hereinafter referred to as ‘Project’) promoted by Delhi Infratech Limited (hereinafter referred to as “Respondents” or “Respondent Company”).
The Respondents through their Memorandum of Understanding dated 21.10.2018 confirmed the membership of the Complainant in their proposed “Delhi Gate” project.
The Complainant submitted that he paid a total of ₹ 10,81,500/- (Rupees Ten Lacs Eighty-One Thousand Five Hundred Only) to the Respondents in many instalments for the subject flat and is claiming a refund for the same amount due to delay in implementation of the project.
A preliminary hearing in the case was held on 28.04.2025 and a notice to the Respondents was issued on 23.06.2025 via registered post and on 24.06.2025 via email.
In spite of service of various notices, the Respondents did not file reply to the complaint. Also, no one appeared for the Respondents during the hearings held on various dates. In light of the Respondent Company’s repeated non-appearance on various dates, the Authority, by order dated 28.01.2026, chose to proceed ex-parte.
I have perused the documents available on record and heard the arguments of the Ld. Counsel for the Complainant.
Analysis and Consideration:
A perusal of the documents available on record shows that two receipts were issued by the Respondents to the Complainant as follows:
| S.No. | Date | Amount Paid |
| 1. | 01.11.2019 | ₹ 5,14,750/- |
| 2. | 10.09.2018 | ₹ 52,000/- |
| TOTAL | ₹ 5,66,750/- | |
Accordingly, it is an established fact that the Complainant paid ₹ 5,66,750/- to the Respondents. Additionally, through the Memorandum of Understanding dated 21.10.2018, the Respondents confirmed receiving a cash payment of ₹ 5,14,750/- from the Complainant. Consequently, the total sum remitted by the Complainant to the Respondents amounts to ₹ 10,81,500/- (Rupees Ten Lacs Eighty-One Thousand Five Hundred Only).
The Complainant placed on record copies of Memorandum of Understanding and payment receipts which clearly show that the Respondents collected money for constructing flats in their project “Delhi Gate”.
The RE (RD) Act, 2016 has been enacted to induce professionalism and standardization in the real estate sector, paving the way for catalyzing investments and accelerating growth of the sector in the long run. To achieve these objectives, the Act created a Regulatory Authority to supervise the conception, initiation and completion of a real estate project. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. Therefore, all disputes between homebuyers/allottees and promoters/developers relating to any real estate project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered under the Act to determine. Moreover, Section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.
An exhaustive definition of "promoter" is provided under Section 2(zk) of the Real Estate (Regulation and Development) Act, 2016 which is reproduced below:
2.(zk) “promoter” means, -
i)a person who constructs or causes to be constructed an independent building or a building consisting of apartments, or converts an existing building or a part thereof into apartments, for the purpose of selling all or some of the apartments to other persons and includes his assignees; or
ii) a person who develops land into a project, whether or not the person also constructs structures on any of the plots, for the purpose of selling to other persons all or some of the plots in the said project, whether with or without structures thereon; or
iii) any development authority or any other public body in respect of allottees of-
(a)buildings or apartments, as the case may be, constructed by such authority or body on lands owned by them or placed at their disposal by the Government; or
(b)plots owned by such authority or body or placed at their disposal by the Government, for the purpose of selling all or some of the apartments or plots; or
iv) an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its members or in respect of the allottees of such apartments or buildings; or
v)any other person who acts himself as a builder, colonizer, contractor, developer, estate developer or by any other name or claims to be acting as the holder of a power of attorney from the owner of the land on which the building or apartment is constructed or plot is developed for sale; or
vi) such other person who constructs any building or apartment for sale to the general public.
Explanation. - For the purposes of this clause, where the person who constructs or converts a building into apartments or develops a plot for sale and the persons who sells apartments or plots are different persons, both of them shall be deemed to be the promoters and shall be jointly liable as such for the functions and responsibilities specified, under this Act or the rules and regulations made thereunder;
The payment receipts issued by the Respondents to the Complainant clearly mention about the project “Delhi Gate” as promoted by “M/s Delhi Infrastructure Limited”. The aim and objective of the Respondents was to raise a housing project and the Complainant invested money to purchase a flat in the said housing project. The Respondents, thus, fall within the definition of “promoter” as defined in the RE (RD) Act, 2016. Therefore, the Authority has jurisdiction to adjudicate the matter and pass appropriate orders on the complaint.
It must be appreciated that the statement of objects and reasons of RE(RD) Act, 2016 clearly states that the Act attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It also seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.
In the present complaint, the Complainant intends to withdraw from the said project and is seeking refund of the amount paid to Respondents in respect of subject unit for delay under Section 18(1) on account of delay and misrepresentation of facts under Section 12 of the Act which read as under:
“Section 18. Return of amount and compensation. -
18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building,
(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”
“Section 12. Obligations of the promoter regarding veracity of the advertisement or prospectus. -
Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act: Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
Further, the Respondents collected monies from the Complainant for the flat in their proposed project “Delhi Gate” after 01.05.2017, i.e. the day RE(RD) Act, 2016 came into force, without registering the project with RERA, Delhi under Section 3 of RE (RD) Act, 2016. Accordingly, the office is directed to issue a show cause notice to the Respondents to explain why penal action should not be initiated under Section 59 of the RE (RD) Act, 2016 for this statutory violation.
The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. The legislature has taken a conscious decision to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authority has exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Limited Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Limited v. State of UP And Ors. LL 2021 SC 641).
On perusal of the documents on record and submissions made by the Complainant, I am of the view that the Respondents are in contravention of Sections 18 and 12 of RE (RD) Act, 2016 and as such, the Complainant is entitled to get the refund of the amount paid by him along with the interest at prescribed rate @ 10.75% p.a. (i.e., MCLR plus 2%) as per provisions of Section 18 and 12 of RE (RD) Act, 2016 read with Rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016.
In the light of the aforesaid, I consider it appropriate to direct the Respondents, i.e. ‘Delhi Infratech Limited’ to refund the entire amount of ₹ 10,81,500/- (Rupees Ten Lacs Eighty-One Thousand Five Hundred Only) to the Complainant, i.e. Mr. Pratik Kumar within 45 days of issuance of this order along with interest at the rate of 10.75% per annum (i.e., MCLR+2%) from the date of payment of each sum until the date of its actual return.
The case is disposed of accordingly.
No orders as to costs.