Tribunals and CommissionsDivision Bench(2024) 07 RERA CK 2866

Mr. Pankaj Kumar vs M/s Delhi Infratech Ltd.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 11 July 2024

HON’BLE JUDGES
Ajay Kumar Kuhar, Member · Devesh Singh, Member
RESULT
Disposed Of
CASE NUMBER
Com/04/04/2023

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

38 paragraphs · 1,973 words
1.

A complaint was filed in FORM ‘M’ on 20.04.2023 by Mr. Pankaj Kumar (hereinafter referred to as “Complainant”) under Section 31 r/w Section 18 of RE (RD) Act, 2016 stating that he booked a flat in a housing project “Delhi Gate” promoted by M/s Delhi Infratech Ltd. (hereinafter referred to as “Respondents”) and paid Rs. 14,22,095/- (Rupees Fourteen Lakhs Twenty Two Thousand and Ninety Five Only) in the year 2016 on different dates towards plot purchase for the housing project to the Respondents.

2.

The Complainant submitted that no progress has been made in the project since 2016 by the Respondents till date, and, therefore, the Complainant wants to withdraw from the project and seek refund of amount deposited with the Respondents along with interest.

3.

A preliminary hearing in the case was held on 29.05.2023. Notice to the Respondents was issued on various dates. Notice was also served through Email and Registered Post.

4.

The matter was subsequently heard on 08.08.2023, 10.10.2023, 18.01.2024 and 02.04.2024. Inspite of service of notice, the Respondents did not file reply to the complaint. Also no one appeared for the Respondents during the hearings held on various dates. Therefore, vide order dated 18.01.2024, the Authority decided to proceed ex-parte due to repeated absence of the Respondents on various dates.

5.

We have perused the documents available on records and heard the arguments of the Complainant.

Analysis and Consideration:

6.

A perusal of the documents available on record shows that five receipts were issued by the Respondents dated 02.02.2016, 17.03.2016 and 29.06.2016 acknowledging deposits of Rs. 4,25,000/-, Rs. 1,25,000/-, Rs. 80,523/-, Rs. 80,522/- and Rs. 7,11,050/- respectively. Hence, a total payment of Rs. 14,22,095/- (Rupees Fourteen Lakhs Twenty-Two Thousand and Ninety-Five Only) by the Complainant to the Respondents is a recorded fact.

7.

The Complainant asserts that a Memorandum of Understanding (MoU) dated 21.07.2016 was executed between the Complainant and the Respondent. According to Clause 5 of this MoU, the Respondent Company issued a post-dated cheque bearing number 307915, dated 20.07.2016 for Rs. 20,22,095 (Twenty Lakhs Twenty-Two Thousand Ninety-Five only). This amount was agreed upon in lieu of the Complainant's investment of Rs. 14,22,095 (Fourteen Lakhs Twenty-Two Thousand and Ninety-Five only). Consequently, the Complainant is seeking a refund of Rs. 20,22,095 (Twenty Lakhs Twenty-Two Thousand Ninety-Five only) as stipulated in the MoU.

8.

The RE (RD) Act, 2016 has been enacted to induct professionalism and standardisation in the real estate sector, paving the way for catalysing investments and accelerating growth of sector in the long run. To achieve these objectives, the Act created a Regulatory Authority to supervise the conception, initiation and completion of a Real Estate Project. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. All disputes between homebuyers/allottees and promoters/developers relating to any Real Estate Project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered under the Act to determine. Moreover, section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.

9.. An exhaustive definition of "promoter" is provided under section 2(zk) of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as “RE (RD) Act, 2016 or Act”) which is reproduced below:

“2.

(zk) “promoter” means,-

i)

a person who constructs or causes to be constructed an independent building or a building consisting of apartments, or converts an existing building or a part thereof into apartments, for the purpose of selling all or some of the apartments to other persons and includes his assignees; or

ii) a person who develops land into a project, whether or not the person also constructs structures on any of the plots, for the purpose of selling to other persons all or some of the plots in the said project, whether with or without structures thereon; or

iii) any development authority or any other public body in respect of allottees of-

(a)

buildings or apartments, as the case may be, constructed by such authority or body on lands owned by them or placed at their disposal by the Government; or

(b)

plots owned by such authority or body or placed at their disposal by the Government, for the purpose of selling all or some of the apartments or plots; or

iv) an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or

v)

any other person who acts himself as a builder, coloniser, contractor, developer, estate developer or by any other name or claims to be acting as the holder of a power of attorney from the owner of the land on which the building or apartment is constructed or plot is developed for sale; or

vi) such other person who constructs any building or apartment for sale to the general public.

Explanation.- For the purposes of this clause, where the person who constructs or converts a building into apartments or develops a plot for sale and the persons who sells apartments or plots are different persons, both of them shall be deemed to be the promoters and shall be jointly liable as such for the functions and responsibilities specified, under this Act or the rules and regulations made thereunder;”

10.

The Respondents collected money for purchase of land for the housing project. The Agreement-cum-Memorandum of Understanding signed between the Respondents and the Complainant clearly mention that the project “Delhi Gate” is promoted by “M/s Delhi Infratech Ltd”. The aim and objective of the Respondents, thus, was to raise a housing project and the Complainant invested money to purchase a flat in the said housing project. The Respondents fall within the definition of “promoter” as defined in the RE (RD) Act, 2016. Therefore, the Authority has jurisdiction to adjudicate the matter and pass appropriate orders on the complaint.

11.. The statement of objects and reasons of the RE (RD) Act, 2016 attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoters and purchasers, enhance transparency of contractual conditions, set minimum standards of accountability and establish a fast-track dispute resolution mechanism.

12.

Under section 18 of RE (RD) Act, 2016, an allottee/house buyer can seek refund of amount invested/deposited with the promoter, along with interest and compensation, if the promoter fails to complete the project by the date specified in Agreement to Sale, and also under section 12 of RE (RD) Act, 2016, if he/she was misled by any information furnished by the promoter, with regard to the project, either through advertisement or otherwise.

13.

In the present complaint, the Complainant intends to withdraw from the project on the ground of delay and are seeking refund of the amount paid to the Respondents in respect of the unit under section 18(1) of the RE (RD) Act, 2016 which reads as under:

“Section 18. Return of amount and compensation: -

18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —

(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or

(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”

14.

As stated earlier, section 12 of the RE (RD) Act, 2016 casts a duty upon the promoter to provide correct and updated information to allottees regarding the project. It reads as under:

“Section 12. Obligations of promoter regarding veracity of the advertisement or prospectus:-

Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:

Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”

15.

The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. Therefore, if the Complainant wishes to withdraw from the project, the Respondents do not have any legal or moral authority to keep money deposited by the Complainant. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount deposited alongwith interest to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors. LL 2021 SC 641).

16.

Based on the provisions outlined in Section 18, the Authority's jurisdiction is limited to ordering the return of funds received by the promoter, along with prescribed interest. The enforcement of other contractual obligations falls outside the purview of the Authority. It is the case of the complainant that they have not received the amount as per the Memorandum of Understanding (MOU) executed between the Complainant and the Respondent on 21.07.2016. In our considered view the remedy for breach of contractual obligation would lie in Civil Courts. Section 18 and section 12 of the RE(RD) Act, 2016 provide for refund of principal amount only along with interest.

17.

On perusal of the documents on record and submissions made by the Complainant, the Authority is of view that the Respondents are in contravention of the sections 18 and 12 of RE (RD) Act, 2016. As such, the Complainant is entitled to get the refund of the amount paid by him alongwith interest at prescribed rate @ 10.75% p.a. (i.e., MCLR plus 2%) as per provisions of sections 18 and 12 of RE (RD) Act, 2016 read with rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016.

18.

In the light of the aforesaid, we direct the Respondents, M/s Delhi Infratech Ltd. to refund the principle amount Rs. 14,22,095/- (Rupees Fourteen Lakhs Twenty-Two Thousand and Ninety-Five Only), deposited with the Respondents, to the Complainant, Mr. Pankaj Kumar, within 45 days of issuance of this order along with interest at the rate of 10.75% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.

19.

The case is disposed of accordingly.

20.

No order as to costs.