A complaint was filed in FORM ‘M’ on 31.01.2025 by Mr. Harvinder Singh (hereinafter referred to as “Complainant” or “Allottee”) under Section 31 r/w Section 18 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter, referred to as ‘RE (RD) Act, 2016’ or ‘The Act’) stating that he booked a Commercial Unit No. F11-F in the project named "Devika Sadar" (hereinafter referred to as ‘Project’) located at Qutub Road, Delhi. The project is registered with this Authority under Registration No. DLRERA2021P0001.
The Complainant entered into an Agreement for Sale on 21.05.2022. This was a tripartite arrangement between the Complainant; M/s Devika Universal Land Private Limited (hereinafter referred to as “Company” or “Respondents 1”) and M/s Hiptage Infrastructure Private Limited (hereinafter referred to as “Promoter” or “Respondents 2”).
The Respondents 1 through their payment receipt dated 18.05.2022 confirmed the receipt of ₹ 4,00,000/- for the said unit.
The Complainant submitted that he paid a total sum of ₹ 16,00,000/- (Rupees Sixteen Lacs only) to the Respondents in many instalments for the subject flat and have claimed refund for the same amount due to delay in implementation of the project. He annexed a document signed and stamped by the Respondents 1, confirming the payment of ₹ 16,00,000/- (Rupees Sixteen Lacs Only).
As per Clause 7.6 of the tripartite Agreement, the virtual possession of the unit was promised by 31.03.2023. The grievance of the Complainant is that even after more than 1.5 years of the promised date, the project is nowhere near completion. The Complainant has further alleged that both the Respondents have been non-responsive to his repeated follow-ups and emails.
A preliminary hearing in the case was held on 24.03.2025. Notices to both the Respondents were issued on 17.04.2025 via registered post as well as via email.
Ld. Counsel for Complainant stated that her clients’ claim is genuine, although, an amount of ₹ 4,03,200/- (Rupees Four Lacs Three Thousand Two Hundred Only) has only been admitted in the tripartite agreement dated 21.05.2022 by the Respondents.
In spite of service of various notices, the Respondents 1 neither filed reply to the complaint nor appeared before this Authority on various dates of hearing. In light of the repeated non-appearances on various dates, the Authority, by order dated 19.11.2025, chose to proceed ex-parte against Respondents 1.
For the sake of convenience, the arguments and submissions made on behalf of the Respondents 2 are summarized as under:
Respondents 2 completed the project construction and obtained Completion cum Occupation Certificate from the competent authority on 24.05.2023.
They fulfilled their contractual obligations by handing over physical possession of the unit to Respondents 1 on 5.12.2022, for fit-outs and leasing.
There is no privity of contract between the Complainant and Respondents 2. The Complainant has paid no consideration of any kind to them and all payments have been made in favor of Respondents 1.
Under the Agreement dated 06.01.2022, Respondents 1 was granted independent rights and sole discretion to sell, allot, or transfer units within its allocated carpet area to third parties. The agreement between Respondents 1 and the Complainant is a distinct contract, and its obligations cannot be attributed to them.
Respondents 1 is contractually bound to keep them indemnified against all claims, losses, or demands raised by any third party to whom Respondents 1 sold or allotted a unit. They maintain that they cannot be held liable for any dispute arising from the independent dealings between Respondents 1 and the Complainant.
We have perused the documents available on record and heard the arguments of Ld. Counsel for both the parties.
Analysis and Consideration:
A perusal of the documents available on record show that only one receipt was issued by the Respondents 1 to the Complainant as follows:
| S.No. | Date | Amount Paid |
| 1. | 18.05.2022 | ₹ 4,00,000/- |
| TOTAL | ₹ 4,00,000/- | |
However, it is also seen that Respondents 1 admitted a payment of ₹ 16,00,000/-(Rupees Sixteen Lacs Only) by the Complainant in Annexure ‘A’ to the tripartite agreement dated 21.05.2022. Hence, we consider that payment of ₹ 16,00,000/-(Rupees Sixteen Lacs Only) by the Complainant to the Respondents as recorded fact.
The RE (RD) Act, 2016 has been enacted to induce professionalism and standardization in the real estate sector, paving the way for catalyzing investments and accelerating growth of the sector in the long run. To achieve these objectives, the Act created a Regulatory Authority to supervise the conception, initiation and completion of a real estate project. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. Therefore, all disputes between homebuyers/allottees and promoters/developers relating to any real estate project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered under the Act to determine. Moreover, Section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.
We note that paragraphs 67, 68, and 69 of this Authority’s earlier order dated 01.08.2024, in the matter of ‘Suo-Moto v. M/s Hiptage Infrastructure Private Limited’, read as follows:
"67.The perusal of the Agreement reveals that all the responsibilities under the Agreement were assigned to, and lie with, the Promoter M/s Hiptage Infrastructure Pvt. Ltd. For example, it was responsibility of the Promoter M/s Hiptage Infrastructure Pvt. Ltd. to intimate to the Allottee the amount payable and provide the details of taxes paid, or demanded, along with Acts/Rules/Notifications. (Term 1.3 (iii) of the Agreement). Total price for the unit shall be payable as per payment plan directly to the Promoter (Point 2 of the MoU with third parties). The Promoter has the powers to allow early payment of instalments (Term 1.6). The Promoter is responsible for not making any addition and alterations in the sanctioned plans, layout plans and specifications except minor changes or alterations as may be necessary (Term 1.7). The Promoter is responsible to pay all outgoings before transferring the possession of the unit to the Allottee(s) (Term 1.12). The Allottee was required to make payments on demand by the Promoter (Term 1.13). The Promoter was responsible to offer possession of the unit on or before a specified date (Clause 7.1). The Promoter shall offer the possession of the unit to the Allottee in terms of the Agreement (Clause 7.2). The Promoter shall compensate the Allottee(s) in case of any loss caused due to defective title of land (Clause 7.3). The Promoter shall be responsible for maintenance of the unit (Clause 7.4). The Promoter shall give the title of the unit (Clause 7.6). The Promoter shall be responsible for all defects in construction for a period of five years (Clause 7.8).
68.It is thus, obvious that even though M/s Hiptage Infrastructure Pvt. Ltd. had allotted the shops to DULPL, they continued to be the 'Promoter' for the subsequent allottees and entered into fresh Agreement for Sale with the subsequent/new allottees as the 'Promoter'. DULPL only became the co-signatory to said Agreement as the 'Company'.
69.It may, therefore, be concluded that M/s Hiptage Infrastructure Pvt. Ltd. is the promoter of the real estate project 'Devika Sadar' and is responsible for all obligations and responsibilities as a 'Promoter' under the RE(RD) Act, 2016.”
A review of the findings in the aforementioned Order dated 01.08.2024 clarifies that M/s Hiptage Infrastructure Pvt. Ltd. (Respondents 2) maintains the definitive status of a ‘Promoter’ for the real estate project 'Devika Sadar.' The Authority, after examining the distribution of responsibilities, including the collection of payments, maintenance of sanctioned plans, and the duty to deliver possession has unequivocally held that the Respondent is the primary entity responsible for all statutory and contractual obligations. Consequently, M/s Hiptage Infrastructure Pvt. Ltd. remains liable for all financial discharges and liabilities arising under the RE(RD) Act, 2016.
An exhaustive definition of "promoter" is provided under Section 2(zk) of the Real Estate (Regulation and Development) Act, 2016 which is reproduced below:
2.(zk) “promoter” means, -
i)a person who constructs or causes to be constructed an independent building or a building consisting of apartments, or converts an existing building or a part thereof into apartments, for the purpose of selling all or some of the apartments to other persons and includes his assignees; or
ii) a person who develops land into a project, whether or not the person also constructs structures on any of the plots, for the purpose of selling to other persons all or some of the plots in the said project, whether with or without structures thereon; or
iii) any development authority or any other public body in respect of allottees of-
(a)buildings or apartments, as the case may be, constructed by such authority or body on lands owned by them or placed at their disposal by the Government; or
(b)plots owned by such authority or body or placed at their disposal by the Government, for the purpose of selling all or some of the apartments or plots; or
iv) an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its members or in respect of the allottees of such apartments or buildings; or
v)any other person who acts himself as a builder, colonizer, contractor, developer, estate developer or by any other name or claims to be acting as the holder of a power of attorney from the owner of the land on which the building or apartment is constructed or plot is developed for sale; or
vi) such other person who constructs any building or apartment for sale to the general public.
Explanation. - For the purposes of this clause, where the person who constructs or converts a building into apartments or develops a plot for sale and the persons who sells apartments or plots are different persons, both of them shall be deemed to be the promoters and shall be jointly liable as such for the functions and responsibilities specified, under this Act or the rules and regulations made thereunder;
A conjunctive reading of Section 2(zk) of the RE(RD) Act, 2016, along with its Explanation, reveals the legislature's intent to broaden the scope of accountability. The statute explicitly provides that where the entity responsible for construction or development and the entity engaged in the sale of apartments are distinct persons, both shall be 'deemed' to be promoters and held jointly liable. In the present matter, M/s Devika Universal Land Private Limited (Respondents 1) performed the functions of a selling unit and facilitating the transactions. Consequently, by operation of law, Respondents 1 falls squarely within this expanded definition and cannot divest itself of the joint and several liabilities shared with the developer.
Upon reviewing the tripartite Agreement dated 21.05.2022, it is observed that:
M/s Hiptage Infrastructure Private Limited is the Special Purpose Vehicle and the registered "Promoter" of the project.
M/s Devika Universal Land Private Limited is the "Company" that was allotted a larger Commercial space by the Promoter with the specific right to sell smaller virtual units to third parties.
The transactions show both entities working in tandem. One as the developer/landholder and the other as the primary allottee/marketing agent selling virtual spaces.
Since both Respondents are parties to the same agreement and have collectively failed to fulfill their obligation of delivering possession, they are both responsible for the default.
It must be appreciated that the statement of objects and reasons of RE(RD) Act, 2016 clearly states that the Act attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It also seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.
In the present complaint, the Complainant intends to withdraw from the said project and is seeking refund of the amount paid to Respondents in respect of subject unit for delay under Section 18(1) on account of delay and misrepresentation of facts under Section 12 of the Act which read as under:
“Section 18. Return of amount and compensation. -
18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building,
(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”
“Section 12. Obligations of the promoter regarding veracity of the advertisement or prospectus. -
Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. The legislature has taken a conscious decision to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authority has exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors. LL 2021 SC 641).
On perusal of the documents on record and submissions made by the Complainant, we are of the view that both the Respondents are in contravention of Sections 18 and 12 of RE (RD) Act, 2016 and as such, the Complainant is entitled to get the refund of the amount paid by him along with the interest at prescribed rate @ 10.75% p.a. (i.e., MCLR plus 2%) as per provisions of Section 18 and 12 of RE (RD) Act, 2016 read with Rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016.
In the light of the aforesaid, we consider it appropriate to order as follows:
M/s Devika Universal Land Private Limited (Respondents 1) and M/s Hiptage Infrastructure Private Limited (Respondents 2) are held jointly and severally liable for the refund of the Complainant’s money.
We direct both the Respondents to jointly or severally refund the entire amount of ₹ 16,00,000/- (Rupees Sixteen Lacs Only) to the Complainant, i.e. Mr. Harvinder Singh within 45 days of issuance of this order along with interest at the rate of 10.75% per annum (i.e., MCLR+2%) from the date of payment of each sum until the date of its actual return.
The case is disposed of accordingly.
No orders as to costs.