Tribunals and CommissionsFull Bench(2025) 11 RERA CK 3772

Mr. Bikash Banerjee & Anr. vs Delhi Development Authority & Anr.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 27 November 2025

RESULT
Disposed Of
CASE NUMBER
Com/07/11/2024
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

44 paragraphs · 1,823 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

A Complaint was filed by Mr. Bikash Banerjee and Ms. Priyanka Banerjee(hereinafter, referred to as ‘Complainants’) under Section 31 read with Section 18(1) of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as ‘RE (RD) Act’ or ‘the Act’) read with Rule 33 (1) of the NCT of Delhi Real Estate (Regulation and Development) (General) Rules, 2016 (hereinafter referred to as ‘Rules’) in Form ‘M’ on 18.11.2024.

2.

The Complainant is seeking penalty for delayed possession of their 3BHK apartment, promoted by DDA (hereinafter, referred to as ‘Respondents’) HIG category, Sector 19B, Dwarka, Delhi.

3.

The subject unit was e-auctioned as part of DDA's ‘Diwali Special Housing Scheme 2023’.

4.

The Complainants submitted that they paid a total sum of ₹ 2,08,38,948/- (Rupees Two Crores Eight Lacs Thiry-Eight Thousand Nine Hundred and Forty-Eight Only) to the Respondents for the subject flat. However, they annexed the receipts for an amount of ₹ 1,91,31,709/- (Rupees One Crore Ninety-One Lacs Thiry-One Thousand Seven Hundred and Nine Only).

5.

The records indicate that an Allotment cum Demand Letter was issued by the Respondents on 15.03.2024. A Circular demanding 25% due amount was issued by the Respondents on 28.06.2024, pursuant to which, the Complainants made the full payment for the apartment on 08.07.2024.

6.

Thereafter, though the Respondents issued a possession letter in favour of the Complainants on 16.08.2024, but it took around 4 months for them to actually handover the possession. The committed date for the handover of possession by the Respondents was 14.11.2024. The actual physical possession was transferred on 10.12.2024, with a delay of 26 days.

7.

The fundamental submission of the Complainants is that the Respondents failed to meet their commitment to hand over the flat within the stipulated timeline.

8.

The Complainants specifically quantified this delay as 28 days and are seeking a delay interest for this period.

9.

A preliminary hearing in the case was held on 02.12.2024 and a notice to the Respondents was issued on 02.04.2025 via registered post and on 04.04.2025 via email. Respondents filed their reply on 31.07.2025. After hearing the arguments of the Complainant and Ld. Counsel for the Respondents, the case was reserved for Orders on 28.08.2025.

10.

The Complainants highlighted several deficiencies concerning the project completion status, asserting that the construction quality of the flat itself was poor. The most critical grievance was the absence and non-development of common areas. These incomplete amenities were specifically the cycling track, dedicated parking space, and commercial shops.

11.

The Complainants argued that these facilities were integral to the purchased unit and were required to be developed prior to or concurrently with the handover of the apartment.

12.

Considering that the Authority exercises its jurisdiction to ensure compliance with the obligations cast upon promoters under Section 34(f) of the RE (RD) Act, 2016, the Complainants primarily have prayed for two reliefs:

A. Grant of penalty/interest for delayed possession,

B. Completion of parking and other promised common facilities.

13.

The Respondents appeared through its Authorized Representatives and Ld. Counsel and provided clarification regarding the completion status.

14.

The principal argument by the Respondents concerning the delay in possession was that it was unavoidable and attributable to circumstances beyond their control, contending the delay to force majeure provision. They specifically contended that the delay occurred mainly due to the mandatory restrictions imposed by the Graded Response Action Plan (GRAP) Orders.

15.

The Respondents submitted GRAP orders that were in force from 14.10.2024 to 24.12.2024. It was argued that since the period between the committed date of possession (i.e., 14.11.2024) and the actual handover date (i.e., 10.12.2024) fell within the period of aforesaid governmental restrictions, they are not liable to pay delayed interest/penalty.

16.

Regarding the status of the project, the Respondents placed on record the Provisional Completion Certificate (hereinafter, referred to as ‘PCC’) dated 23.03.2025. The PCC indicated that while the residential structure was largely complete, certain pending works, particularly relating to the common amenities, were required to be finished within a period of six months to obtain the final Completion Certificate.

17.

The Respondents also argued that the flats were offered under the scheme on “as-is where-is" basis and the Complainant participated in auction for the subject flat after checking ground realities.

18.

We have perused the documents available on record and heard the arguments of the Ld. Counsels for both the parties.

Analysis and Consideration:

19.

The Authority has reviewed the submissions made by both the parties and documentary evidence provided. The analysis is based on two questions:

i.

Whether the delay in possession attracts penalty under the Act, and

ii.

Whether the non-completion of common amenities warrants a directive for completion or compensation.

20.

The RE (RD) Act, 2016 has been enacted to induce professionalism and standardization in the real estate sector, paving the way for catalyzing investments and accelerating growth of the sector in the long run. To achieve these objectives, the Act created a Regulatory Authority to supervise the conception, initiation and completion of a real estate project. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. Therefore, all disputes between homebuyers/allottees and promoters/developers relating to any real estate project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered under the Act to determine. Moreover, Section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.

21.

It must be appreciated that the statement of objects and reasons of RE(RD) Act, 2016 clearly states that the Act attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It also seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.

22.

Regarding the first issue, the Complainants intend to enforce their right to a delay penalty from the Respondents for late possession. The proviso to Section 18(1) of the Act guarantees the allottee's right to claim interest for this delay, i.e.:

“Section 18. Return of amount and compensation. -

“Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.” This right is unconditional unless the delay can be attributed either force majeure or for a cause beyond the control of the Promoter. The Respondents' defense is placed entirely on the GRAP Orders, which constitute an event of force majeure.

23.

The Authority finds that the Respondents were required by contract to hand over possession by 14.11.2024. This date was noted in the possession letter given to the Complainants on 16.08.2024. However, the Complainants didn't actually receive possession until 10.12.2024, which is confirmed by the 'Actual Handover Agreement'. This means there was a clear delay of 26 days between the promised date and the actual date of handover.

24.

The Respondents have pointed out that this period coincided with severe pollution control measures in the National Capital Region. Records of the Commission for Air Quality Management (CAQM) show that Stage IV of the revised Graded Response Action Plan was invoked on 17.11.2024, immediately following the due date of possession. Stage IV mandates a comprehensive ban on all construction and demolition (C&D) activities across the National Capital Region. These mandatory statutory bans are designed to protect public health and safety.

25.

The promoter was barred from completing the final work required to deliver the unit for possession. This was a result of the implementation of the Graded Response Action Plan (GRAP), which imposed a statutory cessation of all relevant construction and development activities. The promoter was obligated to comply with these directives, making the completion of the unit by the committed date an impossibility.

26.

The entire 26-day delay falls within the ambit of the stringent GRAP restrictions. Therefore, the duration of the mandatory construction ban provides a valid and excusable extension of time to the promoter. The imposition of interest on the promoter for non-delivery during a period when work was legally prohibited would run contrary to the fundamental principle underpinning the force majeure exception within the real estate contract and under the Act.

27.

Following the ruling by the Hon'ble REAT in Basant Projects Limited v. RERA (Appeal No. 145/REAT/2024), which confirmed that GRAP orders are a form of 'force majeure,' the Authority accepts the Respondents' claim. The Authority agrees that the delay was solely and directly caused by the mandatory construction ban imposed by the GRAP orders constituting a Force Majeure event.

28.

Regarding the second issue, the Complainants seek directions to the Respondents for completion of the promised common facilities.

29.

The Authority notes that the Complainants purchased the unit through an e-auction on "as-is where-is" basis. Furthermore, the Respondents never set a specific deadline or fixed completion date for the promised common facilities.

30.

The Provisional Completion Certificate and the handover of possession confirm that the apartments are complete. The timelines for finishing Common Amenities (like bicycle tracks or shopping complexes) are separate and follow the project's overall plan. Although the Complainants accepted the unit while reserving the right to complain about incomplete common amenities, this does not automatically activate the penalty rules meant for compensating delays in handing over the unit itself.

31.

Compensation under Section 18 of the RE (RD) Act is mainly designed to cover financial losses caused when a developer delays handing over the unit itself. The Authority rules that unfinished common facilities are not valid grounds for claiming this penalty/interest for delayed possession under Section 18 of the Act. This is especially relevant here because the purchase was made on an "as-is where-is" basis.

32.

From the reply filed by the Respondents, that includes recent photographs of the site, it is evident that the construction of common amenities is finished. However, we do not absolve the Respondents of their statutory and contractual obligations to complete all common amenities as per the sanctioned plan and the stipulated timelines. The Complainants will be at liberty to seek appropriate reliefs by way of Compensation under Section 18(3) before Adjudicating Officer, if these common facilities are not developed.

33.

In the light of the aforesaid analysis and findings we order as follows:

a. The Complainants’ prayer for interest on account of delayed possession does not have merit and is hereby dismissed.

b. The Respondents shall complete the promised common facilities, if any, as per timelines in the projects’ sanctioned plan.

34.

The case is disposed of accordingly.

35.

No order as to costs.