M/s DCM Nouvelle Ltd. vs Purearth Infrastructure Ltd. & Anr.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 24 January 2023

RESULT
Disposed Of
CASE NUMBER
Com/11/01/2022, Com/12/01/2022, Com/13/01/2022, Com/18/01/2022
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

60 paragraphs · 3,770 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

By this common order we decide all the four complaints titled as above, filed in FORM ‘M’ before this Authority under section 31 of the Real Estate (Regulation and Development) Act, 2016 [hereinafter referred as “RE (RD) Act, 2016 or Act”] as common questions of facts and law are involved and they are filed against common Respondents-1, “M/s Purearth Infrastructure Ltd.” and Respondents-2, “M/s Basant Projects Limited”.

2.

The Complainant company is an allottee in the residential group housing project, “Amaryllis, Phase-1” at New Rohtak Road, New Delhi being developed by both the Respondents. The said project is registered with this Authority having registration no. DLRERA2018P0004 which was valid till 31.01.2020.

3.

Initially, M/s DCM Ltd. and both the Respondents entered into four “Agreements for Sale” for apartments (mentioned in the table below) on 29.04.2019, 22.07.2019, 24.06.2019 and thereafter M/s DCM Ltd. vide endorsement agreements dated 25.07.2019 transferred these apartments to the Complainant Company, M/s DCM Nouvelle Ltd. with all the rights and liabilities under the “Agreements for Sale”. As per clause 7.1 of these ‘Agreements for Sale’, the Respondents were to deliver the possession of the apartments by 31.01.2020. The sale deeds for flats no. T9-706 and T9-311 were registered on 15.12.2021 and flats no. T9-712 and T9-606 on 29.12.2021. However, in violation and breach of the provision of RE (RD) Act, 2016, the Respondents made the Complainant sign the possession letter on 14.12.2021 without actually handing over the physical actual possession.

4.

Aggrieved by the delay in handing over the possession of apartments, the Complainant filed four complaints in Form ‘M’ seeking several reliefs before this Authority on 24.01.2022.

5.

The Complainant has sought following reliefs in all the above-mentioned cases:

i.

Direct the Respondents to handover the vacant and peaceful physical possession of the aforementioned apartments alongwith interest for every month of delay till handing over of possession as per RE (RD) Act, 2016 and the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016;

ii.

Direct the Respondents to handover the registered Conveyance/Sale Deeds to the Complainants which are lying with them;

iii.

Direct the Respondents to handover the copies of the Maintenance Agreements;

iv.

Any other order which this Hon'ble Authority deems fit & proper in the interest of justice.

6.

The details of the complaints, dates of their filing, dates of notice & hearings, unit details, dates of signing Agreements for Sale, dates of Endorsement Agreements, names of project, dates of possession letter and possession taken over, cost of property (as per circle rate ), sale consideration as per sale deed, total sale consideration and payment made by Complainant as per ‘Agreements for Sale’ are mentioned in the table below:

S.

no.

Case no. and Name of ComplainantDates of filing, notice and hearingsDetails of unit as per the ‘Agreements for Sale’Dates of ‘Agreements for Sale’, Endorsement Agreements and name of projectDates of offer of possession, possession letter and possession taken overDates of execution of Sale Deed,Cost of property (as per circle rate ) and Sale consideration as per sale deed.Total sale consideration and payment made by Complainant as per ‘Agreement for Sale’
1.

Com/11/01/2022

M/s DCM Nouvelle Ltd. Vs. M/s Purearth Infrastructure Ltd.

24.01.2022 12.04.2022, 21.04.2022, 05.07.2022, 02.08.2022, 22.09.2022, 13.10.2022, 29.11.2022T9-712, 1140 sq. ft. carpet area, 269 sq. ft. balcony area, 1910 sq. ft. super area, Type 3 BHK + Servant, 7th floor in Tower No. 922.07.2019, 25.07.2019 The Amaryllis, Phase-120.08.2021, 10.12.2021 and 02.03.202229.12.2021Rs.1,05,92,626/-and Rs.40,11,000/-Rs.40,29,030/-and Rs.40,11,000/-
2.

Com/12/01/2022

M/s DCM Nouvelle Ltd. Vs. M/s Purearth Infrastructure Ltd.

24.01.2022 12.04.2022, 21.04.2022, 05.07.2022, 02.08.2022, 22.09.2022, 13.10.2022, 29.11.2022T9-706, 892 sq. ft. carpet area, 217 sq. ft. balcony area, 1501 sq. ft. super area, Type 3 BHK + 2 Toilets, 7th floor in Tower No. 929.04.2019, 25.07.2019 The Amaryllis, Phase-120.08.2021, 10.12.2021 and 02.03.202215.12.2021Rs. 83,00,002/-and Rs.31,52,100/-Rs.31,66,269/-and Rs.31,75,200/-
3.

Com/13/01/2022

M/s DCM Nouvelle Ltd. Vs. M/s Purearth Infrastructure Ltd.

24.01.2022 12.04.2022, 21.04.2022, 05.07.2022, 02.08.2022, 22.09.2022, 13.10.2022, 29.11.2022T9-606, 892 sq. ft. carpet area, 216 sq. ft. balcony area, 1500 sq. ft. super area, Type 3 BHK + 2 Toilets, 6th floor in Tower No. 929.04.2019, 25.07.2019 The Amaryllis, Phase-120.08.2021, 10.12.2021 and 02.03.202229.12.2021Rs. 83,00,002/-and Rs.31,50,000/-Rs.31,64,160/-and Rs.31,75,200/-
4.

Com/18/01/2022

M/s DCM Nouvelle Ltd. Vs. M/s Purearth Infrastructure Ltd.

02.02.2022 21.04.2022, 05.07.2022, 02.08.2022, 22.09.2022, 13.10.2022, 29.11.2022T9-311, 892 sq. ft. carpet area, 217 sq. ft. balcony area, 1501 sq. ft. super area, Type 3 BHK + 2 Toilets, 3rd floor in Tower No. 924.06.2019, 25.07.2019 The Amaryllis, Phase-120.08.2021, 10.12.2021 and 02.03.202215.12.2021Rs. 83,00,002/-and Rs.31,52,100/-Rs.31,66,269/-and Rs.31,75,200/-
7.

During the pendency of complaints on 21.04.2022, Ld. Counsel for Complainant made statement to withdraw the prayer for early possession as the Respondents had already given possession of flats.

8.

He pleaded that since actual possession of flats was given only on 02.03.2022, his client is entitled for interest for delay in possession.

9.

Respondents-1 filed replies in all cases on 01.08.2022. The above complaints were contested by Respondents-1 only and none appeared on behalf of M/s Basant Project Ltd. i.e., Respondents-2 during all hearings. The Complainant filed rejoinders on 15.09.2022 and the Respondents-1 filed affidavit for placing letters for offer of possession on 14.10.2022 in all cases. Written arguments were filed by the Complainant on 15.12.2022 and by Respondents-1 on 20.12.2022.

10.

We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of Respondents-1 are summarized as under:

i.

The Respondents-1 vide applications dated 18.11.2019 and 16.03.2020 applied to RERA, Delhi for extension of validity of registration of subject project, “The Amaryllis Phase-I” beyond 31.01.2020 due to stoppage of work owing to the orders issued by Hon’ble Supreme Court and other government authorities and pandemic Covid-19, as such delays were caused by circumstances beyond the control of the Respondents-1. The Authority vide its reasoned order dated 03.12.2020 granted an extension of 432 days beyond 31.01.2020 i.e. till 07.04.2021 for completion of the project. During this period, on 23.03.2020 a national lock-down was declared and imposed by the Government of India in the entire country by exercising powers under Disaster Management Act, 2005 and the Epidemic Diseases Act, 1897. The delay in possession of the said flats beyond 31.01.2020 was due to reasons beyond control of the Promoter and therefore, the Complainant is not entitled to any interest for alleged delay.

ii.

The Respondents-1 completed the project and applied for completion certificate on 14.01.2021 and got it on 19.04.2021. But, in view of restrictions imposed on movements by the Government on account of Pandemic Covid-19 Second Wave, no action could be taken by the Respondent-1 till August 2021. The Respondents-1 conveyed to Complainant about completion of project and delivery of possession on execution of sale deed on 20.08.2021.

iii.

After the charges for stamp duty and registration were deposited by Complainant on 15.11.2021, the sale deeds were executed on 15.12.2021 and 29.12.2021. The Complainant duly acknowledged getting physical possession of the apartments as per clause 4 of the respective registered sale deeds, as per the Agreement.

iv.

The Complainants was in possession of the apartments as per the physical possession letters dated 14.12.2021 which were duly signed by them and the sale deeds. The said possession letters and sale deeds are valid and binding in nature.

11.

Despite service of notice to Respondents-2, neither they appeared during any hearings nor filed replies to the complaints. Hence, the Authority decided to proceed ex-parte against Respondents-2.

Analysis and Consideration:

12.

The relief of handing over of possession and original sale deeds sought in complaints has become infructuous in view of the submission of Ld. Counsel for Complainant that possession of flats has been given and documents supplied. The only issue for consideration before us is whether Respondents-1 delayed in handing over the possession of said flats to the Complainant or not?

13.

A perusal of documents available on record shows that the Respondents entered into ‘Agreements for Sale’ with the Complainant for four flats i.e., T9-712, T9-706, T9-606 and T9-311. Clause 7 of the said “Agreement for Sale” provides for handing over of possession and is reproduced below:

7. “ POSSESSION OF THE APARTMENT:

7.1

Schedule for possession of the said Apartment- Promoter agrees and understands that timely delivery of possession of the Apartment to the Allottee and the common areas to the association of allottees or the competent authority, as the case may be, is the essence of Agreement. Promoter assures to hand over possession of the Apartment along with ready and complete common areas with all specifications, amenities and facilities in Phase-1 in place on 31 st January 2020, unless there is delay or failure due to war, flood, drought, fire, cyclone, earthquake or any other calamity caused by nature affecting the regular development of the real estate project or delay in Government clearances, issue of completion certificate & court injunction(s) without any fault of and beyond the control of the Developer (“ Force Majeure”). If, however, the completion of the Project is delayed due to the Force Majeure conditions then the Allottee agrees that the Promoter shall be entitled to the extension of time for delivery of possession of the Apartment provided that such Force Majeure conditions are not of a nature which make it impossible for the contract to be implemented. The Allottee agrees and confirms that, in the event it becomes impossible for the Promoter to implement the project due to Force Majeure conditions, then this allotment shall stand terminated and the Promoter shall refund to the Allottee the entire amount in the proportion received by them from the allotment within 45 days from that date. Promoter shall intimate the Allottee about such termination at least thirty days prior to such termination. After refund of the money paid by the Allottee, the Allottee agrees that he/she shall not have any rights, claims etc. against the Promoter and that the Promoter shall be released and discharged from all its obligations and liabilities under this Agreement.

14.

By virtue of clause 7.1 of the “Agreements for Sale” executed between the parties, the possession of the booked apartments was to be delivered on 31.01.2020. However, due to delays that were caused by circumstances beyond the control of the Respondents-1, the Respondents-1 could obtain Completion Cum Occupancy Certificate on 19.04.2021 and thereafter, offered the possession of respective apartments to the Complainant on 20.08.2021.

15.

On 15.11.2021, i.e. after a lapse of more than two and a half months of Respondent-1 offering Registration and possession i.e. 20.08.2021, the Complainant deposited the requisite registration and stamp duty charges for the purpose of sale deeds registration in respect of the said apartments. On receipt of the above stamp duty and registration charges, the Respondents-1 took appointment from the Sub-Registrar’s office at Kashmere Gate, Delhi for registration of the sale deeds of above said apartments. The appointment was given by the Sub-Registrar I, Kashmere Gate, Delhi on 14.12.2021. The sale deeds qua apartment nos. T9-706 and T9-311 were executed vide registration no. 11,487 in book no. 1, volume no. 8,816 at pages 141 to 163 and registration no. 11,848 in book no. 1, volume no. 8,816 at pages 164 to 186 respectively on 15.12.2021. However, due to technical error in the office of Sub-Registrar I, Delhi, the registration for rest two apartments could not take place on 15.12.2021 and the Respondents-1 executed the sale deed of these two apartment nos. T9-712 & T9-606 in favour of Complainant vide registration no.12,897 in book no.1 volume no. 8,863 at pages 16 to 38 and registration no. 12,901 in book no. 1, volume no. 8,863 at pages 91 to 113 respectively on 29.12.2021 at the office of Sub-registrar I, Kashmere Gate, Delhi.

16.

It is noteworthy to mention here that the acknowledgement of possession is contained in clause 4 of the sale deeds, though separate physical possession letters were also acknowledged and duly signed by the Complainant in respect of the above said apartments. Clause 4 of sale deeds is reproduced below for ready reference:

4. “POSSESSION OF THE APARTMENT:

The Vendor has handed over and the Vendee has taken over the vacant physical possession of the Apartment in accordance with the Agreement. The Vendee agrees that it has inspected the construction of the said Apartment and confirms that the Apartment is complete/ fully functional in all respects and that it has no claim/ grievance against the Vendor in respect of the terms of work done in the Apartment or any defect in design, specification, building material used or for any reasons whatsoever. The Vendee agrees that works done in the Apartment, are as per the Vendee's specifications and the Vendee is fully satisfied with the condition in which the Apartment has been handed over to it.”

17.

As it is evident from the above-mentioned clause for possession of the apartments in “Agreements for Sale” or in the ‘sale deeds’, the Respondents had duly informed the Complainant about the actual date for handing over the possession. Both documents are signed and executed by the Complainant. So, it can be inferred from these documents that the Complainant was very well aware that how and what procedure will be followed for handing over the possession of said apartments.

18.

The contention of Complainant that the Respondents-1 delayed the possession of said apartments cannot be accepted as after going through all the documents it is found that the Respondents-1 had time to time followed the due procedure for handing over the possession of apartments i.e., obtained the Completion Cum Occupancy Certificate from competent authority on 19.04.2021, offered the possession of apartments to the Complainant on 20.08.2021 and thereafter, took appointment from the Sub-Registrar’s office for execution of sale deeds, executed the sale deeds with the Complainant on 14.12.2021 and 29.12.2021. The sale deeds are also seen to be signed by the authorized signatory of the Complainant, namely Mr. Vishal Sharma along with the possession letters. The Complainant has not denied that this possession letter was not signed by the authorised signatory at the time of execution of sale deeds.

19.

At this stage, the Authority would express its views regarding the concept of 'valid offer of possession'. It is necessary to clarify this concept because after valid and lawful offer of possession liability of promoter for delayed possession comes to an end. On the other hand, if the possession is not valid and lawful, liability of promoter continues till a valid offer is made and allottee remains entitled to receive interest for the delay caused in handing over valid possession.

20.

The Authority after detailed consideration of the matter has arrived at the conclusion that a valid offer of possession must have following components:

i.

Possession must be offered after obtaining completion and occupation certificate- The subject unit after its completion should have received completion and occupation certificate from the Competent Authority certifying that all basic infrastructural facilities have been laid and are operational. Such infrastructural facilities include water supply, sewerage system, storm water drainage, electricity supply, roads and street lighting.

ii.

The subject unit should be in habitable condition- The test of habitability, in our view, is that the allottee should be able to live in the subject unit within 30 days of the offer of possession after carrying out basic cleaning works and getting electricity, water and sewer connections etc from the relevant authorities. In a habitable unit all the common facilities like lifts, stairs, lobbies, etc should be functional or capable of being made functional within 30 days after completing prescribed formalities. The authority is further of the view that minor defects like little gaps in the windows or minor cracks in some of the tiles, or chipping plaster or chipping paint at some places or improper functioning of drawers of kitchen or cupboards etc. are minor defects which do not render unit uninhabitable. Such minor defects can be rectified later at the cost of the developers. The allottees should accept possession of the subject unit with such minor defects under protest. This Authority can award suitable relief for rectification of minor defects after taking over of possession under protest. However, if the subject unit is not habitable at all because the plastering work is yet to be done, flooring works is yet to be done, common services like lift etc. are non-operational, infrastructural facilities are non-operational then the subject unit shall be deemed as uninhabitable and offer of possession of an uninhabitable unit will not be considered a legally valid offer of possession.

iii.

Possession should not be accompanied by unreasonable additional demands- In several cases additional demands are made and sent along with the offer of possession. Such additional demands could be unreasonable which put heavy burden upon the allottees. An offer accompanied with unreasonable demands beyond the scope of provisions of Agreement to Sale should be termed as invalid offer of possession. Unreasonable demands themselves would make an offer unsustainable in the eyes of law. The Authority is of the view that if Respondents have raised additional demands, the allottees should accept possession under protest.

21.

In the present complaints, the Respondents-1 applied for grant of Completion Cum Occupation Certificate on 14.01.2021, and, the concerned authority granted the Completion Cum Occupancy Certificate on 19.04.2021, but offer of possession was given on 20.08.2021. Clause 7.2. of ‘Agreements of Sale’ states the procedure for taking possession. It says that the promoter within 30 days upon obtaining the completion certificate from the competent authority shall offer in writing the possession of the apartment to the allotttee. Possession in terms of this Agreement was to be given within thirty days from the date of issue of completion certificate. The Authority takes note of the fact that on account of the Covid-19 Second Wave, there were restrictions on movements and activities. Therefore, the offer of possession dated 20.08.2021 given by the Respondents to the Complainant, though after thirty days, is valid in the eyes of law, as delay was due to ‘Force Majeure’. The argument of Ld. Counsel for Complainant that letter dated 20.08.2021 was conditional offer of possession is not acceptable to us. The Complainant deposited the registration charges for registration of sale deed on 15.11.2021 and thereafter, the Respondents obtained a date of execution of documents for registration from the Sub-Registrar’s office at Kashmere Gate, Delhi for registration of the sale deeds of said apartments. The sale deeds for apartment nos. T9-706 and T9-311 were executed on 15.12.2021 and apartment nos. T9-712 & T9-606 were executed on 29.12.2021. The Complainant received the actual possession of the flats on 14.12.2021 as can be seen from the possession letters signed by the authorised signatory of the Complainant.

22.

The Respondents-1 could not initiate the process of registration of sale deeds after issue of offer for possession letter because the Complainant deposited the requisite charges only on 15.11.2021. We note that date for registration of documents was given by office of Sub-Registrar as per its schedule. So, the Respondents -1 cannot be held liable for the time gap between the deposit of requisite fees and registration of sale deeds. The sale deeds were executed along with possession letters duly signed by authorized signatory of the Complainant. Simply because sale deeds were handed over after few days will not nullify the possession taken by the Complainant through the possession letters duly signed by the authorised signatory. The Authority considering these facts and circumstances has come to the conclusion that there was no delay in handing over the possession which can be attributed to Respondents-1.

23.

The Ld. Counsel for the Complainant further argued that the grant of extension of time to complete the project does not supersede the date of possession mentioned in the ‘Agreements for Sale’ and the extension granted by this Authority is only for the RERA compliance purposes and relied on the judgment passed by Hon'ble Bombay High Court in Neelkamal Realtors Suburban Pvt. Ltd. & Anr. Vs. Union of India & Ors. (Writ Petition 2737/2017) wherein it has been observed as under-

"256.

Section 4(2)(l)(C) enables the promoter to revise the date of completion of project and hand over possession. The provisions of RERA, however, do not rewrite the clause of completion or handing over possession in agreement for sale. Section 4(2)(l)(C) enables the promoter to give fresh time line independent of the time period stipulated in the agreements for sale entered into between him and the allottees so that he is not visited with penal consequences laid down under RERA. In other words, by giving opportunity to the promoter to prescribe fresh time line under Section 4(2)(l)(C) he is not absolved of the liability under the agreement for sale."

24.

However, the facts in the present case are different. Section 4(2)(l)(c) gives liberty to a promoter to give fresh timeline for completion of project which was ongoing as on 01.05.2017, i.e., the date on which Act came into force. In other words, we can say, had there been an ‘Agreement to Sale’ before 01.05.2017, then the Complainant could have raised this argument and could have sought relief of refund of amount or interest on delayed possession under section 18 of RE (RD) Act, 2016. But in present cases, the ‘Agreements to Sale’ were executed on 22.07.2019, 29.04.2019 and 24.06.2019 i.e., after the Act came into being. We note that the promoter registered the project “The Amaryllis, Phase-I” under the provisions of the RE (RD) Act, 2016 with this Authority on 05.03.2018 vide registration no. DLRERA2018P0004. The Authority vide order dated 03.12.2020 granted an extension to the project for a total of 432 days beyond 31.01.2020. The Authority by its certificate no. F1(12)PR/RERA/2017/3171 dated 07.12.2020 (‘Extension Certificate’) granted an extension of time till 07.04.2021 for the completion of the said project. Thus, the due date of possession of the apartments stood extended. The project, itself was registered on 05.03.2018 i.e., after the Act became effective. Therefore, section 4(2)(l)(c) of RE (RD) Act, 2016 will not be applicable in this case.

25.

The extension of time for completion of project was given by the Authority, as per the provisions of the RE (RD) Act, 2016 considering the delay due to reasons beyond the control of Respondent-1. Therefore, the allottee of the project is bound by the extensions granted.

26.

In the above backdrop of facts and circumstances, no delay in handing over the possession of the flats on the part of Respondents-1 has been established. Therefore, the Complainant is not entitled for interest on account of delay in possession under section 18 of RE (RD) Act, 2016. All above-mentioned cases are disposed of accordingly.

27.

No orders as to costs.

28.

Files are consigned to Record Room.