Tribunals and CommissionsDivision Bench(2022) 06 RERA CK 0878

Mr. Amit Bagga vs Delhi Development Authority

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 29 June 2022

RESULT
Disposed Of
CASE NUMBER
Comp/Dec/06/2021
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

15 paragraphs · 761 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

A complaint was filed in FORM ‘M’ on 21.12.2021 by Mr. Amit Bagga (hereinafter referred as “Complainant”) stating that in the year 2020, unit no. 33 at CSC no. 9, Sector-13, Rohini measuring 13.05 sq. mt. was allotted to him vide e-auction held on 15.02.2020 by the Delhi Development Authority (hereinafter referred as “Respondents”).

2.

A Letter of Intent was sent to the Complainant by the Respondents on 22.06.2020. Also, a demand letter dated 14.08.2020 was issued by the Respondents to the Complainant to pay the due amount. The Respondents delivered the possession of the unit to the Complainant vide possession letter dated 27.09.2021. A possession slip dated 27.09.2021 was also received by the Complainant on 28.10.2021.

3.

The Complainant submitted that the gross area of shop in all documents of DDA was mentioned as 13.05. sq. mt. but on the actual calculation at the time of receiving possession, it was found to be 7.0 sq. mt. only. He further submitted that since DDA delayed the possession, he seeks compensation for the delay in handing over the possession of the said unit.

4.

A preliminary hearing in this case was held on 21.02.2022 and a notice to the Respondents was issued on 17.01.2022.

5.

The matter was heard in several hearings dated 21.02.2022, 06.04.2022 and 01.06.2022. The Respondents filed their reply on 25.03.2022.

6.

The Respondents submitted that a demand letter dated 14.08.2020 was issued by them to the Complainant and last payment was made by him on 14.10.2020. It was submitted that the delay in handing over the possession happened as Complainant did not file proof of payment in time with them. It was filed by him only on 29.07.2021 that too on the request of their Accounts Department.

7.

Clause 12 of the tender document for e-auction, clearly mentions :

“12.

Within 10 days from the date of making the payment indicated in the clause 2(8) above the highest bidder shall appear before the Dy. Director (CE) in his office in person or through authorized representative along with terms and conditions of bid duly typed on a non-judicial stamp paper worth Rs. 10/- signed by bidder and duly attested by the notary public. Specimen signature of individual or combined as case may be duly attested by notary public/gazatted officer and 4 passport size joint photo one of which should be attested by gazetted officer and conveyance deed paper duly stamped by collector of stamps and any other documents indicated in the demand letter. On submission of the above documents, the possession letter will be issued same day and the same can also be collected in person by Bidder on the same day. The possession letter so issued shall carry the date by which the physical possession of the unit will be handed over to the bidder at site. For non-production of proof of the payment of balance 75% of premium in time as stipulated above clause 2(vii) the bid is liable to be cancelled and the earnest money shall be forfeited.”

8.

The Complainant apparently did not appear before the Deputy Director (CE) in time with proof of payment. Asstt. Director (CE) DDA asked the Complainant to produce the proof of payment as per his letter dated 22.07.2021. Subsequently, after Complainant produced proof of payment, the Respondents issued to him possession letter dated 27.09.2021. The physical possession was handed over to Complainant on 28.10.2021 and he also signed the possession slip taking possession in which it is clearly stated:

"Certified that possession of Unit No. 33, Pocket No. Block, Sector -13, Floor Ground measuring 13.05 Sqm (includes plinth area & common area) Scheme CSC No. 9, Sector -13, Rohini has been taken over by me on dated 28.10.2021 and it is free from encroachment.”

9.

We have heard the arguments of both the parties and perused the records.

10.

A perusal of records shows that the Respondents had issued the possession letter and possession slip dated 27.09.2021 to the Complainant and he had voluntarily signed it without raising any objections regarding short area. Now, after accepting the possession as mentioned in para 8 above, he cannot claim that area of shop is short.

11.

It is evident from letter no. F.No. 93(2) 2020/CE/818 dated 22.07.2021 aforementioned that the delay caused in delivering the possession was due to the fault of the Complainant i.e., for not submitting the proof of payment in time before the Respondents. Therefore, the Complainant cannot claim any interest for delay.

12.

The complaint is, therefore, disposed of accordingly.

13.

No order as to cost.