High CourtsSingle Bench(2026) 10 AP CK 0705

M/s. P N. Reddy Infrastructure Pvt. Ltd. vs The State Of Andhra Pradesh & Ors.

Andhra Pradesh High Court, Amaravati · Decided on 5 October 2026

HON’BLE JUDGES
Harinath N., J
CASE NUMBER
Writ Petition No: 28250/2026

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

7 paragraphs · 287 words

The Court made the following order:

The learned counsel for the petitioner submits that the petitioner was entrusted with the execution of the work i.e., providing pavement from Nunnamalyadri house (D.No.10-11-145/A) to Danam Suresh Kumar (D.No.11-31-82/1) in 13th ward Pullareddy Nagar Main Road Extension of Kavali Municipality covered by Agreement No.16/2017-18, dated 12.12.2017.

2.

It is submitted that the petitioner had completed the work entrusted to him and that the competent authority of the respondents had also approved the payment due and payable to the petitioner. The respondents have also recorded the progress of the works and the amounts due and payable to the petitioner in the M-Book. However, the respondents are yet to release the amounts due and payable to the petitioner.

3.

Heard the submissions of the learned counsel for the petitioner and the learned Government Pleader for Social Welfare.

4.

During the course of hearing, the learned Government Pleader of Social Welfare submits, on the basis of the instructions received, that the work has been completed and that the petitioner has also submitted the final bills and the amounts due and payable to the petitioner have been duly admitted. It is submitted that further funds are awaited and that, soon after the release of the funds, the bills due and payable to the petitioner shall be cleared.

5.

Recording the submissions, the Writ Petition is disposed of directing the respondents to verify and release the payments due and payable to the petitioner as expeditiously as possible, preferably within a period of six (06) weeks from the date of receipt of a copy of this order. There shall be no order as to costs.

As a sequel, pending miscellaneous petitions, if any, shall stand closed.