Judgment
Heard learned advocate for the petitioner and learned advocate for the State.
The petitioner, being a Director of Construction and Supplies Pvt. Ltd., has approached this Court seeking a direction upon the respondent Executive Engineer, Local Area Engineering Organisation, Works Division-02, Benipur, Darbhanga, to issue an order for resumption of the construction work of the Panchayat Sarkar Building at Budh Way Inayatpur Panchayat, under Block-Ghanshyampur, District-Darbhanga,
pursuant to Agreement No. 03/SBD 2024-25 dated 04.09.2024, or, in the alternative, to refund the security deposit and earnest money deposited by the petitioner.
From the materials on record, it appears that the petitioner entered into an agreement with the Executive Engineer, Local Area Engineering Organisation, Works Division-02, on 04.09.2024.
The petitioner, having been declared the successful bidder, was directed to proceed with the execution of the aforesaid work in accordance with the terms and conditions of the contract. The construction work of the Panchayat Sarkar Building, in terms of the Agreement dated 04.09.2024, was required to be completed by 03.11.2025 from the date of commencement. However, it is the specific contention of learned Advocate for the petitioner that the work, in question, could not be completed on account of severe waterlogging at the proposed site, due to which, the construction work was brought to a halt pursuant to Memo No. 433 dated 09.05.2025 issued by the Circle Officer, Ghanshyampur.
The Executive Engineer, LAEO, Works Division, sought clarification from the Circle Officer, Ghanshyampur, vide Letter No. 864 dated 17.05.2025, with regard to the
execution of the work at the site. However, till date, no decision has been taken regarding the resumption of the work. More than two years have elapsed. In such circumstances, the petitioner made a representation before the Executive Engineer, LAEO, Works Division-02, Benipur, Darbhanga, requesting him either to direct the resumption of the construction work or to cancel the agreement and refund the security deposit and earnest money. However, no final decision has been taken on the said representation, hence, the present writ petition.
Learned Advocate for the State, however, prays for a short adjournment to apprise this Court with regard to the present factual position.
Considering the nature of the claim as raised in the present writ petition, this Court finds it appropriate to dispose of the same with the liberty to the petitioner to file a fresh representation before the Executive Engineer, LAEO, Works Division-02, Benipur, Darbhanga, preferably within a period of two weeks.
In case, such a representation is filed, the concerned respondent Executive Engineer, LAEO, Works Division-02, Benipur, Darbhanga shall pass an appropriate order, in accordance with law, within a further period of eight weeks.
With the aforesaid direction, the present writ petition stands disposed of.