Heard the parties.
The petitioners, claiming to be the residents of Rajeev Nagar and Digha area, have approached this Court seeking a direction upon the respondent authorities, particularly respondent nos. 6 and 7, to accept the application of the petitioners for an electric connection and allow them to deposit the requisite amount for supply of electric connection in the premises of the petitioners situated in the aforesaid locality.
The petitioners are either in possession of a General Power of Attorney and a rent agreement executed in their favour, on the basis of which they are seeking an electricity connection.
Learned advocate for the petitioners submits that similarly situated residents of the Rajeev Nagar and Digha
areas had approached this Court, and their applications were disposed of considering the reliance placed by the applicants, especially on Clause 4.13(B) of Chapter 4 of the Bihar Electricity Supply Code, 2007, which requires the concerned respondent(s) to grant electricity connections even in respect of encroached government/semi-government/public land, subject to the furnishing of the documents required under the said Supply Code. In support of the aforesaid contention, a copy of the order passed in CWJC No. 11980 of 2026 has also been brought on record as Annexure-P/9.
Learned advocate for the South Bihar Power Distribution Company Limited has fairly submitted that the claim of the petitioners shall be considered by the SBPDCL, if they will submit online application for grant of electric connection along with all the requisite documents as per the Bihar Electricity Supply Code, 2007.
Considering the submissions advanced by learned advocates for the respective parties, this Court disposes the present writ petition with a direction to the petitioners to submit online application along with the requisite documents within a period of four weeks from today. If such online application(s) is filed by the petitioners, the concerned
respondent shall be obliged to consider the same and take appropriate decision, in accordance with law, within a further period of four weeks from the date/receipt of the application of the petitioners.
With the aforesaid observation and direction, the present writ petition stands disposed.