Anant S. Dave, J
1 The petitioner has filed this Writ Petition (PIL), with the following main prayers:
“[A] YOUR LORDSHIPS may be pleased to issue a writ of mandamus or a writ in the nature of mandamus or any other appropriate writ, order
or directions quashing and setting aside Land Re-survey of Jamnagar and Devbhoomi Dwarka Districts as per the Jamnagar District Project considering the report dated 09.02.2017 (At Annexure-V) and 16.02.2017 (At Annexure-X) and further be pleased to direct the concerned respondent authorities to undertake fresh re-survey of Jamnagar and Devbhoomi Dwarka Districts as per the Re-survey Manual — 2012;
[B] YOUR LORDSHIPS may further be pleased to issue a writ of mandamus or a writ in the nature of mandamus or nay other appropriate writ,
order or directions directing inquiry and actions Civil as well as Criminal) against the concerned erring officers of the respondent authorities /
companies who are responsible for the illegal re-survey of Jamnagar and Devbhoomi Dwarka districts and further be pleased to direct that such concerned erring officers / persons shall bear the cost of re-survey and further be pleased to direct respondent no.16 to investigate the complaint of the petitioner (At Annexure-W) and submit a report to this Hon'ble Court and also be pleased to direct Responded no.1 to submit the report on the complaints / representations of the petitioner (At Annexure-W, Y and Z);
[C] During pendency and Final disposal of the present petition, YOUR LORDSHIPS may be pleased to direct respondent no.16 to investigate the complaint of the petitioner (At Annexure-W) and submit a report to this Hon'ble Court and also be pleased to direct Respondent no.1 to submit the report on the complaints / representations of the petitioner (At Annexure-W, Y and Z);—
2 In this petition, Deputy Director, Land Records, Rajkot filed affidavit in reply dated 09.02.2018 on behalf of respondent No.2, wherein it was submitted that the re-survey project is carried out in various stages viz. [a] Pre Survey, [b] Survey, [c] Objections & Adjudication, [d] Record
Scrutiny & Record Preparation, [e] Notification & promulgation, and [f] Post promulgation objection redressal and accordingly in Jamnagar and
Devbhoomi Dwarka districts, 27,913 and 9,458 objections were received and such objections were resolved. Further, upon resolving initial objections as above, post scrutiny and approval of the records were sent to the Prant Officer within the subject districts for promulgation as provided under the
Gujarat Land Revenue Code and the Rules made thereunder and by circular dated 14.03.2016 the State Government has evolved post promulgation objections redressal mechanism and as per the above circular also objections were received, which were also resoled, but 1,421 and 733 objections remained pending with the Districts of Jamnagar and Devbhoomi Dwarka respectively. Along with the above, it is submitted that the District Revenue
Authorities have undertaken re-survey of Gauchar land and other requirements are required to be followed.
3 However, a rejoinder was filed by the petitioner wherein certain lacunas were pointed out and further inquiry is to be made in re survey project by re-survey agency and accordingly appropriate measures are to be taken.
4 Now, further affidavit in reply dated 09.70.2019 is filed by the Deputy Director Land Records, Rajkot on behalf of respondent Nos.3 and 4, wherein details are provided about re-survey undertaken after promulgation as on 02.07.2019 and in para 3 thereof, it is averred as under:
“3. In this regard as per the 18 that were being raised by the petitioner, the respondent authorities are in the process of re-survey of land located
at Jamnagar and Devbhoomi Dwarka. The objections of the petitioner with regard to promulgation and measurement were taken into consideration by the respondent authorities and if found correct then appropriate entries with regard to promulgation and measurement were entered into revenue
records. It is further submitted before this Hon'ble Court that the objection of the petitioner with regard to measurement of land were taken into consideration by the respondent authorities and by applying techniques like Digital Global Position Survey (DGPS) were adopted by the respondent
authorities. It is further submitted before this Hon'ble Court at the time of re-survey and measurement of land all the stake holders including the individuals whose lands are measured are informed in advanced and the measurement is being carried out in their presence. A statement showing a details of re-survey at District : Jamnagar and Devbhoomi-Dwarka along with the details of objections received and processed thereof is annexed
hereto and marked as Annexure-R1 (Colly.).”
5 Having heard learned counsels for the parties and on perusal of the record of the case, we noticed that the authority concerned has undertaken an extensive exercise pursuant to re survey project of the land, revenue land and other lands in the districts of Jamnagar and Devbhoomi Dwarka and we find at this stage that no further monitoring is necessary. However, it will be open for the petitioner to to take appropriate steps in accordance with
law, if any grievance still exists.
With the aforesaid, this Writ Petition [PIL] stands disposed of.