PER: DR. SANJIV KUMAR, MEMBER (A)
This OA has been filed under Section 19 of the Administrative Tribunals Act, 1985, seeking the following reliefs:-
“(i)Quash the order issued on F.No. 13011/11/2015/D(Vig-M&B)/250 dt. 08.03.2022 issued by the Respondent at Annexure: A8 with all the consequential benefits, in the interest of justice. and,
(ii)Grant such other relief(s) to the applicant as this Hon’ble Tribunal deems fit to grant in the facts and circumstances of the case, in the interest of justice.”
The aforesaid reliefs have been sought on the following grounds:-
“(i)That, the Applicant has not committed the misconduct alleged in the memorandum of charge at Annexure: A-1 and hence, the impugned order at Annexure: A-8 is unjust and unsustainable in law.
(ii)The impugned order of penalty suffers from arbitrariness in as much as the relevant facts have not been appreciated properly, due to non application of mind by the Respondent.
(iii)The Applicant is innocent and has discharged his part of duties honestly, diligently and to the best of his knowledge.
(iv)No allegation of malice, corruption or culpable negligence has been made against the Applicant in the Memorandum of charge at Annexure: A-1.
(v)None of the ingredients constituting the misconduct has been established against the Applicant still the Applicant has been unjustly punished.
(vi)There is no iota of evidence placed in the inquiry, finding Applicant as guilty. There is no iota of ingredients constituting misconduct as to the job which Applicant has discharged. Despite the Applicant has not committed any misconduct, he has been punished unjustly by the Respondent by non-application of mind to the entire circumstances of the case.
(vii)Before imposing any punishment, the Respondent is expected to apply his mind fully to the entire facts and circumstances of the case in addition to the below mentioned attributes to the “misconduct” judicially & universally accepted. According to the Applicant, the Respondent has punished the Applicant arbitrarily, though the Applicant has not committed any misconduct.
“ Misconduct. A transgression of some established and definite rule of action, a forbidden act, a dereliction from duty, unlawful behavior, willful in charecter, improper or wrong behavior, its synonyms are mis-demeanor, misdeed, misbehavior, delinquency, impropriety, mismanagement, offense, but not negligence or carelessness. Term “misconduct” when applied to act of attorney, implies dishonest act or attempt to persuade court or jury by use of deceptive or reprehensible methods. People v. Sigal, 249 C.A.2d 299, 57 Cal. Rptr. 541, 549. renders Misconduct, which discharged employee ineligible for unemployment compensation, occurs when conduct of employee evinces willful or wanton disregard of employer’s interest, as in deliberate violations, or disregard of standards of behavior which employer has right to expect of his employees, or in carelessness or negligence of such degree or recurrence as to manifest wrongful intent or evil design. Wilson v. Brown, La.App., 147 So.2d 27, 29. See also Wanton misconduct.” [Black’s Law Dictionary-5th Edition].
(viii)That, the impugned order dated 08.03.2022 at Annexure: A-8 is against the acceptable evidence placed on record and the said order is based on surmises and conjectures and hence arbitrary due to non-application of mind to the facts and circumstances of the case and hence, unsustainable in law. That the decisions taken by the Respondent are unsustainable in law, if one examines the evidence on record dispassionately.
(ix)The I.O. has come to a perfect finding of facts. In respect of IV-Article of charge, his finding of facts is correct, but his decision that the charges are partly proved on the basis of mere placement of false and fabricated test certificates submitted by the Contractor is fallacious in absence of finding that the Applicant was aware of these test certificates as false & fabricated and still placed them on record. There was no chance on the part of the Applicant to doubt the genuineness of these certificates, since result recorded in these certificates matched with the test conducted in the field lab which was in-charge of AGE (I) working under the direct control & command of the Chief Engineer (AF).
(x)Impugned order is arbitrary and is a no-speaking order and hence unsustainable in law.”
The brief facts of the case, as stated in the synopsis, are as follows:-
“ The Applicant was issued with a Memorandum of charges dated 09.02.2018 U/R 14 of the CCS (CCA) Rules, 1965 the Respondent (vide Annexure: A-1). The Applicant denies the charges by a reply dated 05.04.2018 (vide Annexure: A-2). I.O. after holding inquiry submits his report dated 07.12.2019 in two parts to the Respondent holding that the Articles of charges I, II & III are not proved and that the IV-Article of charges proved partly (vide Annexures: A-4 & A-5). Infact certain alleged facts are proved and the proved facts do not constitute commission of misconduct. The Respondent asks the Applicant to submit his representation by enclosing a disagreement note by a letter dated 13.09.2021 (vide Annexure: A-6). The Applicant submits his representation to the disagreement note by a letter dated 25.11.2021 (vide Annexure: A-7). The Respondent imposes penalty on the Applicant by an order dated 08.03.2022 (vide Annexure: A-8). The Applicant being aggrieved the said unjust order of penalty has filed the present O.A.
LIST OF DATES
09.02.2018 (i) Respondent issues Memorandum U/R 14 of the CCS (CCA) Rules, 1965 against the applicant frame in four Articles of Charges. (ii) Respondent orders to hold common disciplinary proceedings against 6 officers including the applicant. 05.04.2018 Applicant denies the alleged charges. 07.12.2019 I.O. submits his report in 2 parts to the Respondent. 13.09.2021 Respondent issues letter enclosing disagreement note seeking representation of the applicant, if any, on the disagreement note. 25.11.2021 Applicant submits his response to the disagreement note to the Respondent. 08.03.2022 The Respondent impose penalty on the applicant arbitrarily.
On notice being issued, the respondent filed their reply statement. Thereafter, the applicant filed a rejoinder. The parties have also filed a list of authorities and memos along with the relevant documents.
The case came up for final hearing on 15.09.2026. Shri N.G. Phadke, learned counsel for the applicant, and Shri Vishnu Bhat, learned counsel for the respondent, were present and heard.
We have carefully gone through the records and considered the rival contentions advanced by the parties.
The respondent have averred that the disciplinary inquiry against the applicant was conducted in accordance with the prescribed procedure and in adherence to the principles of natural justice, and that the impugned order was passed thereafter in due process. According to the respondent, the impugned order is a speaking and self-contained order. They have further contended that, since the impugned order is a Presidential Order, it is legitimately precise and to the point and that there is no further appeal against the same. However, according to the respondent, the entire details are available in the original record, where the authorities concerned considered and appreciated all the evidence, including the applicant’s reply to the disagreement note issued by the Disciplinary Authority. It is, therefore, contended that there is no infirmity in the impugned order and that the OA deserves to be dismissed.
Before examining the grounds urged by the applicant and the submissions of the parties, it would be appropriate to notice the Articles of Charge, there being four charges in all.
The first Article of Charge relates to the alleged failure of the applicant to carry out physical verification of the entries in the documents with the quantity of stocks/raw materials, with particular reference to the cement brought to the site by the contractor. It is alleged that, by the said conduct, the applicant failed to maintain absolute integrity, exhibited lack of devotion to duty, acted in a manner unbecoming of a Government Servant, and failed to maintain high ethical standards and honesty, etc.
The second Article of Charge relates to the alleged failure of the applicant to carry out physical verification of the entries in the documents with the quantity of stocks/raw materials, namely, bitumen brought to the site by the contractor. It is alleged that, by the aforesaid conduct, the applicant failed to maintain absolute integrity, exhibited lack of devotion to duty, acted in a manner unbecoming of a Government Servant, and failed to maintain high ethical standards and honesty, etc.
The third Article of Charge alleges that the applicant failed in the discharge of his official duty by suppressing information that the contract work had been sublet and that, by the aforesaid acts, he failed to maintain absolute integrity, exhibited lack of devotion to duty, acted in a manner unbecoming of a Government Servant, and failed to maintain high ethical standards and honesty, etc.
The fourth Article of Charge alleges that the applicant had connived with the AGE to show that the samples of cement brought to the site had been sent to Coimbatore Institute of Technology, Coimbatore, for testing and had kept on file false and fabricated Test Certificates submitted by the contractor, which were purportedly issued by Coimbatore Institute of Technology, Coimbatore, to show that the tests had been carried out as stipulated in the Contract Agreement. By the aforesaid acts, the applicant was alleged to have failed to maintain absolute integrity, exhibited lack of devotion to duty, acted in a manner unbecoming of a Government Servant, and failed to maintain high ethical standards and honesty, etc.
Accordingly, the charges were framed and a detailed disciplinary inquiry was conducted. The Inquiry Officer submitted his report and recorded that Charge Nos. 1, 2 and 3 were not proved and that only Charge No. 4 was partially proved. When the Inquiry Officer’s report was placed before the Disciplinary Authority, the Disciplinary Authority disagreed with the conclusions of the Inquiry Officer and issued a disagreement note, to which the applicant submitted his reply. After considering the applicant’s submissions, the Disciplinary Authority concluded that Charge No. 1 was partially proved, Charge No. 2 was not proved, Charge No. 3 was partially proved and Charge No. 4 was partially proved, and accordingly proceeded to impose the penalty by the impugned order.
We shall now examine the contentions raised by the applicant in support of his case, one by one.
In para 5(i), the applicant contends that he has not committed the misconduct alleged in the memorandum of charge at Annexure: A1 and, therefore, the impugned order at Annexure: A8 is unjust and unsustainable in law.
The respondent have denied the said contention. The mere assertion of innocence, in the absence of any supporting material, cannot by itself constitute a ground for interference with the impugned order. Therefore, this assertion, considered in isolation, does not advance the applicant’s case.
In para 5(ii), the applicant contends that the impugned order of penalty suffers from arbitrariness inasmuch as the relevant facts have not been properly appreciated on account of non-application of mind by the respondent.
At the time of arguments, this contention was elaborated by submitting that a relevant fact which, according to the applicant, was not appreciated by the respondent was that he was an untrained, newly appointed Engineer and, in the first place, ought not to have been posted in such an important and technically specialised assignment relating to the construction of an Air Force airfield. It was contended that the respondent failed to appreciate that the applicant was in no manner responsible for the acts alleged against him.
According to the applicant, his job was not to carry out physical verification of the entries in the documents with the quantity of stocks/raw materials with reference to cement brought to the site by the contractor. His role, according to him, was restricted to making entries in the Register.
The respondent, however, contend that, being a Site Engineer/JE, the applicant cannot contend that his role was merely to make entries in a stock register. He was a site engineer and not an accountant, and it was his duty to physically verify what was being brought to the site, from where it was being brought, and whether the information contained in the documents and entered in the Register was correct. Otherwise, according to the respondent, the function would amount merely to mechanically entering information, for which the presence of a technically qualified site engineer at the site would serve no meaningful purpose.
The same contention arises with regard to the physical verification of the entries relating to the quantity of stocks/raw materials, namely, bitumen, brought to the site by the contractor.
The applicant has similarly contended that, as a Site Engineer, it was not his responsibility to ascertain whether the work had been sub-contracted. The respondent, on the other hand, contend that, as a Site Engineer, the applicant was responsible for overseeing whether the work was progressing in accordance with the terms of the contract. According to them, he was required to observe who was executing the work and whether the contractual conditions were being complied with, including the condition prohibiting sub-contracting. The respondent further contend that, during the inquiry, sufficient material was brought on record to show that sub-contracting was taking place and that certain documents handled by the applicant contained details from which the identity of the sub-contractor could be ascertained. Hence, according to the respondent, the applicant cannot at this stage contend that he had no means of knowing about the sub-contracting.
Similarly, the applicant contends that it was not his responsibility to send samples for testing the quality of materials supplied, particularly cement. According to him, his responsibility was only to receive and place on record any certification documents formally submitted to him. He accordingly received and placed on file the test certificates relating to cement, without independently verifying the veracity or credibility of the certificates purportedly issued by the Coimbatore Institute of Technology.
The respondent, however, contend that a Site Engineer is expected to exercise due diligence with regard to the materials brought to and utilised at the site and the activities being undertaken there. According to them, he was not merely functioning as a “Post Office” for receiving certificates regarding the quality of cement, the sending of samples for testing and the receipt of test reports. The respondent further contend that the applicant was required to remain alert regarding what was being received, from where it was received, and the vehicles in which the materials were transported. According to the respondent, a technically qualified Site Engineer, exercising due diligence and remaining attentive to the activities at the site, could have noticed the discrepancies and detected the irregularities.
Thus, while the applicant contends that the charges have not been proved, the respondent contend that the charges stand proved on the basis of the material available on record.
Before us, Annexure – A1 is the Charge Memorandum dated 09.02.2018, wherein Annexure-I is the Statement of Articles of Charge Framed against the applicant, Annexure-II is the Statement of Imputation of Misconduct or Misbehaviour in support of the articles of charge framed against the applicant, Annexure-III is the list of documents relied upon, wherein 18 documents were relied upon for Article-I, 8 documents were relied upon for Article-II, 9 documents were relied upon for Article-III and 2 documents were relied upon for Article-IV, and Annexure-IV is the list of Witnesses, wherein 11 witnesses are listed to be examined by the department.
Annexure – A2 dated 05.04.2018 is the applicant’s detailed reply to the charge memorandum in respect of each of the charges. We shall return to this aspect while considering whether the penalty order is arbitrary and whether the evidence has been properly appreciated.
Further, in para 5(iii), the applicant contends that he is innocent and has discharged his duties honestly, diligently and to the best of his knowledge.
These assertions, however, do not, by themselves, absolve the applicant of the charges or discredit the disciplinary inquiry. A mere assertion of innocence cannot substitute for a defence supported by material evidence.
In para 5(iv), the applicant contends that no allegation of malice, corruption or culpable negligence has been made against him in the memorandum of charge (Annexure –A1).
Misconduct may take different forms and may have several dimensions, including malice, corruption or culpable negligence. In the present case, the charges relate, inter alia, to alleged failure to properly verify the stocks of cement and bitumen, failure to notice sub-contracting and the placing on record of false Test Certificates relating to cement. The respondent contend that these allegations have dimensions of negligence and other forms of misconduct. Therefore, on the face of it, the absence of specific words such as malice, corruption or culpable negligence in the charge memorandum may not, by itself, constitute a convincing ground for interference.
Further, in para 5(v), the applicant contends that none of the ingredients constituting misconduct has been established against him, yet he has been unjustly punished.
The applicant has not specified in this ground the basis on which he contends that the ingredients of misconduct have not been proved or in what manner the respondent have erred in reaching their conclusions.
Thus, considered in isolation, this ground also does not provide a specific basis for interference. However, we understand this contention as essentially raising the broader issue of the alleged absence or insufficiency of evidence against the applicant.
In para 5(vi), the applicant contends that there is no iota of evidence placed in the inquiry finding him guilty and that there is no evidence establishing the ingredients of misconduct in relation to the duties discharged by him. According to him, despite having committed no misconduct, he has been unjustly punished by the respondent on account of non-application of mind to the entire circumstances of the case.
Essentially, the applicant seeks to contend that there is no evidence at all against him. At the time of arguments, learned counsel for the applicant emphasised that the responsibilities attributed to the applicant were never entrusted to him. It was contended that he was still under training, was newly recruited and was not yet competent to hold such a post or perform the work in question, but was nevertheless required by the respondent to discharge those functions.
Learned counsel further emphasised that the Inquiry Officer had rightly concluded that the first three charges were not proved and that only the fourth charge was partially proved. Even the fourth charge, according to the applicant, was not proved because it was not his responsibility either to sample-check the quality of cement or to send the samples to the concerned laboratory. His responsibility was limited to keeping the test reports received by him on record. Therefore, according to the applicant, merely filing the documents received by him could not justify the imposition of a penalty.
We shall return to this recurring contention of the applicant regarding the alleged absence of evidence while considering the scope of judicial review and the material available on record.
In para 5(vii), the applicant contends that, before imposing any punishment, the respondent was required to apply his mind fully to the facts and circumstances of the case, in addition to the attributes of “misconduct” judicially and universally accepted. According to the applicant, the respondent has punished him arbitrarily despite the fact that he has not committed any misconduct.
The respondent, on the other hand, contend that a detailed inquiry was conducted and that, after following the prescribed procedure, the Disciplinary Authority rightly arrived at the conclusion that Charge Nos. 1, 3 and 4 were partially proved and Charge No. 2 was not proved. According to the respondent, the applicant had accepted the responsibility entrusted to him and had been discharging those functions, although he was at an early stage of his service. Being a qualified engineer, he could reasonably be expected, according to the respondent, to understand the functions of a Site Engineer and to verify the stocks of cement and bitumen arriving at the site, identify any sub-contracting prohibited under the contract and satisfy himself regarding the reliability of quality certificates relating to cement.
At the time of arguments, learned counsel for the applicant sought to justify the quality of the cement by pointing out that the life of the work was only a decade, yet the work continued to be in use without requiring further repair and maintenance. It was further submitted that reports indicated that the work remained in good physical condition and had also received certain awards for quality.
Learned counsel for the applicant further submitted that there were two levels of cement quality control. Samples from each lot were taken at the site and tested in the Departmental Laboratory, and all such test reports were satisfactory. The second test, involving the sending of samples to an engineering college, was the responsibility of the contractor, and no responsibility for the same could be fastened upon the applicant. According to learned counsel, therefore, the charges were essentially theoretical and had not been proved against the applicant.
Thus, even in this ground, the principal contention of the applicant is that the Disciplinary Authority failed to properly appreciate the evidence on record, including the nature and extent of the responsibilities actually entrusted to the applicant.
In para 5(viii), the applicant contends that the impugned order dated 08.03.2022 at Annexure: A-8 is contrary to the acceptable evidence on record and is based on surmises and conjectures. It is, therefore, alleged to be arbitrary on account of non-application of mind to the facts and circumstances of the case and hence unsustainable in law. It is further contended that the decisions taken by the respondent are unsustainable in law if the evidence on record is examined dispassionately.
Essentially, the applicant is challenging the quality and sufficiency of the evidence and contending that there is no evidence sufficient to substantiate the charges against him and, consequently, that the imposition of penalty reflects non-application of mind.
The respondent, in reply, have referred to the detailed inquiry and the oral and documentary evidence adduced therein. They have also placed before us the relevant files concerning the issuance of the disagreement note and the decision to impose the penalty. According to them, the prescribed procedure was followed, the principles of natural justice were adhered to, oral and documentary evidence was properly considered, and the applicant was afforded ample opportunity to cross-examine witnesses, represent his case and place his defence.
The respondent further emphasised that the disagreement note had treated Charge No. 2 relating to bitumen stock as proved, contrary to the finding of the Inquiry Officer. However, after considering the applicant’s reply, the Disciplinary Authority ultimately treated Charge No. 2 as not proved. According to the respondent, this distinction between the disagreement note and the final penalty order itself demonstrates that the Disciplinary Authority carefully considered the applicant’s defence and did not mechanically adopt the conclusions contained in the disagreement note.
We have examined this aspect with reference to the record before us. The facts borne out from the record show that the disagreement note disagreed with the Inquiry Officer’s finding in respect of bitumen stock also, but, after considering the applicant’s response, the Disciplinary Authority ultimately treated Charge No. 2 as not proved. Therefore, this aspect does not support the applicant’s contention of non-application of mind.
In para 5(ix), the applicant contends that the Inquiry Officer has arrived at a correct finding of fact. In respect of Article-IV of Charge, according to him, the finding of fact is correct, but the conclusion that the charge was partly proved merely on account of the placement of false and fabricated test certificates submitted by the contractor is fallacious in the absence of a finding that the applicant was aware that the certificates were false and fabricated and nevertheless placed them on record. According to the applicant, there was no occasion for him to doubt the genuineness of the certificates because the results recorded therein matched the tests conducted in the field laboratory, which was in the charge of AGE (I), functioning under the direct control and command of the Chief Engineer (AF).
The respondent, on the other hand, contend that, had the applicant remained sufficiently alert, he could have noticed irregularities in the manner in which cement was being brought to the site. They point out that several vehicles stated to have transported cement were subsequently traced through the RTO and found to have registration numbers belonging to two-wheelers. According to the respondent, this demonstrated that there were discrepancies at an earlier stage itself. These circumstances, according to the respondent, have to be considered along with the allegation concerning fabricated and false certificates relating to the quality of cement submitted by the contractor.
The respondent further contend that, although the applicant may have received and filed the certificates in a passive manner, he cannot thereby completely absolve himself of responsibility for placing the certificates on record. According to them, the matter cannot be examined in isolation and the totality of the functions of a Site Engineer, who was required to be present at the site and remain alert to the activities taking place there, has to be considered.
The respondent further contend that the Disciplinary Authority considered the evidence of different witnesses as well as the documentary material relating to the events and arrived at conclusions in respect of all four charges, namely, that Charge Nos. 1, 3 and 4 were partially proved and Charge No. 2 was not proved. The Disciplinary Authority thereafter imposed the penalty. According to the respondent, there is therefore no infirmity in the impugned order.
We shall consider this aspect further while examining the question of re-appreciation of evidence and the adequacy of the evidence available on record.
In para 5(x), the applicant contends that the impugned order is arbitrary and is a non-speaking order and hence unsustainable in law.
At the time of arguments, learned counsel for the applicant emphasised this contention and pointed out that the impugned order of the Disciplinary Authority dated 08.03.2020 is brief and cryptic, is non-speaking, and has imposed a major penalty which has resulted in the applicant becoming junior to several persons who were junior to him. It was submitted that his juniors have since obtained promotions and that his upward mobility has been seriously affected, with more than 500 persons having gone ahead of him.
The applicant further contends that the penalty of reduction to a lower stage in the time-scale of pay by one stage for a period not exceeding three and half years, without cumulative effect, is harsh and disproportionate. It is also contended that the order of the Disciplinary Authority does not indicate in what manner the applicant’s reply to the disagreement note was considered and appreciated, since the order does not deal with the contentions raised by the applicant.
The respondent, on the other hand, submit that, since there was a joint inquiry and the President himself was the Disciplinary Authority, the order in a Presidential proceeding would necessarily be a summary order, while the detailed consideration and deliberations would be reflected in the file. The respondent have accordingly placed the entire original file before us, in which the decision was taken.
The applicant, however, contends that the Disciplinary Authority’s order is cryptic and non-speaking and does not disclose the consideration given to the issues and grounds raised by him in his reply to the disagreement note. According to the applicant, if the reasoning remains confined to the file and is not communicated to him, he would not be in a position to defend himself against the conclusions, since he would not know the reasons on the basis of which the findings have been recorded. It is, therefore, submitted that, viewed from any angle, the impugned order is not a speaking order and that the procedure adopted has failed to satisfy the requirements of natural justice.
From the ten grounds raised by the applicant in para 5 of the OA, it is evident that most of them relate to the sufficiency of evidence and the conclusions drawn by the respondent that Charge Nos. 1, 3 and 4 were partially proved. The principal procedural issue raised by the applicant is that the order of the Disciplinary Authority is non-speaking and does not disclose the reasons for rejecting the contentions raised by him in response to the disagreement note. According to the applicant, this demonstrates non-application of mind by the Disciplinary Authority.
We have carefully examined the entire record. Annexure – A1 is the charge memorandum dated 09.02.2018, which has not been challenged and which, on examination, is found to be in order. Annexure – A2 dated 05.04.2018 is the applicant’s reply to the charge memorandum. Annexure – A3 dated 09.02.2018 records the decision to hold a joint inquiry and provides that the President shall function as the Disciplinary Authority for the purpose of the common proceedings.
Annexure – A4 is the common Inquiry Report. It is detailed and records reasons for concluding that Charge Nos. 1, 2 and 3 were not proved and that only Charge No. 4 was partially proved against the applicant. Annexure – A5 dated 07.12.2019 is the true copy of the Inquiry Report in respect of the applicant. It is also detailed and contains reasons supporting the conclusions reached by the Inquiry Officer.
Annexure – A6 dated 13.09.2021 is the true copy of the letter of the respondent enclosing the Inquiry Report and the disagreement note. The disagreement note is detailed and sets out the reasons for the Disciplinary Authority’s disagreement with the Inquiry Officer’s conclusions in respect of Charges Nos. 1, 2 and 3. The reasons for disagreement were thus communicated to the applicant, and he was afforded an opportunity to submit his representation against the tentative conclusions of the Disciplinary Authority.
Annexure – A7 dated 25.11.2021 is the true copy of the applicant’s representation on the Inquiry Report and disagreement note. The representation itself demonstrates that the applicant availed himself of the opportunity afforded to him to be heard.
Annexure – A8 dated 08.03.2022 is the punishment order of the Disciplinary Authority. The order records that, after considering the replies to the disagreement note and the entire record, the Disciplinary Authority concluded that the charges under Article I, III and IV of the Charge Memorandum stood partially proved against the applicant.
It is significant that this conclusion is not identical to the position reflected in the disagreement note. In the disagreement note, the Disciplinary Authority had indicated reasons for disagreeing with the Inquiry Officer in respect of Charges Nos. 1, 2 and 3. However, after considering the applicant’s reply, the Disciplinary Authority did not sustain the tentative conclusion in respect of Charge No. 2 and ultimately treated that charge as not proved, as had been concluded by the Inquiry Officer. This circumstance is relevant while examining the applicant’s contention that his reply to the disagreement note was not considered.
The applicant has also filed two documents, namely, the true copy of the respondent’ order dated 08.03.2022 (Annexure – A9) exonerating MES-610927, Shri V. Simhachalam, JE, and the true copy of the order dated 05.02.2020 exonerating MES-316016, Shri Rohitasva Kumar Meena, AE. However, as those orders are based on facts of the cases of those officers is no way relevant.
From the aforesaid material, it is evident that a detailed inquiry was conducted in accordance with the prescribed procedure and that ample opportunity of hearing was afforded to the applicant. The applicant has not identified any procedural irregularity in the conduct of the inquiry. He has not challenged the charge sheet or the Inquiry Officer’s report. His principal challenge is to the conclusion that Charge No. 4 was partially proved and to the subsequent conclusions of the Disciplinary Authority in respect of Charges Nos. 1, 3 and 4.
In substance, therefore, the applicant seeks re-appreciation of the evidence and invites us to examine the matter as an appellate authority over the Inquiry Officer and the Disciplinary Authority. His principal grievance is with the adequacy and appreciation of the evidence relied upon to establish the charges.
The applicant has also contended that he was still under probation and training, was inexperienced and had been placed in a complex assignment. In support of this contention, he has placed before us a document titled “Air Field Works: Quality Control” vide Pol Letter No.17/2006 and No.37696/Gen/Pol/E2W(PPC) dated 06.10.2006, particularly para 5, which reads as follows:-
“5.It should be the endeavour to ensure that executives deployed for the airfield works should have executed runway works before. Under no circumstances will work commence unless above requirement is fulfilled. All executives (GEs/AGEs/JEs) executive the runway construction/resurfacing works for the first time will visit at least one of the runway works in progress and also SEM Wing, CME for training.”
A plain reading of the aforesaid provision only indicates that executives deployed for airfield works should preferably have prior experience of executing runway works and that those executing runway construction/resurfacing works for the first time should visit an ongoing runway work and the SEM Wing, CME, for training. The provision, however, does not establish that the applicant was exempted from the ordinary responsibilities attached to the post which he was occupying. Nor does it show that the duties forming the subject matter of the charges were beyond the scope of his functions merely because he was under training or probation.
The applicant was required to discharge the functions entrusted to him even during the period of training and probation. Accordingly, this defence does not, by itself, provide a basis for interference with the findings recorded in the disciplinary proceedings.
We have also examined the oral and documentary evidence placed before the Inquiry Officer. A substantial body of evidence was produced and systematically documented, and the conclusions were reached after considering that material.
It is well settled that, in disciplinary proceedings, the scope of judicial review is limited. The Tribunal does not ordinarily sit as an appellate authority over the findings recorded by the Inquiry Officer or the Disciplinary Authority and cannot re-appreciate the evidence merely because another view may be possible. In the present case, therefore, we cannot assume the role of an appellate authority and undertake a fresh appreciation of the entire evidence.
From the material before us, this is certainly not a case of ‘no evidence’, as contended by the applicant. The applicant has also not identified any specific deficiency in the disagreement note itself. On the contrary, he submitted a detailed response to the disagreement note before the Disciplinary Authority.
The principal grievance of the applicant is that the Disciplinary Authority did not disclose in the final order the manner in which his reply to the disagreement note was considered and the reasons why Charge Nos. 1, 3 and 4 were ultimately held to be partially proved. According to the applicant, the final order is brief, cryptic and non-speaking.
The respondent, on the other hand, contend that a Presidential Order need not reproduce in detail the entire reasoning contained in the file. According to them, the relevant reasoning and deliberations are available in the original record and, in any event, the applicant had been given a detailed disagreement note and a full opportunity to respond to the same. The respondent also rely upon the fact that, after considering the applicant’s reply, the President accepted the applicant’s defence in respect of Charge No. 2 and did not treat that charge as proved.
The applicant has also filed, by way of a memo dated 27.08.2026, the Proceedings of Regular Hearing Daily Order Sheet No.28 dated 06.07.2019 and the Submission of Defence Statement in respect of the charges against him. Among the questions put to the applicant was Question No.1, which alleged that there were several corrections/overwritings in the cement portion of the “Bitumen and Cement consumption register” Exhibit No. S-3 on pages 11 and 16 to 19, and asked the applicant to state (a) why the corrections were made, (b) who made the corrections, and (c) which corrections were made during his period. The applicant answered as follows:
Answer for Q.No.1 (a) & (c) There is no correction/overwriting done by me in the column of “Quantity brought at site”, “Total (Cumulative) quantity brought at site” and “consumption in bags”. Last entry done by me is on 16 June 2010.
Answer for Q.No.1 (b) These arithmetical corrections would have been done by E-8 staff during technical check as confirmed by State witness MR. V K Mohanan in answer to question No. 2 of Daily Order Sheet No. 21 dated 29 June 2019 and answer to question No. 3 of Daily Order Sheet No. 23 dated 02 July 2019.
The second question was whether the applicant had connived with the AGE to show that the samples of cement brought to the site were sent to CIT Coimbatore, and whether, having kept the test results purportedly issued by CIT Coimbatore on the office file, he had ever attempted to ascertain whether the test results were genuine.
The applicant answered that, as per the conditions of the contract, acceptance of cement would be based on the 07 days test result conducted at the site laboratory. He stated that he had sent samples of cement to the site laboratory for testing and that the results were issued by the AGE laboratory after conducting the tests at the site laboratory. According to him, the results were satisfactory and, therefore, the cement was recommended for acceptance. He further stated that, for a higher level of quality control, additional testing, which was not mandatory under the Contract Agreement, had been requested from CIT Coimbatore. As per the Contract Agreement, transportation of samples and payment were the responsibility of the contractor. The samples were therefore collected by the contractor and submitted to CIT, and the test results were collected by the representative of the contractor and handed over to the sub-division.
The applicant stated that he had never had any doubt about the genuineness of the documents.
In Question No.3, the applicant was asked whether he had noticed that some of the T&P used at the site was marked as belonging to M/S JKS Construction and, if so, whether this should have raised a doubt in his mind regarding subletting.
The applicant answered that he had seen several machines, tools and plants belonging to different firms engaged in the work, of which a few were marked as M/S JKS. He stated that he assumed that the contractor had hired them from different firms and that he therefore had no doubt regarding subletting. These evidences are material and have been appreciated properly by the respondents while drawing conclusions based on other oral and documentary evidences on record, which shows active and balanced consideration of evidences on record by the respondent authorities.
We have carefully examined all the ten contentions raised by the applicant. We find that, except for the contention relating to the nature and sufficiency of the reasons disclosed in the final order, the grounds substantially seek reconsideration of the sufficiency and appreciation of evidence.
In the light of the judgments of the Hon’ble Apex Court in B.C. Chaturvedi vs. Union of India & others, reported in 1995 (6) SCC 749 and Union of India vs. P. Gunasekaran, reported in 2015 (2) SCC 610, the Tribunal cannot re-appreciate the evidence as an appellate authority. On examination of the records, we are satisfied that the inquiry was conducted in accordance with the prescribed procedure, which has not been shown to have been violated. The applicant was afforded adequate opportunity to defend his case and the principles of natural justice were adhered to.
Consequently, the principal legal issue which remains for consideration is whether the impugned order of the Disciplinary Authority, being brief and precise, can be sustained notwithstanding the applicant’s contention that it is non-speaking.
The respondent contend that Presidential Orders, by their very nature, may be brief and need not reproduce the detailed consideration undertaken in the file. In support of this contention, they have drawn our attention to Rule 15 and the Government of India OM No. 134/1/81-AVD.I dated 13.07.1981, G.I., MHA, D.P.&A.R., which, inter alia, mentions the following:-
“3.Instances have also come to notice where, though the decisions in Disciplinary / Appellate cases were taken by the competent Disciplinary /Appellate Authorities in the files, the final orders were not issued by that authority but only by a lower authority. As mentioned above, the Disciplinary/Appellate / Reviewing Authorities exercise quasi-judicial powers and as such, they cannot delegate their powers to their subordinates. It is therefore, essential that the decision taken by such authorities are communicated by the Competent Authority under their own signatures, and the order as issued should comply with the legal requirements as indicated in the preceding paragraphs. It is only in those cases where the President is the prescribed Disciplinary / Appellate / Reviewing Authority and where the Minister Discerned has considered the case and given his orders that an order may be authenticated by an officer, who has been authorized to authenticate orders in the name of the President.”
The respondent specifically emphasise that, where the decision is taken by a Minister or by the President, the decision is recorded in the file after considering the relevant material and is thereafter authenticated by an officer authorised to authenticate orders in the name of the President. According to them, the final order consequently need not reproduce the entire reasoning contained in the file.
Learned counsel for the applicant, however, has relied upon the judgment of the Hon’ble Apex Court in Mahinder Singh Gill vs. Chief Election Commissioner, reported in AIR 1978 SC 851, wherein, inter alia, at para 8, the Hon’ble Apex Court has observed as follows:-
“ The second equally relevant matter is that when a statutory functionary makes an order based on certain grounds, its validity must be judged by the reasons so mentioned and cannot be supplemented by fresh reasons in the shape of affidavit or otherwise. Otherwise, an order bad in the beginning may, by the time it comes to court on account of a challenge, get validated by additional grounds later brought out. We may here draw attention to the observations of Bose J. in Gordhandas Bhanji Public orders, publicly made, in exercise of a statutory authority cannot be construed in the light of explanations subsequently given by the officer making the order of what he meant, or of what was in Ms mind, or what he intended to, do. Public orders made by public authorities are meant to have public effect and are intended to effect the actings and conduct of those to whom they are addressed and must be construed objectively with reference to the language used in the order itself.”
The submission of learned counsel for the applicant, essentially, is that the aforesaid principle requires the statutory authority, namely, the Disciplinary Authority, to pass a speaking order and that the reasons cannot subsequently be supplemented by reference to the contents of the file. According to the applicant, the order must be communicated to the applicant in a form which enables him to understand the basis of the decision and, if necessary, effectively challenge it. The applicant contends that the reasoning contained only in the internal file is not accessible to him in the ordinary course and, therefore, he would not have a sufficient opportunity to contest the reasons which actually weighed with the Disciplinary Authority.
At the request of the parties, the original file in which the Presidential decision was taken was called for, and the respondent placed the entire file before us.
It is a matter of record that the Presidential file contains detailed consideration of the Inquiry Officer’s conclusions, the disagreement note and the applicant’s reply to the disagreement note. The record demonstrates that, after considering the material available on record, the Disciplinary Authority arrived at the conclusion that Charge Nos. 1, 3 and 4 were partially proved and Charge No. 2 was not proved. The decision was thereafter approved by the Disciplinary Authority and the impugned order was issued and served upon the applicant.
We have carefully examined the relevant portion of the original record and are satisfied that the decision-making process reflects consideration of the material placed before the President. In particular, the difference between the conclusions contained in the disagreement note and those ultimately recorded in the penalty order is material. The disagreement note had treated Charge Nos. 1, 2 and 3 as partly proved, whereas the final decision treated Charge Nos. 1, 3 and 4 as partly proved and Charge No. 2 as not proved. The record indicates that the applicant’s reply was considered and that the tentative view expressed in the disagreement note in respect of Charge No. 2 was not ultimately sustained.
This circumstance supports the respondent’ contention that the applicant’s reply to the disagreement note was not merely received but was considered before the final decision was taken. The record also demonstrates that the decision was not arrived at by mechanically accepting the findings contained in the disagreement note.
At the same time, we observe that, once the penalty had been imposed, the reasoning contained in the file, to the extent it was not confidential, could have been made available to the applicant. The applicant could also seek access to the relevant record in accordance with law, including under the RTI mechanism. The respondent may make available the relevant reasoning to the applicant if he so desires.
The applicant has placed reliance on a large number of case laws. We proceed to examine them seriatim:
Maria Margarida Sequeira Fernandes & others vs. Erasmo Jack De Sequeira (Dead) through LRS, reported in (2012) 5 SCC 370. Learned counsel for the applicant draws our attention to the principles laid down therein that truth must be the guiding star in the judicial process, reflecting the motto Satyameva Jayate (Truth alone triumphs), and that judges and lawyers play equal roles in the administration of justice. It is emphasized that, like judges, lawyers must also ensure that truth triumphs, and judicial officers must leave no stone unturned to ascertain the truth in every matter, giving due weight to the veracity of pleadings and documents.
There can be no disagreement with these unexceptionable propositions. Indeed, we are satisfied that in the present case, truth has ultimately prevailed. Decisions were taken based on oral and documentary evidence adduced through a regular departmental inquiry, wherein the applicant was afforded full opportunity of being heard in complete compliance with the principles of natural justice. Consequently, this citation does not in any manner discredit the inquiry process.
Further, the applicant has quoted S.G. Jaisinghani vs. Union of India & others, reported in AIR 1967 SC 1427, para 14 which speaks the following thing:-
“…….In this context it is important to emphasize that the absence of arbitrary power is the first essential of the rule of law upon which our whole constitutional system is based. In a system governed by rule of law, discretion, when conferred upon executive authorities, must be confined within clearly defined limits. The rule of law from this point of view means that decisions should be made by the application of known principles and rules and, in general, such decisions should be predictable and the citizen should know where he is. If a decision is taken without any principle or without any rule it is unpredictable and such a decision is the antithesis of a decision taken in accordance with the rule of law. (See Dicey-"Law of the Constitution"-Tenth Edn., Introduction ex). "Law has reached its finest moments", stated Douglas, J. United States v. Wunderlick (1), "when it has freed man from he unlimited discretion of some ruler........ Where discretion; absolute, man has always suffered". It is in this sense that the rule of law may be said to be the sworn enemy of caprice. Discretion, as Lord Mansfield stated it in classic terms in the case of John Wilkes (2), "means sound discretion guided by law. It must be governed by rule, not by humour: it must not be arbitrary, vague and fanciful." …..”
While we respectfully agree with the principles enunciated above, we are unable to accept the contention of learned counsel for the applicant that this ruling in any way discredits the present departmental inquiry, the Inquiry Officer's Report, the Disagreement Note, the applicant's representation thereto, or the ultimate penalty order, all of which were rendered pursuant to a detailed inquiry conducted in accordance with the due process of law.
Further, the applicant has relied on A.L. Kalara vs. Project & Equipment Corporation of India Ltd., reported in (1984) 3 SCC 316. He has drawn our attention to paras 19 and 22 which reads the following:
“19.…….From a positivistic point of view equality is antithetic to arbitrariness. In fact equality and arbitrariness are sworn enemies; one belongs to the rule of law in a republic while the other, to the whim and caprice of an absolute monarch. Where an act is arbitrary it is implicit in it that it is unequal both according to political logic and constitutional law and is therefore violative of Art. 14, and if is affects any matter relating to public employment, it is also violative of Art. 16. Arts. 14 and 16 strike at arbitrariness in State action and ensure fairness and equality of treatment." This view was approved by the Constitution Bench in Ajay Hasia case It thus appears well-settled that Art. 14 strikes at arbitrariness in executive/administrative action because any action that is arbitrary must necessarily involve the negation of equality. One need not confine the denial of equality to a comparative evaluation between two persons to arrive at a conclusion of discriminatory treatment. An action per se arbitrary itself denies equal of protection by law. The Constitution Bench pertinently observed in Ajay Hasia's case and put the matter beyond controversy when it said 'wherever therefore, there is arbitrariness in State action whether it be of the legislature or of the executive or of an "authority" under Article 12, Article 14 immediately springs into action and strikes down such State action.' This view was further elaborated and affirmed in D.S. Nakara v. Union of India. In Maneka Gandhi v. Union of India it was observed that Art. 14 strikes at arbitrariness in State action and ensure fairness and equality of treatment. It is thus too late in the day to contend that an executive action shown to be arbitrary is not either judicially reviewable or within the reach of Art. 14……
22.Rule 4 bears the heading 'General'. Rule 5 bears in the heading 'misconduct'. The draftsmen of the 1975 Rules made a clear distinction about what would constitute misconduct. A general expectation of a certain decent behaviour in respect of employees keeping in view Corporation culture may be a moral or ethical expectation. Failure to keep to such high standard of moral, ethical or decrous behaviour befitting an officer of the company by itself cannot constitute misconduct unless the specific conduct falls in any of the enumerated misconduct in Rule 5. Any attempt ' to telescope Rule 4 into Rule 5 must be looked upon with apprehension because Rule 4 is vague and of a general nature and what is unbecoming of a public servant may vary with individuals and expose employees to vagaries of subjective evaluation. What in a given context would constitute conduct unbecoming of a public servant to be treated as misconduct would expose a grey area hot amenable to objective evaluation. Where misconduct when proved entails penal consequences, it is obligatory on the employer to specify and if necessary define it with precision and accuracy so that any ex post facto interpretation of some incident may not be camouflages as misconduct. It is not necessary to dilate on this point in view of a recent decision of this Court in M/s Glaxo Laboratories (I) Ltd. v. Presiding officer, Labour Court, Meerut & Others where this Court held that 'everything which is required to be prescribed has to be prescribed with precision and no argument can be entertained that something not prescribed can yet be taken into account as varying what is prescribed. In short it cannot be left to the vagaries of management to say ex post facto that some acts of omission or commission nowhere found to be enumerated in the relevant standing or is nonetheless a misconduct not strictly falling within the enumerated misconduct in the relevant standing order but yet a misconduct for the purpose of imposing a penalty.' Rule 4 styled as 'General' specifies a norm of behaviour but does not specify that its violation will constitute misconduct. In Rule 5, it is nowhere stated that anything violative of Rule 4 would be per as a misconduct in the sub-clauses of Rule 5 which specifies misconduct. It would therefore appear that even if the facts alleged in two heads of charges are accepted as wholly proved, yet that would not constitute misconduct as prescribed in Rule 5 and no penalty can be imposed for such conduct. It may as well be mentioned that Rule 25 which prescribes penalties specifically provides that any of the penalties therein mentioned can be imposed on an employee for misconduct committed by him. Rule 4 does not specify a misconduct.”
This decision deals with the concepts of equality, non-arbitrariness, and the requirement of defining misconduct with precision. Relying on this precedent, the applicant contends that his alleged acts cannot be classified as misconduct and that no penalty could be imposed on him. The respondents, on the other hand, have clearly established on record that a thorough inquiry was conducted wherein oral and documentary evidence was adduced, and full opportunity of being heard was extended to the applicant at every stage in conformity with the principles of natural justice. The Disagreement Note issued by the Disciplinary Authority was detailed, and the applicant's reply thereto was examined at the highest level, demonstrating due application of mind. Indeed, clear application of mind is evident from the fact that while the Disagreement Note tentatively considered Charge No. 2 as partly proved along with Charges 1, 3, and 4, the Disciplinary Authority ultimately arrived at an independent final finding holding Charge Nos. 1, 3, and 4 as partially proved, while holding Charge No. 2 as not proved.
This Court, sitting in judicial review, cannot step into the shoes of the Appellate Authority to re-appreciate the evidence or re-evaluate its sufficiency. We explicitly record that there is a plethora of evidence on record supporting the conclusions reached. The record demonstrates that proper and legitimate inferences were drawn to hold Charge Nos. 1, 3, and 4 partially proved and Charge No. 2 not proved, followed by the imposition of a proportionate penalty. Consequently, this citation does not assist the applicant.
Further, the applicant has relied on Debasis Das vs Canara Bank, reported in (1992) 2 LLJ 697, wherein our attention is drawn to paras 10 to 12 which reads the following:-
“10.Having carefully gone through the entire judgment in the case of Kalra (supra) and applying the same in the facts of the instant case, I am unable to accept the contention of Mr. Chakraborthy. The observation of the Supreme Court in the case of Kalra (supra) that where misconduct when proved entails penal consequences, it is obligatory on the employer to specify and, if necessary, define it with precision and accuracy so that any ex post facto interpretation of some incident may not be camouflaged as misconduct, is one of general application for, if that is not so done, a public servant may be exposed to vagaries of subjective evaluation as pointed out by the Supreme Court in that case. That the Bank is also conscious of the above proposition is evident from the fact that after framing Regulation 3 under the heading 'General', it has in Regulations 4 to 23, specified with precision and accuracy,duties and obligations of its officers, breach of which will amount to a misconduct under Regulation 24. From a careful perusal of the Regulations 4 to 23, it is evident that for breach of any of them, an inference can be legitimately drawn that an officer has not taken all possible steps to ensure and protect the interests of the Bank and/or has not discharged his duties with utmost integrity, honesty, devotion and diligence and/or had done something, which is unbecoming of a Bank Officer and thereby has committed a breach of Regulation 3(1) also For example; Regulation 4, which comes under the heading "Observance of Secrecy' provides, inter alia, that every Bank Officer shall maintain strictest secrecy regarding the Bank's affairs and, therefore, needless to say, breach of the above Regulation amounts to breach of all the three norms laid down under Regulation 3(1). To cite another example: Regulation 12 comes under the heading "Seeking to influence" and it says that no officer shall try to influence either politically or otherwise his superiors to further his own interest in respect of matter pertaining to his service under the Bank. By committing breach of the above provision, it can be certainly said that the concerned Officer has not acted with utmost integrity and/ or has displayed a conduct unbecoming of a Bank Officer, in two of the norms laid down in Regulation 3(1).
11.From the above discussion, it follows therefore, that if Regulation 3(1) has to be treated as an independent provision, breach of which will amount to a 'misconduct' by the deeming provision of Regulation 24, there was no need to frame Regulations 4 to 23. That apart, if read in isolation, the above Regulation will suffer from the indefensible attack of laying down certain norms without laying down any objective criteria for its assessment or evaluation. I am, therefore, of the opinion that when Regulation 24 says "a breach of any of the provisions of these Regulations shall be deemed to constitute misconduct", it does not and cannot mean and include Regulation 3(1), and for that matter, any other clause of Regulation 3. In forming this opinion, I have drawn sustenance from, apart from the foregoing discussion, the nature of the contents of Clauses (2) and (3) of the Regulation 3, which have been earlier quoted. As has been noticed, Clause (3) of Regulation 3, asks the officer to act according to his best judgment except when acting under the direction of his official superior. Now, can an officer be said to have violated the above Regulation and thereby committed a 'misconduct' if the Disciplinary Authority in its 'judgment' feels that the concerned officer has made an error in his 'judgment'? The answer must be an emphatic no, for an error of judgment cannot be culpable.
12.In my view any other interpretation would mean that an officer of the Bank may be departmentally proceeded against on the ground that he had acted in a manner unbecoming of a Bank Officer for dishonour of cheque issued by him in liquidation of personal debts, if the Disciplinary Authority feels that such a conduct of the concerned officer belies its moral and ethical expectation. Such an assessment would be purely subjective and would vary with individuals. While on this point, a reference, by way of illustration, may be made to Regulation 6(1) of the Conduct Regulations, which provides that no officer shall, except with the previous sanction of the Bank engage directly or indirectly in any trade or business or undertake other employment. Breach of the Regulation can be proved by objective standards only and there is no scope of subjective evaluation in deciding the same. It is of course true that if wilful dis-obediene of a lawful order amounts to misconduct, it can be objectively evaluated and assessed but then the authority concerned has not taken recourse to, nor referred to, any Regulation to indicate that it is a misconduct.”
The applicant relies on this precedent to contend that where misconduct entails penal consequences, the employer is obligated to specify and define it with precision, that an error of judgment is distinct from misconduct, and that willful disobedience of orders amounts to misconduct. However, this contention goes to the fundamental validity of the charges—a challenge that the applicant never raised at the initial stage. Having participated in the inquiry without challenging the relevance or maintainability of the charge sheet, it is not open to the applicant at this stage to contend that the charges are meaningless or that no misconduct was committed. Four distinct charges were framed against the applicant, a detailed inquiry was held, and oral as well as documentary evidence was adduced, on the basis of which the respondents arrived at a reasoned decision through due process. In our opinion, this citation also does not in any way discredit the respondents' decision.
Further, the applicant relied on Rajasthan State Electricity Board vs. Iqbal Singh, reported in 1996 LAB I.C. 1526, wherein our attention is drawn to paras 16 to 18 which reads the following:-
“16.'Misconduct' and 'negligence' are two different notions. According to Aiyer's Law of Lexicon, 'misconduct' implies a wrongful intention and not a mere error of justice. According to Stroud's Judicial Dictionary, 'misconduct' means misconduct arising from ill-motive. Act of negligence, error of judgment or innocent mistake, does not constitute such 'misconduct: The Supreme Court in Union of India v. J. Ahmed (AIR 1979 SC 1022: (1979 Lab IC 792) held that:-
"Lack of efficiency, failure to attain the highest standard of administrative ability while holding a high post would not themselves constitute misconduct. There may be negligence in performance of duty and a lapse in performance of duty or error of judgment in evaluating the developing situation may be negligence in discharge of duty but would not constitute misconduct unless the consequences directly attributable to negligence would be such as to be irreparable or the resultant damage would be so heavy that the degree of culpability would be very high."
The Apex Court further held that:-
“ Gross or habitual negligence in performance of duty may not involve mens rea but may still constitute misconduct for disciplinary proceedings.”
17.In: M. Krishna Swami v. Union of India (JT 1992 (5) SC 92) the Supreme Court held that :-
“ Misconduct is said to be a vague and relative term. Literally it means a wrong conduct or improper conduct. It has to be construed with reference to the subject matter and the context wherein the term used having regard to the scope of the Act and the statute.”
The Apex Court further held that :-
" Every act or conduct or even error of judgment on negligent acts by higher judiciary per se does no amount to misbehaviour. Wilful abuse of judicial office, wilful misconduct in the office, corruption, lack of integrity or any other offence involving moral turpitude would be misbehaviour. Misconduct implies actuation of some degree of mens rea by the doer. Even administrative action or omissions too need accompaniment of mens rea."
18.'Misconduct' is a violation of definite law, a forbidden act and it differs from carelessness or negligence. The expression 'misconduct' covers a large area of human conduct and the term has to be construed with reference to the subject and context in which it is used. Regulation 5 of the Regulations, 1962 provides that the punishment enumerated in the Regulations can be imposed for good and sufficient reasons to be recorded. The expression "good and sufficient reasons" used in this regulation clearly shows that each and every error does not constitute the ground for imposition of the punishment. The expression "good and sufficient reason" has to be read in a reasonable manner, for otherwise the words will become too vague and bereft of the guidelines. To fall within the scope of Regulation 5 the mere error of judgment or a bona fide mistake does not furnish a ground for punishment to be imposed. Error of judgment cannot be eliminated in all human affairs. Negligence in the performance of duty, error of judgment and an innocent mistake will not constitute misconduct unless it is actuated by ill-motive and a wilful act. A wilful and intentional disobedience of the instruction of the superior authority will amount to misconduct. If the decision taken by the officer reflects that it has been taken with ulterior corrupt motive then it will, also, constitute 'misconduct'. To fall within the definition of the 'misconduct' while doing something the doer must know that he is wrong. An inadvertent violation of certain instructions of the superiors without any ulterior motive, would not amount to 'misconduct' for which the penalty can be imposed unless the conduct is a calculated attempt to defy the order passed by the superiors or to violate the instructions.”
The applicant emphasizes that misconduct implies a violation of a definite law or a forbidden act, as distinguished from carelessness or negligence, and asserts that the allegations against him did not amount to misconduct. We differ with learned counsel for the applicant and find that this judgment does not support his case in any manner. The charge sheet itself defined the four heads of alleged misconduct in explicit terms, and the applicant never challenged the validity of the charge sheet.
Further, the applicant counsel cites Inspector Prem Chand vs. Govt. of NCT of Delhi & others, reported in (2007) 4 SCC 566, wherein our attention is drawn to para 12 which reads the following:-
“12.It is not in dispute that a disciplinary proceeding was initiated against the appellant in terms of the provisions of the Delhi Police (Punishment and Appeal) Rules, 1980. It was, therefore, necessary for the disciplinary authority to arrive at a finding of fact that the appellant was guilty of an unlawful behaviour in relation to discharge of his duties in service, which was willful in character. No such finding was arrived at. An error of judgment, as noticed hereinbefore, per se is not a misconduct. A negligence simpliciter also would not be a misconduct. In Union of India & Ors. vs. J. Ahmed (1979 (2) SCC 286), whereupon Mr. Sharan himself has placed reliance, this Court held so stating:
"11.Code of conduct as set out in the Conduct Rules clearly indicates the conduct expected of a member of the service. It would follow that conduct which is blameworthy for the Government servant in the context of Conduct Rules would be misconduct. If a servant conducts himself in a way inconsistent with due and faithful discharge of his duty in service, it is misconduct (see Pierce v. Foster, 17 Q.B. 536, 542). A disregard of an essential condition of the contract of service may constitute misconduct [see Laws v. London Chronicle (Indicator Newspapers, 1959 1 WLR 698)]. This view was adopted in Shardaprasad Onkarprasad Tiwari v. Divisional Superintendent, Central Railway, Nagpur Division, Nagpur, (61 Bom LR 1596), and Satubha K. Vaghela v. Moosa Raza (10 Guj LR 23). The High Court has noted the definition of misconduct in Stroud's Judicial Dictionary which runs as under:
" Misconduct means, misconduct arising from ill motive; acts of negligence, errors of judgment, or innocent mistake, do not constitute such misconduct." [Emphasis supplied]
Relying on this judgment, the applicant contends that to establish misconduct, there must be a finding of willful unlawful behavior in the discharge of duties, that mere error of judgment or negligence simpliciter does not amount to misconduct, and that his conduct conformed to the applicable conduct rules. However, these assertions are unfounded. On a holistic appraisal of the totality of the evidence before us, we agree with the findings and conclusions reached by the respondents and hold that this citation does not assist the applicant in any way.
Further, the applicant relies on Krushnakant B. Parmar vs. Union of India & others, reported in (2012) 3 SCC 178, wherein our attention is drawn at paras 16 to 19 which reads the following:-
“15.In the case of appellant referring to unauthorised absence the disciplinary authority alleged that he failed to maintain devotion of duty and his behaviour was unbecoming of a Government servant.
16.The question whether `unauthorised absence from duty' amounts to failure of devotion to duty or behaviour unbecoming of a Government servant cannot be decided without deciding the question whether absence is wilful or because of compelling circumstances.
17.If the absence is the result of compelling circumstances under which it was not possible to report or perform duty, such absence can not be held to be wilful.
18.Absence from duty without any application or prior permission may amount to unauthorised absence, but it does not always mean wilful. There may be different eventualities due to which an employee may abstain from duty, including compelling circumstances beyond his control like illness, accident, hospitalisation, etc., but in such case the employee cannot be held guilty of failure of devotion to duty or behaviour unbecoming of a Government servant.
19.In a Departmental proceeding, if allegation of unauthorised absence from duty is made, the disciplinary authority is required to prove that the absence is wilful, in absence of such finding, the absence will not amount to misconduct.
20.In the present case the Inquiry Officer on appreciation of evidence though held that the appellant was unauthorisedly absent from duty but failed to hold the absence is wilful; the disciplinary authority as also the Appellate Authority, failed to appreciate the same and wrongly held the appellant guilty.”
We have carefully perused the cited decision, which arose in the specific context of unauthorized absence and examined when such absence amounts to a willful failure to maintain devotion to duty. The facts and allegations in the present proceedings are entirely distinct. In our opinion, this decision neither strengthens the case of the applicant nor impairs the findings of the respondents.
Further, the applicant reliefs on M.S. Bindra vs. Union of India & others, reported in (1998) 7 SCC 310, wherein our attention is drawn at para 13 which reads the following:-
“13.While viewing this case from the next angle for judicial scrutiny i.e. want of evidence or material to reach such a conclusion, we may add that want of any material is almost equivalent to the next situation that from the available materials no reasonable man would reach such a conclusion. While evaluating the materials the authority should not altogether ignore the reputation in which the officer was held till recently. The maxim "Nemo Firut Repente Turpissimus" (no one becomes dishonest all on a sudden) is not unexceptional but still it is a salutary guideline to judge human conduct, particularly in the field of Administrative Law. The authorities should not keep the eyes totally closed towards the overall estimation in which the delinquent officer was held in the recent past by those who were supervising him earlier. To dunk an officer into the puddle of "doubtful integrity" it is not enough that the doubt fringes on a mere hunch. That doubt should be of such a nature as would reasonably and consciously be entertainable by a reasonable man on the given material. Mere possibility is hardly sufficient to assume that it would have happened. There must be preponderance of probability for the reasonable man to entertain doubt regarding that possibility. Only then there is justification to ram an officer with the label "doubtful integrity".”
This authority deals with the standards of judicial scrutiny, the evaluation of evidence, and the principle that the past reputation of an officer should not be ignored, guided by the maxim nemo fuit repente turpissimus (no one becomes dishonest all of a sudden). While the applicant asserts that he is not an officer of doubtful integrity, these observed principles are general propositions of law that cannot undermine the systematic departmental inquiry conducted in accordance with prescribed procedure and the principles of natural justice by the respondents. Hence, this citation does not strengthen the applicant's case.
Further, the applicant relies on Kuldeep Singh vs. Commissioner of Police & others, reported in (1999) 2 SCC 10, wherein our attention is drawn at para 8 which reads the following:-
“8.The findings, recorded in a domestic enquiry, can be characterised as perverse if it is shown that such a finding is not supported by any evidence on record or is not based on the evidence adduced by the parties or no reasonable person could have come to those findings on the basis of the that evidence. This principle was laid down by this Court in State of Andhra Pradesh vs. Sree Rama Rao. 1964 2 LLJ 150 = AIR 1963 SC 1723 = 1964 (3) SCR 25, in which the question was whether the High Court, under Article 226, could interfere with the findings recorded at the departmental enquiry. This decision was followed in Central Bank of India vs. Prakash Chand Jain, 1969 2 LLJ 377 (SC) = AIR 1969 SC 983 and Bharat Iron Works vs. Bhagubhai Balubhai Patel & Ors. 1976 Labour & Industrial Cases 4 (SC) = AIR 1976 SC 98 = 1976 (2) SCR 280 = (1976) 1 SCC 518. In Rajinder Kumar Kindra vs. Delhi Administration through Secretary (Labour) and Others. AIR 1984 SC 1805 = 1985 (1) SCR 866 = (1984) 4 SCC 635, it was laid down that where the findings of misconduct are based on no legal evidence and the conclusion is one to which no reasonable man could come, the findings can be rejected as perverse. It was also laid down that where a quasi-judicial tribunal records findings based on no legal evidence and the findings are his mere ipse dixit or based on conjectures and surmises, the enquiry suffers from the additional infirmity of non-application of mind and stands vitiated.”
This judgment lays down that findings in a domestic inquiry can be characterized as perverse only if they are unsupported by any evidence on record, are contrary to the evidence adduced, or are such that no reasonable person could have arrived at them on the basis of that evidence. However, the findings against the present applicant cannot be said to be devoid of evidence. On the contrary, there is voluminous oral and documentary evidence on record, which was evaluated at three distinct stages: first, by the Inquiry Officer; second, by the Disciplinary Authority while framing the Disagreement Note; and third, by the Disciplinary Authority after considering the applicant's reply alongside the Disagreement Note and IO Report to pass the final penalty order. We find that this citation does not in any way discredit the findings or the quantum of punishment imposed by the Disciplinary Authority.
Further, the applicant cites Union of India vs. H.C. Goel, reported in AIR 1964 SC 364, wherein our attention is drawn at para 27 which reads the following:-
“27.Now, in this state of the evidence, how can it be said that respondent even attempted to offer a bribe to Mr. Rajagopalan. Mr. Rajagopalan makes a definite statement that respondent did not offer him a bribe. He merely refers to the fact that respondent took out a paper from his wallet and the said paper appeared to him like a hundred rupee note double folded. Undoubtedly, Mr. Rajagopalan suspected the respondent's conduct, and so, made a report immediately. But the suspicion entertained by Mr. Rajagopalan cannot, in law, be treated as evidence against the respondent even though there is no doubt that Mr. Rajagopalan is a straightforward and an honest officer. Though we fully appreciate the anxiety of the appellant to root out corruption from public service, we cannot ignore the fact that in carrying out the said purpose, mere suspicion should not be allowed to take the place of proof even in domestic enquiries. It may be that the technical rules which govern criminal trials in courts may not necessarily apply to disciplinary proceedings, but nevertheless, the principle that in punishing the guilty scrupulous care must be taken to see that the innocent are not punished, applies as much to regular criminal trials as to disciplinary enquiries held under the statutory rules. We have very carefully considered the evidence led in the present enquiry and borne in mind the plea made by the learned AttorneyGeneral, but we are unable to hold that on the record, there is any evidence which can sustain the finding of the appellant that charge No. 3 has been proved against the respondent. It is in this connection and only incidentally that it may be relevant to add that the U.P.S.C. considered the matter twice and came to the firm decision that the main charge against the respondent had not been established.”
This judgment emphasizes that although technical rules governing criminal trials do not strictly apply to disciplinary proceedings, scrupulous care must nevertheless be taken to ensure that an innocent person is not penalized on mere suspicion. The applicant asserts complete innocence; however, where a regular inquiry was held in accordance with due process and a plethora of oral and documentary evidence was adduced leading the respondents to conclude that Charge Nos. 1, 3, and 4 stand partially proved against him, we find no basis to accept the applicant's plea of complete innocence. The charges relate to basic supervisory functions: receiving and accounting for stocks of cement and bitumen, monitoring site execution to check for potential sub-contracting, and ensuring proper quality checks of cement rather than mechanically placing contractor-supplied quality reports on record.
From the applicant's submissions, he seeks to plead that he was completely untrained and understood his duties to be restricted solely to maintaining entries in stock registers. We respectfully disagree with this submission. These basic supervisory functions represent core and essential duties expected of any site engineer or site supervisor. They are neither so technical nor so complex that a probationer or less experienced person could not have satisfactorily discharged them. Consequently, we also reject his plea that he ought not to have been assigned such work due to lack of experience. Thus, we are unable to find that this decision supports the case of the applicant or discredits the findings of the respondents.
Further, the applicant has relied on Union of India and others vs. Gyan Chand Chattar, reported in (2009) 12 SCC 78, wherein our attention is drawn at paras 20 and 21 which reads the following:-
“20.So far as charge no.6 i.e. asking for 1% commission for making the payment of pay allowances is concerned, the learned Single Judge has appreciated the evidence of all the witnesses examined in this regard and came to the conclusion that not a single person had deposed before the Enquiry Officer that the respondent employee had asked any person to pay 1% commission for making payment of their allowances. It was based on hearsay statements. All the witnesses stated that this could be the motive/reason for not making the payment.
21.Such a serious charge of corruption requires to be proved to the hilt as it brings civil and criminal consequences upon the concerned employee. He would be liable to be prosecuted and would also be liable to suffer severest penalty awardable in such cases. Therefore, such a grave charge of quasi criminal nature was required to be proved beyond any shadow of doubt and to the hilt. It cannot be proved on mere probabilities.”
That decision pertained to a grave allegation of corruption involving the demand of a 1% commission for disbursing salary allowances, in respect of which the Hon'ble Supreme Court held that such a serious charge of a quasi-criminal nature must be proved to the hilt due to the severe civil and criminal consequences involved. The charges against the present applicant are of a completely different nature and cannot be equated with the facts of that case. Hence, this citation is of no assistance to the applicant.
Further, the applicant relies on Sher Bahadur vs. Union of India and others, reported in (2002) 7 SCC 142, wherein our attention is drawn at para 7 which reads the following:-
“7.…..Evidence, however, voluminous it may be, which is neither relevant in a broad sense nor establishes any nexus between the alleged misconduct and the charged officer, is no evidence in law. The mere fact that the enquiry officer has noted in his report, "in view of oral, documentary and circumstantial evidence as adduced in the enquiry", would not in principle satisfy the rule of sufficiency of evidence. Though, the disciplinary authority cited one witness Sh.R.A.Vashist, Ex. CVI/N.Rly., New Delhi, in support of the charges, he was not examined. Regarding documentary evidence, Ex.P-1, referred to in the enquiry report and adverted to by the High Court, is the order of appointment of the appellant which is a neutral fact. The enquiry officer examined the charged officer but nothing is elicited to connect him with the charge. The statement of the appellant recorded by the enquiry officer shows no more than his working earlier to his re-engagement during the period between May 1978 and November 1979 in different phases. Indeed, his statement was not relied upon by the enquiry officer. The finding of the enquiry officer that in view of the oral, documentary and circumstantial evidence, the charge against the appellant for securing the fraudulent appointment letter duly signed by the said APO (Const.) was proved, is, in the light of the above discussion, erroneous. In our view, this is clearly a case of finding the appellant guilty of charge without having any evidence to link the appellant with the alleged misconduct…….”
This precedent holds that evidence, regardless of its volume, which lacks relevance or fails to establish a nexus between the alleged misconduct and the charged officer, does not constitute evidence in law. We have carefully examined the evidence on record as well as the original administrative file wherein the decisions were taken, and we are satisfied that there is sufficient material collected and adduced through due process. Upon proper consideration, legitimate inferences were drawn holding Charge Nos. 1, 3, and 4 partially proved, culminating in the imposition of a proportionate penalty. Thus, this citation does not assist the applicant.
Further, the applicant relies on J.B. Totade vs. M.N. Bhagat, reported in 1991 (62) FLR 104, wherein our attention is drawn at the following:-
“ I fully appreciate the anxiety on the part of the Chairman of the Maharashtra Public Service Commission to root out corruption from his office but one should bear in mind that in carrying out such purpose a mere suspicion should not be allowed to take the place of proof even in the domestic enquiry.”
This ruling underlines that mere suspicion cannot take the place of proof, even in a domestic inquiry. Having examined the record, we find that the findings against the applicant are anchored in concrete evidence rather than mere suspicion. Hence, this judgment is inapplicable.
Further, the applicant relies on Roop Singh Negi vs. Punjab National Bank and others, reported in (2009) 2 SCC 570, wherein our attention is drawn at paras 14 and 21 which reads the following:-
“14.Indisputably, a departmental proceeding is a quasi-judicial proceeding. The Enquiry Officer performs a quasi-judicial function. The charges leveled against the delinquent officer must be found to have been proved. The enquiry officer has a duty to arrive at a finding upon taking into consideration the materials brought on record by the parties. The purported evidence collected during investigation by the Investigating Officer against all the accused by itself could not be treated to be evidence in the disciplinary proceeding. No witness was examined to prove the said documents. The management witnesses merely tendered the documents and did not prove the contents thereof. Reliance, inter alia, was placed by the Enquiry Officer on the FIR which could not have been treated as evidence.
21.Yet again in M.V. Bijlani vs. Union of India & ors. (2006) 5 SCC 88, this Court held:
"....Although the charges in a departmental proceedings are not required to be proved like a criminal trial, i.e., beyond all reasonable doubts, we cannot lose sight of the fact that the Enquiry Officer performs a quasi-judicial function, who upon analysing the documents must arrive at a conclusion that there had been a preponderance of probability to prove the charges on the basis of materials on record. While doing so, he cannot take into consideration any irrelevant fact. He cannot refuse to consider the relevant facts. He cannot shift the burden of proof. He cannot reject the relevant testimony of the witnesses only on the basis of surmises and conjectures. He cannot enquire into the allegations with which the delinquent officer had not been charged with."”
This decision lays down that departmental proceedings are quasi-judicial in nature and that findings must be based on evidence proved on record by examining witnesses rather than relying on unproved investigation documents. It further reiterates that while charges in departmental proceedings need not be proved beyond reasonable doubt as in a criminal trial, the Inquiry Officer must arrive at conclusions based on a preponderance of probabilities derived from material on record, without relying on surmises or conjectures. We are satisfied that the respondents discharged their quasi-judicial function meticulously and judiciously in the present case, and these principles in no way discredit their inquiry.
Further, the applicant has relied on the order of Principal Bench of C.A.T in OA No.710/2011 dated 03.01.2012. We have carefully perused the same and are of the considered opinion that it was rendered on its own specific facts and does not lay down any proposition of general application. Hence, it is not relevant.
Further, we have examined this case with reference to Union of India vs. P. Gunasekaran (supra) in paras 12, 13 and 20, wherein the Hon’ble Apex Court ruled the following:-
“12.Despite the well-settled position, it is painfully disturbing to note that the High Court has acted as an appellate authority in the disciplinary proceedings, re-appreciating even the evidence before the enquiry officer. The finding on Charge no. I was accepted by the disciplinary authority and was also endorsed by the Central Administrative Tribunal. In disciplinary proceedings, the High Court is not and cannot act as a second court of first appeal. The High Court, in exercise of its powers under Article 226/227 of the Constitution of India, shall not venture into re- appreciation of the evidence. The High Court can only see whether:
a. the enquiry is held by a competent authority;
b. the enquiry is held according to the procedure prescribed in that behalf;
c. there is violation of the principles of natural justice in conducting the proceedings;
d. the authorities have disabled themselves from reaching a fair conclusion by some considerations extraneous to the evidence and merits of the case;
e. the authorities have allowed themselves to be influenced by irrelevant or extraneous considerations;
f. the conclusion, on the very face of it, is so wholly arbitrary and capricious that no reasonable person could ever have arrived at such conclusion;
g. the disciplinary authority had erroneously failed to admit the admissible and material evidence;
h. the disciplinary authority had erroneously admitted inadmissible evidence which influenced the finding;
i.the finding of fact is based on no evidence.
13.Under Article 226/227 of the Constitution of India, the High Court shall not:
(i). re-appreciate the evidence;
(ii). interfere with the conclusions in the enquiry, in case the same has been conducted in accordance with law;
(iii). go into the adequacy of the evidence;
(iv). go into the reliability of the evidence;
(v). interfere, if there be some legal evidence on which findings can be based.
(vi). correct the error of fact however grave it may appear to be;
(vii). go into the proportionality of punishment unless it shocks its conscience.
19.The disciplinary authority, on scanning the inquiry report and having accepted it, after discussing the available and admissible evidence on the charge, and the Central Administrative Tribunal having endorsed the view of the disciplinary authority, it was not at all open to the High Court to re- appreciate the evidence in exercise of its jurisdiction under Article 226/227 of the Constitution of India.
20.Equally, it was not open to the High Court, in exercise of its jurisdiction under Article 226/227 of the Constitution of India, to go into the proportionality of punishment so long as the punishment does not shock the conscience of the court. In the instant case, the disciplinary authority has come to the conclusion that the respondent lacked integrity. No doubt, there are no measurable standards as to what is integrity in service jurisprudence but certainly there are indicators for such assessment. Integrity according to Oxford dictionary is "moral uprightness; honesty". It takes in its sweep, probity, innocence, trustfulness, openness, sincerity, blamelessness, immaculacy, rectitude, uprightness, virtuousness, righteousness, goodness, cleanness, decency, honour, reputation, nobility, irreproachability, purity, respectability, genuineness, moral excellence etc. In short, it depicts sterling character with firm adherence to a code of moral values.”
We have examined the present case with reference to the principles articulated above. We are satisfied that the departmental inquiry was conducted by a competent authority in accordance with the prescribed procedure. We find no violation of the principles of natural justice in conducting the proceedings. Furthermore, there is nothing on record to indicate that the authorities disabled themselves from reaching a fair conclusion due to extraneous considerations, or that they allowed themselves to be influenced by irrelevant considerations.
We further find that the conclusions reached, on the very face of the record, are balanced, non-arbitrary, and far from capricious—such that a reasonable person could certainly arrive at them. We also find that the Disciplinary Authority did not erroneously fail to admit admissible and material evidence, nor did it admit inadmissible evidence that influenced the findings. The findings of fact are grounded in evidence, and the present case cannot be categorized as one of 'no evidence'.
As the Hon’ble Apex Court has unequivocally held, courts and tribunals shall not re-appreciate evidence, interfere with conclusions where the inquiry has been conducted in accordance with law, go into the adequacy or reliability of evidence, or interfere where there is legal evidence to support the findings. Nor can they correct errors of fact, however grave, or interfere with the quantum of punishment unless it shocks the conscience of the Court.
Applying these settled standards, we find that the departmental proceedings against the applicant were conducted following due process, affording ample opportunity in full adherence to the principles of natural justice, and that a balanced decision was taken based on the record and evidence adduced during the inquiry. Consequently, we are of the considered opinion that the applicant has failed to substantiate his case, and we find no reason to interfere with the impugned order.
Our conclusion regarding the limited scope of judicial review, particularly concerning the re-appreciation of evidence, is further supported by the judgment of the Hon’ble Apex Court in B.C. Chaturvedi vs. Union of India & others (supra), wherein the Court ruled as under:-
“The Enquiry Officer submitted his report holding the charges against the appellant to have been proved. After consultation with the UPSC, the appellant was dismissed from service by an order dated 29.10.1986. The Tribunal after appreciating the evidence, upheld all the charges as having been proved but converted the order of dismissal into one of compulsory retirement. The delinquent filed an appeal challenging the finding on merits, and the Union filed an appeal canvassing the jurisdiction of the Tribunal to interfere with the punishment imposed by it. Allowing the appeal of the Union of India and dismissing that of the delinquent.
Per Ramaswamy and Jeevan Reddy, JJ
Judicial review is not an appeal from a decision but a review of the manner in which the decision is made. Power of judicial review is meant to ensure that the individual receives fair treatment and not to ensure that the conclusion which the authority reaches is necessarily correct in the eye of the court. When an inquiry is conducted on charges of misconduct by a public servant, the Court/Tribunal is concerned to determine whether the inquiry was held by a competent officer or whether the inquiry was held by a competent officer or whether rules of natural justice are complied with. Whether the findings or conclusions are based on some evidence, the authority entrusted with the power to hold inquiry has jurisdiction, power and authority to reach a finding of fact or conclusion. But that finding must be based on some evidence. Neither the technical rules of Evidence Act nor of proof of fact or evidence as defined therein, apply to disciplinary proceeding. When the authority accepts that evidence and conclusion receives support therefrom, the disciplinary authority is entitled to hold that the delinquent officer is guilty of the charge. The Court/Tribunal in its power of judicial review does not act as appellate authority to re- appreciate the evidence and to arrive at its own independent findings on the evidence. The Court/Tribunal may interfere where the authority held the proceedings against the delinquent officer in a manner inconsistent with the rules of natural justice or in violation of statutory rules prescribing the mode of inquiry or where the conclusion or finding reached by the disciplinary authority is based on no evidence. If the conclusion or finding be such as no reasonable person would have ever reached, the Court/Tribunal may interfere with the conclusion or the finding, and mould the relief so as to make it appropriate to the facts of each case.”
Further, in the case of Union of India vs. Upendra Singh, reported in 1994 (3) SCC 357, the Hon'ble Apex Court observed as follows:-
“In the case of charges framed in a disciplinary inquiry the tribunal or court can interfere only if on the charges framed (read with imputation or particulars of the charges, if any) no misconduct or other irregularity alleged can be said to have been made out or the charges framed are contrary to any law. At this stage, the tribunal has no jurisdiction to go into the correctness or truth of the charges. The tribunal cannot take over the functions of the disciplinary authority. The truth or otherwise of the charges is a matter for the disciplinary authority to go into. Indeed, even after the conclusion of the disciplinary proceedings, if the matter comes to court or tribunal, they have no jurisdiction to look into the truth of the charges or into the correctness of the findings recorded by the disciplinary authority or the appellate authority as the case may be.”
Conclusions
We have carefully evaluated the rival contentions. It is evident that out of the ten grounds raised in the OA for allowing the application, most relate to a plea for re-appreciation of evidence. The primary remaining ground of defense pertains to alleged non-application of mind in the final penalty order, assailing it as cryptic and non-speaking. We find that no specific or definitive procedural challenge has been set forth in any of the grounds.
We have perused the inquiry-related documents on record as well as the original decision-making file in which the penalty was imposed. We find that the charge-sheet was properly drawn up with all requisite details specified in Annexures-I, II, III, and IV through the prescribed process for a detailed inquiry. The inquiry was conducted after affording the applicant ample opportunity to be heard, to adduce evidence, to cross-examine witnesses, and to inspect relevant documents. No contention has been raised regarding any flaw in the conduct of the inquiry itself. Furthermore, upon submission of the Inquiry Officer's report, the Disciplinary Authority disagreed with certain findings and issued a comprehensive Disagreement Note setting out specific reasons for its disagreement on each charge.
Regarding the four charges levelled against the applicant, the Inquiry Officer had concluded that Charge Nos. 1, 2, and 3 were 'Not Proved', and Charge No. 4 was 'Partly Proved'. In the Disagreement Note, the Disciplinary Authority assigned detailed reasons for disagreeing with the findings on Charge Nos. 1, 2, and 3, tentatively coming to the conclusion that those charges were also 'Partly Proved'. As regards Charge No. 4, the Disciplinary Authority agreed with the Inquiry Officer's conclusion that it was 'Partly Proved'. The Disagreement Note was duly served on the applicant, providing him an opportunity to submit his representation, which the charged officer availed by submitting a detailed response.
Following receipt of his detailed representation, the President/Disciplinary Authority issued the order imposing penalty, which is the impugned order dated 08.03.2022 vide F.No. 13011/11/2015/D(Vig.-M&B)/950 (Annexure – A8). Up to the issuance of the Disagreement Note, no specific procedural lacuna had been pointed out or raised by the applicant. We have examined the Disagreement Note against the judgment of the Hon’ble Apex Court in Punjab National Bank vs. Kunj Behari Misra and Another, reported in (1998) 7 SCC 84 dated 19.08.1998, and find that it fully complies with the principles laid down therein. Under the scheme of service laws, the President/Disciplinary Authority is not bound by the IO’s conclusions and may disagree with the IO provided the prescribed procedure is followed. In accordance with Punjab National Bank vs. Kunj Behari Misra and Another (supra), the President/Disciplinary Authority issued a detailed Disagreement Note recording tentative reasons for holding Charge Nos. 1, 2, and 3 as partly proved, while agreeing with the IO's finding on Charge No. 4 as partly proved. This detailed Disagreement Note was served on the applicant, affording him an opportunity to respond. The essential question that remains is: after the Disagreement Note was served and replied to, to what extent did the President apply his mind to the applicant's submissions?
A closer examination of the impugned penalty order reveals that the President modified his tentative opinion on the charges. In the final order, Charge No. 2 was held as 'Not Proved', indicating acceptance of the applicant's submissions as well as the findings of the IO. For Charge Nos. 1 and 3, the President maintained his disagreement with the IO and recorded them as 'Partly Proved', while concurring with the IO on Charge No. 4 as 'Partly Proved'. These findings across the three statutory stages are tabulated below, providing a comparative analysis that substantiates due application of mind by the President:
Findings of Authorities on various Charges:-
| Article of Charge | Conclusions of the Inquiry Officer | Conclusion in the Disagreement Note | Final Conclusions of Disciplinary Authority in the Penalty Order |
| Charge No.1, Stock of Cement | Not Proved | Disagreed, as partly proved | Partly Proved |
| Charge No.2, Stock of Bitumen | Not Proved | Disagreed, as partly proved | Not Proved |
| Charge No.3, Sub Contracting | Not Proved | Disagreed, as partly proved | Partly Proved |
| Charge No.4, | Partly Proved | Agreed, Partly | Partly Proved |
Sample test by Proved an Engineering College
Furthermore, we have closely perused the original decision-making file produced before us. Since disciplinary orders have been passed by the President, these file contents are no longer confidential. Our examination reveals a clear application of mind, with the President carefully considering the submissions made by the applicant. While it is beyond the scope of judicial review to re-assess the complete evidence de novo, by way of illustration, we refer to the first article of charge. When tentative reasons for disagreement were served on the applicant through the Disagreement Note and he submitted his defence, the file note records that on the issue of physical verification of cement stock at site, the E-in-C Branch stated that, as of date, it is not possible to conclusively prove whether Shri G Sanjeev signed the invoices after checking the stock at site or not. Consequently, this specific point of charge was found unsustainable against Shri G Sanjeev. This demonstrates that individual sub-charges were analyzed and evaluated separately within each charge.
Thus, the record establishes that the President/Disciplinary Authority applied his mind to each charge and sub-charge in a detailed manner. The manner in which the evidence was evaluated lies beyond the purview of judicial review; nevertheless, as the file contents are no longer confidential, the relevant deliberations from the official file are extracted below:-
“5.MES-604478 Shri G. Sanjeev, then JE (Civ):
Article-I
A. Tentative reasons of disagreement with the findings of Inquiry Authority were on following aspects:
(i)Mismatch between quantity of cement as per Invoices' and Bitumen & Cement Consumption Register (BCCR).
(ii)Shri G Sanjeev initialed/endorsed 215 invoices out of a total of 303 invoices, showing procurement of Cement purportedly from M/s Madras Cements Ltd., without physically verifying the consignments brought to site and put up the same to the Engineer-in-Charge, for his verification and defacing of the same, whereby facilitating the contractor.
(iii)Causing wrongful gain to the contractor.
B. Brief of Defence of Shri G Sanjeev on disagreement note (Pg.668/c):
(i)On the issue of entries in BCCR without any reference of invoices/MB entries, Shri Sanjeev has stated that he had entered the invoices of cement lots in Bitumen & Cement Consumption Register (BCCR) from Sl No. 01 to 349 and 349 to 473 mentioning lot numbers in column 3. The same lot numbers alongwith invoice number, date and quantity are reflected in MB No. 759 and Cement Supply and Acceptance Register.
Further, on the issue of 17600 bags entered in MB without mentioning invoice numbers, Shri Sanjeev has stated that he had entered the invoices of cement lots in MB No. 759 along with lot number, invoice number, date and quantity as per normal practice. A table in this regard is placed at Pg. 668/с.
On the issue of 12600 bags of cement not entered in MB but invoices are available, Shri Sanjeev stated that he had entered the invoices of cement lots in MB No. 759 alongwith lot number, invoice number, date and quantity for Lot 01 to 16 only and later on other JEs have entered the balance Cement voucher invoices.
(ii)On the issue of endorsing of invoices without physical verification at site, Shri Sanjeev has stated that State witness No. 02 in his statement Exhibit S34A, states that "I identify the initials of respective JEs who had physically verified the materials as mentioned therein, which were brought to me" proves the fact that cement stock were physically checked at site by myself. On the issue of mismatch Shri Sanjeev has stated that when Presenting Officer (having more than 30 years) of experience makes wrong entry in his written brief (08 out of 23) and the same has also been acknowledge by the Inquiry Officer, than I as a fresher JE at the time of incident has mismatched (01 out of 92) which is ignorable mismatch and which was unintentional.
(iii)On the issue of causing wrongful gain to contractor, Shri G Sanjeev has stated that on one hand Disciplinary Authority has agreed with the findings of IO that verification of purchase vouchers fall in the jurisdiction of Engineer-in-Charge and on the other hand DA stating the failure to ensure verification of invoices has caused wrongful gain to the contractor, is not agreed to.
C. View of Authority on Article-I:
On the first point of disagreement, Shri Sanjeev has simply stated that he had entered invoice reference in BCCR, however, he could not provide any documents in this regard. On the issue of 17600 bag of cement entered in MB without mentioning invoice references, he provided a table of cement bags entered by him. However, on the Appendix A1 of Annexure-I of the disagreement note (Pg. 626/c) which states the details of cement which were entered in MB but not available in list of invoices, he has not given any clarification. Therefore, Shri G Sanjeev is certainly responsible of not maintaining proper entries in BCCR and MB.
Further, on the issue of physical verification of cement stock at site, E-in-C Branch has also stated that as on date it is not exactly possible to prove that Shri G Sanjeev has signed the invoices after checking the stock at site or not. Therefore, this point of charge is not sustainable against Shri G Sanjeev.
On the issue of causing wrongful gain to contractor, it is submitted that verification of purchase voucher is fall under jurisdiction of Engineer-in-charge i.e Shri R Ramalingam. E-in-C Branch has stated that Shri G Sanjeev has failed to advice his Engineer-in-charge for verification of purchase vouchers, therefore he is responsible for this lapse. Though the verification of purchase vouchers does not falls under the charter of duties of JE but being an officer in same channel he cannot simply ignore the shortcomings occurred within same project. In view of the above, Article-I of charge against Shri G Sanjeev, then JE is "Partially proved".
Article-II
A. Tentative reasons of disagreement by the Disciplinary Authority on Article-II (pg.631/c):
On the Article-II of charge, 01 out of 04 point determined by the IO is disagreed and same is as follows:
(i)Shri G Sanjeev was colluded with the contractor since he did not get the vouchers of bitumen verified from the manufacturer: The fact that invoices are fake/fabricated indicates that concerned parties i.e. seller as well as buyer have done tax evasion and may have supplied low/inferior quality of Bitumen and got benefited from it. Otherwise, there was no requirement of submitting fake invoices. So even if CO may not be hand in gloves with the contractor, but his failure to ensure verification of invoices has caused financial gain to the contractor and corresponding loss to state by way of saving of taxes/lower quality of supplied Bitumen.
On the abovementioned point Disciplinary Authority tentatively disagrees with the findings of IO. Since, 01 out of 04 points determined by the IO is disagreed, the Article-II of charge appears to be 'Partially Proved' against the Charged Officer.
B. Brief of Defence of Shri G Sanjeev on disagreement note on Article-II (Pg. 665/c):
On this point of disagreement, Shri G Sanjeev has stated that it is seen that DA agrees with 3 out of 4 IO's point of determination which all are based on charter of duties. But DA stating the failure to ensure verification of invoices of bitumen is contrary and not understood and also not agreed for the reasons below:
(i)Nothing has been mentioned in the contract agreement regarding verification of Bitumen.
(ii)Verification of purchase, vouchers is not assigned to JE, neither the responsibility of JE as per RMES Table M.
C. View of Authority on Article-II:
It this regard it is submitted that for the point of verification of purchase vouchers, it has been agreed that the same is not the responsibility of JE. It has also been agreed that in Contract Agreement there was no provision related to verification of Bitumen. Since, we have agreed with the findings of IO on other points of Bitumen because of no mention in Contract Agreement regarding provisions for Bitumen, we may also exempt Shri G Sanjeev from the charge of causing wrongful gain to the contractor by not getting the Bitumen vouchers verified from the manufacturer. Therefore, it is proposed that we may Agree with the findings of IO that Article-II of charge as "Not Proved".
Article-III
A. Tentative reasons of disagreement by the Disciplinary Authority on Article-III (pg.630/c)
On this article of charge, the Disciplinary Authority tentatively disagrees with the finding of 10 on the following reason:
(i)Shri G Sanjeev, may not be aware about the subletting of the contract by M/s BR Arora & Associates Pvt Ltd to M/s JKS Construction Pvt Ltd, but he has failed to take suitable follow up action with his GE/Engineer-in-Charge at these occasions as given below:-
(a)When he has observed that the most of T&P mentions M/s JKS Construction Pvt Ltd, he should have asked documents related to T&P including ownership/rental documents.
(b)At the time of initiation of DO vide GE (AF) Sulur letter No. 8486/423/E8 dated 05.05.2010, the purchase order dated 11.12.2009 of M/s BR Arora & Asso (page 12/14, S-72, State Documents, Annexure-II) which was initialed by Shri G Sanjeev for defacing the same by Shri R Ramalingam, stipulates as "since we have given the work to M/s JKS Construction Pvt Ltd is back to back basis, the payment will be made by M/s JKS Construction Pvt Ltd". So at that time he should have taken up the matter with M/s BR Arora & Asso/GE (AF) Sulur to get the matter clarified. Since Shri G Sanjeev has failed to take any action on these two occasions, he is responsible for ignoring the letters/not taking requisite action i.e. relationship between M/s BR Arora & Asso and M/s JKS Construction. Hence, this shows that Shri G Sanjeev, has failed to carry out his duties meticulously with full dedication and devotion. In view of the above, Article-III of charge against CO appears to be Partially Proved.
B. Brief of Defence of Shri G Sanjeev on disagreement note on Article-III (Pg. 664/c):
On this point of disagreement Shri G Sanjeev has stated the following:
(i)I have not given any statement stating that I have observed that the most of the T&P mentions M/s JK Construction Pvt Ltd.
(ii)CA permits MoU for Plants/equipments. Contractor has to provide T&P as per contract agreement. In CA, we generally specify list of T&P which should be owned by the contractor.T&P other than that may be hired by the contractor.
(iii)The CA clause does not mention that the registration of the vehicle should be in the name of M/s BR Arora & Associates.
(iv)During execution of project, number of inspection/site visits were carried out by Senior Officers like CE, CWE.
(v)Technical Examination by team of STE office was carried out during execution of the work and no points are outstanding.
(vi)Regarding initiation of DO (Exhibit S-72 Sheet 1/14 to 11/14), I have not initialed or signed in this documents. Exhibit S-72, Sheet 13/14, this document is purely private correspondence between the contractor and third party and no copy is addressed to the department.
C. View of Authority on Article-III: Shri G Sanjeev has misconstrued the disagreement that he has made any statement that he has observed that the most of the T&P mentions M/s JK Construction Pvt Ltd. Rather, as a JE he is ought to observe such activities and report to higher authorities. Further, regarding initiation of DO (Exhibit S-72), Shri G Sanjeev has selectively quoted the Sheet No. 1/14 to 11/14 of Exhibit S-72, while he has not talked about Sheet No. 12/14 of Exhibit S-72 in which he has actually initialed (S-72, Link Folder-V). Therefore, it is well established that Shri G Sanjeev was aware of said DO letter and he ignored the subletting. Hence, this shows that Shri G Sanjeev, has failed to carry out his duties meticulously with full dedication and devotion. In view of the above, it is proposed that the Article-III of charge against Shri G Sanjeev, then JE, stands "Partially Proved”.”
In the facts of the present case, we find that the requirements of natural justice—specifically the opportunity of effectively contesting the proposed disagreement and adverse findings—were fully extended to the applicant. There is no legal requirement that the President/Disciplinary Authority write a formal judgment dealing seriatim with every submission raised in the representation. Nor was there any need to state repetitive or elaborate reasons in the final order, given that the Disagreement Note itself provided comprehensive reasoning, and the representation of the charged officer was duly examined on file in significant detail as extracted above.
In our opinion, the final order is not rendered invalid merely because the President/Disciplinary Authority did not deal separately with each and every contention in the body of the order. The record clearly discloses due application of mind to the material and substantial issues arising for determination. This is evidenced by the fact that while at the stage of issuing the Disagreement Note all four charges were tentatively considered as partly proved, the President, sitting as Disciplinary Authority at the stage of passing the final order, altered his view to hold Charge No. 2 as 'Not Proved', leaving only Charge Nos. 1, 3, and 4 as 'Partly Proved'. This shift in position clearly demonstrates active consideration and deliberate application of mind.
Addressing the applicant's contention regarding non-application of mind and the penalty order being cryptic, we must examine this case with reference to the judgment of the Hon’ble Apex Court in Union of India and others vs. E.G. Nambudiri, reported in (1991) 3 SCC 38 dated 23.04.1991. In that case, the Court dealt with whether reasons must necessarily be communicated in Presidential orders rejecting representations (which pertained to adverse ACR entries and a memorial to the President, where a cryptic order was challenged for lack of application of mind and absence of evidentiary nexus), and held as follows:-
“The President was under no legal obligation to record reasons in rejecting the respondent's representation against the adverse remarks. Consequently, the order of the president was not vitiated in law. The Central Administrative Tribunal committed error in quashing the order of the president as well as the order of the Ministry of Commerce dated 6.1.1986. Assuming that there was some defect in the order rejecting the respondent's representation, the Tribunal was not justified in holding that the adverse entries awarded to the respondent should be treated as having been expunged. We accordingly allow the appeal, set aside the order of the Tribunal dated 27.7.1987. There will be no order as to costs.”
We find that all supporting reasons for holding the charges partly proved exist contemporaneously on the official record produced before this Court. We have expressly included those file notes in this order as they are no longer confidential. Even if the Presidential order were viewed as concise or cryptic on its face, no useful purpose would be served by remanding the matter, as sufficient evidence exists on record upon which the President would inevitably arrive at the same conclusion. We are satisfied that the President/Disciplinary Authority convincingly considered the representation of the applicant pursuant to the Disagreement Note and passed the impugned penalty order only after due consideration, with all underlying reasons for rejecting the applicant's contentions contemporaneously existing in the decision-making file.
This position is further fortified by the ruling of the Hon’ble Apex Court in Boloram Bordoloi vs. Lakhimi Gaolia Bank, reported in (2021) 3 SC 806 dated 08.02.2021, wherein the Court observed the following:-
“7.……..Further, it is well settled that if the disciplinary authority accepts the findings recorded by the Enquiry Officer and passes an order, no detailed reasons are required to be recorded in the order imposing punishment. The punishment is imposed based on the findings recorded in the enquiry report, as such, no further elaborate reasons are required to be given by the disciplinary authority. As the departmental appeal was considered by the Board of Directors in the meeting held on 10.12.2005, the Board’s decision is communicated vide order dated 21.12.2005 in Ref. No.LGB/I&V/Appeal/31/02/2005-06. In that view of the matter, we do not find any merit in the submission of the learned counsel for the appellant that orders impugned are devoid of reasons.”
The Hon’ble Apex Court has held that where the Disciplinary Authority accepts the findings of the Inquiry Officer, detailed reasons need not be recorded in the punishment order, because the findings and reasons in the inquiry report constitute the basis of the punishment. In the present case, the Disciplinary Authority concurred with the IO's finding on Charge No. 4—the most substantive of the four charges—holding it 'Partly Proved'. This finding alone provided sufficient basis for imposing the penalty. By necessary implication, no further elaborate reasons were required in the punishment order itself. Even though detailed Disagreement Notes were issued on other charges, it was not legally required that the Presidential order reproduce every detail of the file deliberations or address each defense submission seriatim. We are satisfied that cogent reasoning exists on the Presidential file; hence, the applicant's ground that the order is cryptic cannot be sustained. The reasons recorded on file demonstrate due consideration of the applicant's substantive defense, and the challenge to the legality of the decision-making process, adequacy of communication, and the penalty order must fail.
The mere brevity of the final order, considered in isolation, cannot by itself render the disciplinary action invalid. The original decision-making file before us demonstrates that the representation submitted by the applicant against the Disagreement Note was considered and that reasons were recorded while arriving at the final conclusions. The pertinent question is not whether the final order reproduces those reasons verbatim, but whether the Disciplinary Authority, after affording the applicant an effective opportunity to respond to the tentative disagreement, duly considered the material submissions made by him and arrived at its conclusions based on the record. We find that the present order fully conforms with the judgment of the Hon’ble Apex Court in E.G. Nambudiri (supra). In the light of these rulings, the contention of the applicant citing Mahinder Singh Gill case (supra) does not dent the impugned order challenged before us.
Having regard to the procedural compliance in the disciplinary proceedings, the active application of mind by the authorities to the material on record, and the clear evidentiary nexus establishing that the charges stand partly proved on the standard of preponderance of probabilities, we hold that the applicant has failed to establish any ground for our interference with the impugned order. The decision-making records clearly disclose a legally sustainable application of mind to the applicant's defence and evidence.
Upon examining the case in light of the standards laid down in the Hon’ble Apex Court rulings in B.C. Chaturvedi (supra), P. Gunasekaran (supra), Punjab National Bank vs. Kunj Behari Misra (supra), E.G. Nambudiri (supra) and Boloram Bordoloi (supra), we find no merit in this Original Application.
Accordingly, we pass the following orders:-
ORDER
OA is dismissed. All associated MA(s), if any pending, shall be treated as disposed of.