Tribunals and CommissionsFull Bench(2022) 05 NGT CK 0035

Dr. Kiran Ramdas Kamble & Anr vs State of Maharashtra

National Green Tribunal · Decided on 18 May 2022

HON’BLE JUDGES
Adarsh Kumar Goel, CP · Sudhir Agarwal, JM · Arun Kumar Tyagi, JM · Dr. Afroz Ahmad, EM
RESULT
Disposed Of
CASE NUMBER
Original Application No. 544 Of 2019

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

72 paragraphs · 1,931 words
1.

Question for consideration is the remedial action for failure of the Municipal Council Trimbak and other concerned authorities of the State of Maharashtra in preventing discharge of Municipal waste into river joining Godavari, in violation of judgement of the Hon’ble Supreme Court in Paryavaran Suraksha v. UOI, (2017) 5 SCC 326. The matter has been considered six times earlier – on 8.8.2019, 4.2.2020, 28.10.2020. 28.6.2021, 16.9.2021 and 11.2.2022 in the last more than two years, apart from orders in other cases on the subject, including an order in the presence of the Chief Secretary of the State on 24.01.2020 in O.A No. 606/2018, Compliance of Municipal Solid Waste Management Rules, 2016 and other environmental issues. Each time finding apathy and noncompliance on the part of the authorities, directions were issued for remedial action but unfortunately the situation remained unremedied to the detriment of environment and public health, forcing living beings to drink contaminated water with potential for water associated diseases at times leading to deaths, in flagrant violation of Constitutional mandate and binding directions of Hon’ble Supreme Court and this Tribunal, with no coercive action against such serious violators. Such attitude of the authorities was found to be disappointing and against human rights. This was found to be so though Trimbakeshwar is holy place of great significance, attracting devotees from all over the world, besides being the origin of river Godavari and lifeline of Maharashtra, Telangana, Andhra Pradesh, Chhattisgarh and Odisha.

2.

Vide last order dated 11.02.2022, status of compliance was reviewed in the presence of Principal Secretary, Urban Development of the State and in the light of the report of Municipal Council Trimbak. It was found that the violations were continuing and untreated sewage was being directly discharged into river Godavari, in violation of judgment of the Hon’ble Supreme Court and the environmental norms, having adverse impact on Madhmeshwar Birds Sanctuary which is a Ramsar Site, created from the backwater of dam on Godavari in Nashik District. Accordingly, the Tribunal directed Chief Secretary, Maharashtra to ensure remedial action and to remain present in person by video conferencing. The operative part of the order is reproduced below:-

“1to4…..xxx……………………………….xxx…………………………….xxx

5.

It is seen that generation of sewage is in the range of 4.5 – 5.0 MLD while arrangement for treatment is only for 1 MLD sewage. Remaining untreated sewage is being discharged into the river which is not fit even for bathing purpose as per primary water quality criteria but may be drunk by human and other living beings to the detriment of their health and in violation of environmental laws and judgment of the Hon’ble Supreme Court in Paryavaran Suraksha case1 followed by directions of this Tribunal referred to above. We place on record our strong disapproval to the ki human conduct of the State of Maharashtra and its concerned officer for such situation and proposing action by August, 2023 inspite of repeated orders of this Tribunal in the last more than two years. We have not found any reason why such action could not have been taken earlier in view of Supreme Court orders of 2017 and why erring officers are not being prosecuted as directed by the Hon’ble Supreme Court. Disciplinary action appears to be an eye wash and wholly inadequate and not against senior officers who are real culprits for the situation. Regretfully, the authorities do not appear to have taken the trouble even to read the order. The report filed is incomplete. Information on cleaning of drains used for dumping sewage and garbage has not been given. Details of quantity of sewage generated from adjoining areas and the progress on underground sewerage needs to be ascertained so as to ensure remedial action. Comprehensive plan for Trimbakeshwar has to be in place, as directed earlier. No response has been given on these significant aspects.

6.

Confronted with such failures, the Principal Secretary, UD, who is present by video conferencing has assured the Tribunal that immediate interim arrangements will be made to prevent untreated sewage being discharged into the river, pending permanent solution by way of setting up necessary STPs and directions earlier issued will now be complied with.

7.

The Tribunal holds that direct discharge of sewage containing both organic and inorganic pollutant into the river Godavari is highly detrimental to the ecology and environment. The polluted water may also have serious negative impact on ecologically sensitive Madhmeshwar Birds Sanctuary in the area which is a Ramsar Site created from the backwater of dam on Godavari in Nashik District.

8.

Let the Chief Secretary, Maharashtra ensure satisfactory action in the light of abovesaid observations, including meaningful coercive action against erring officers which may include prosecution, apart from disciplinary action as per directions of the Hon’ble Supreme Court, quoted earlier. Compliance affidavit of status as on 30.04.2022 be filed before this Tribunal by e-mail at [email protected] preferably in the form of searchable PDF/ OCR Support PDF and not in the form of Image PDF. The District Magistrate, Nasik may, in coordination with concerned stakeholders, prepare and execute action plan for utilization of Rs. 1.0 crore deposited by the State Government for improving the environment consistent with the District Environment Plan. The Chief Secretary, Maharashtra may remain present in person on the next date by video conferencing.”

3.

In pursuance of the above, compliance affidavits have been filed on behalf of the State of Maharashtra as well as Municipal Council Trimbak and the Chief Secretary, Maharashtra is present by VC.

4.

The affidavit filed on behalf of the State gives the compliance status in tabular form as follows:-

Sr.

No.

Point

Action taken Report and Current Status

1.

Refurbishment        of existing                  STP (Capacity  1  MLD)  in the           area           of Trimbakeshwar Municipal Council

·   The  Trimbak  Municipal  Council  completed the  work  of  refurbishment  of  the  existing  1 MLD   STP   through   Maharashtra   Suvarn Jayanti  Nagaratthan  Mahabhiyan  (District Level).  This  work  costs  to  the  tune  of  Rs.

0.94  Crore  and  the  entire  cost  is  paid  by the Government of Maharashtra.

·   Now, this STP is working as per standards.

2.

Augmentation          of STP                 capacity through                 New Scheme       (Capacity

4.5 MLD)

·   A   sewage   project   of   Rs.   34.60   Cr.   With additional     4.5     MLD     STP     capacity     is sanctioned        for        intermediate        stage requirement for the year 2038, by the State Government        on        24.06.2021        under Maharashtra  Suvarn  Jayanti  Nagarotthan Mahabhiyan.

·   The Trimbakeshwar  Municipal Council  has issued       work       order      on       02.12.2021 accordingly.

·   The  work  of  the  project  has  been  started and  current  progress  is 10%.  The  expected date   of   completion   of   the   said   sewage project is August, 2023.

·   The  said  sewage  scheme  is  100%  funded by  the  State  Government  (90%  from  State Scheme and 10% from Tribal Sub Plan)

·   Accordingly,    the    State    Government    has already   released   first   installment   of   Rs.

11.33             Cr      to      the      Trimbakeshwar Municipal Council.

3.

Interim compensation  of  Rs. 1.0 Cr.

·   This  Hon.  Tribunal  has  directed  the  State Government   of   Maharashtra  to   deposit   a sum  of  Rs.1  Cr  as  interim  compensation with   the   Collector   of   District   Nashik   for utilization  towards  the  restoration  of  water quality    of    the    river    at    Trimbakeshwar, District Nashik.

·   Accordingly,    the    State    Government    has deposited    Rs.    1    Cr.    With    the    District Collector, Nashik on 15.11.2021.

·   The  District  Collector,  Nashik  has  finalized the           ozonization           technology           for augmentation    of    sewage    treatment    and restoration  of  water  quality  of  the  river  at

Trimbakeshwar.

·   The  work  order  for  ozonization  was  issued on  14.02.2022  and  the  work  is  completed 100%.  The said  work  will  be commissioned by  10.05.2022  and  40%  more  sewage  will be treated i.e. total 1.4 MLD.

4.

Taking   action against      concerned erring officers

·   The     State     Government     has     identified following officers as erring officers-

1.

Mr.    Praving    Nikam,    the    then    Chief Officer, Trimbak Municipal Council.

2.

Mrs.   Chetana   Kerure,   the   then   Chief Officer, Trimbak Municipal Council.

3.

Mr.      Sanjy      Jadhav,      Chief      Officer (Present), Trimbak Municipal Council

4.

Mr.  Umesh  Rathod,  the  then  Engineer, Trimbak Municipal Council,

5.

Mr.       Abhijeet       Inamdar,       Engineer (Present), Trimbak Municipal Council

·   The     State     Government     has     instituted disciplinary  proceedings  against  the  above

mentioned 5 officers/ engineers.

5.

Keeping      copy      of NGT     order     dated 16.09.2021    in    the ACR      folders      and personal      files      of concerned         erring

officers

·   As    per    the    directions    of    this    Hon’ble Tribunal,    a    copy    of    the    order    dated 16.09.2021  this  Hon’ble Tribunal  has  been placed   in   the   ACR   folders   and   personal files   of   the   concerned   above   mentioned officers.

6.

Preparation               of Standard   DPRs   for sewerage  projects  in the State.

·   Government      of      Maharashtra      through Urban      Development      Department      has directed        the        Maharashtra        Jeevan Pradhikaran  to  prepare  as  Standard  DPR- (Detailed      Project     Report)     for     sewage Projects in the State.

·   Accordingly,           Maharashtra           Jeevan Pradhikaran  has  submitted  the  Standard DPR     for     sewage     projects.     The     said Standard  DPR  has  been  provided  to  all  the

ULBs.

7.

Interim arrangements          to prevent       discharge into river

·   The    State    Government    has    asked    the Maharashtra      Jeevan      Pradhikaran      to submit    a    report    about    generation    and treatment     of     sewage     in     the     area     of Trimbakeshwar Municipal Council.

·   As  per  report  submitted  by  MJP,  current sewage  generation  is  not  4.5  to  5.0  MLD but it is 1.78 MLD.

·   The existing established treatment capacity is  1  MLD  which  will  be  increased  upto  1.4 MLD as a result of ozonization. This will be achieved by 10.05.2022.

·   Thus,   gap   in   treatment   capacity   to   treat current generated sewage is 0.38 MLD.

·   To  bridge  this  gap,  the  State  Government has  sanctioned  installation  of  0.5  MLD  Pre Fabricated       STP.       Administrative       and financial  approval  for  the  same  is  given  on 31.03.2022. The work order for the same is

issued  on  16.04.2022  and  its  installation

and    commissioning    is    expected    to    be completed before 31.05.2022.

·   In    the    meanwhile,    the    Trimbakeshwar Municipal     Council     has     also     identified temporary   measure   of   treating   effluents using      eco-technology      (bio-catalyst      for treating  both  Kailas  Raja  Nagar  Nala  and Dobadwadi Nala.

·   As  a  result  of  these  interim  arrangements, no  untreated  sewage  will  be  discharged  in to river Godavari from 10.05.2022.

·   Also,  Prefabricated  STP  work  is  being  fast tracked  to  achieve  complete  treatment  at the earliest.

·   Thus,        all        the        requisite        interim arrangements    to     prevent     discharge    of untreated sewage are ensured.

”

5.

In view of affidavit of the State, it is not necessary to refer to the affidavit of the Municipal Council.

6.

We have interacted with the Chief Secretary, Maharashtra present before the Tribunal by VC. From the affidavit filed, quoted above, it is seen that the STP is now working and steps have been taken for augmentation of its capacity, interim compensation has been deposited, ecotechnology has been adopted as interim measure and ozonization technology has been finalized as permanent measure for treatment of effluents for which work order has been issued. Action has been taken against some of the erring officers. Gap in generation of effluents and treatment capacity is proposed to be bridged by installing pre-fabricated STP and taking temporary measures. It is also stated that no untreated sewage will henceforth be discharged into the Godavari.

7.

In view of the above, no further action appears to be necessary at this stage except that the compensation deposited may be utilized by the Collector, Nashik for restoration of environment in accordance with the District Environment Plan. Further, steps be taken to ensure connectivity to the STP to fully utilized its capacity. Plan be prepared for utilizing the treated water for secondary purposes, consistent with the directions of this Tribunal on the subject. CPCB may verify compliance status as on 30.11.2022.

The application is disposed of.

A copy of this order be forwarded to the CPCB by email for compliance.