High CourtsSingle Bench(2010) 08 GUJ CK 0134

Deputy Executive Engineer, G.W.R.D.C., Sub-division 2 vs Gendalbhai Bhavabhai Chauhan

Gujarat High Court · Decided on 10 August 2010

HON’BLE JUDGES
H.K. Rathod, J
RESULT
Allowed
CASE NUMBER
Special Civil Application No. 6599 of 2002

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

25 paragraphs · 516 words

H.K. Rathod, J.—By way of this petition, the petitioner has prayed to quash and set aside the judgment and award passed by the Labour

Court, Nadiad in Reference (LCN) No. 532/1990 dated 28.09.2001, whereby, the said reference was partly allowed and the petitioner has been

directed to reinstate the respondent on his original post with continuity of service but, without any back wages.

2.

The facts in brief are that the respondent herein was engaged as a Contractor by the petitioner-Corporation for operating/maintaining the tube-

wells at Village Rasikpura vide two Agreements dated 01.11.1985 & 01.11.1986. As per the second Agreement, the contract period was to end

on 31.10.1987.

3.

After expiry of the second contract period, the petitioner-Corporation undertook the process of making a new contract. However, to ensure

that water supply to the farmers is not affected during the intervening period, the respondent herein was asked to continue to carry on the work on

the same terms and conditions, until the new contract was awarded. In the meantime, the respondent filed S.C.A. No. 4401/1988 before this

Court. Initially, by way of ad-interim relief, the petitioner-Corporation was restrained from terminating the services of the respondent. However,

ultimately, the said petition came to be disposed of vide order dated 03.03.1989 by relegating the respondent to the remedy of raising an industrial

dispute under the provisions of the I.D. Act.

4.

Thereafter, the respondent raised an industrial dispute, which, ultimately, culminated into a reference before the Labour Court. The Labour

Court, after hearing both the sides, passed the impugned award. Hence, this petition.

5.

Heard learned Counsel for the respective parties and perused the documents on record. It is a matter of fact that the respondent was engaged

as a Contractor by two separate Agreements, viz. dated 01.11.1985 & 01.11.1986. However, the respondent was continued in work, after the

completion of the contract period, on account of the interim stay against his termination granted by this Court in S.C.A. No. 4401/1988 filed by

him. Subsequently, vide order dated 03.03.1989, the said petition came to be dismissed. In the said order dated 03.03.1989, it has been recorded

that pursuant to the vacation of ad-interim stay granted in favour of the respondent, his services came to be terminated by the petitioner. Even

otherwise, the work rendered by the respondent under the two different Agreements cannot be considered for counting 240 days, as contemplated

u/s 25B of the I.D. Act, since the said work was done in pursuance of a contract/agreement and not on the basis of any relationship of master -

servant. The Court below failed to appreciate the facts of the case in its proper perspective and committed serious illegality in clubbing the period

of work done by the respondent under the two different Agreements for calculating 240 days. Hence, the impugned award passed by the Court

below, being illegal and contrary to the settled principles of law, deserves to be quashed and set aside.

6.

For the foregoing reasons, the petition is allowed. The impugned award dated 28.09.2001 is quashed and set aside. Rule is made absolute.