Tribunals and CommissionsFull Bench(2022) 11 NGT CK 0029

Benny Sebasstian vs M/s. VKL Infrastructure Facilities (P)Ltd. & Ors

National Green Tribunal · Decided on 15 November 2022

HON’BLE JUDGES
Adarsh Kumar Goel, CP · Sudhir Agarwal, JM · Prof. A. Senthil Vel, EM
RESULT
Disposed Of
CASE NUMBER
Review Application No. 35 Of 2022 IN Original Application No. 119 Of 2022 (I.A. No. 276, 277 Of 2022)

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

129 paragraphs · 3,458 words
1.

This application seeks review of order of this Tribunal dated 12.07.2022 in OA No. 119/2022, Benny Sebasstian vs. M/s. VKL Infrastructure Facilities (P)Ltd. & Ors.

2.

By the said order, the Tribunal considered the violation of environmental norms in operation of quarry projects of the review applicant - M/s. VKL Infrastructure Facilities (P) Ltd. and M/s. VKL Projects (P) Ltd., 1st Floor, Anjana Complex, Kundannoor, Maradu P.O., Kochi-682 304, Kerala, the Project Proponent (PP). Violations considered included location of mining activity within prohibited distance, violation of Environmental Clearance (EC) conditions, quarrying beyond permitted quantity.

3.

Vide order dated 24.02.2022, the Tribunal, constituted a joint Committee comprising SEIAA, Kerala, Kerala State PCB and District Magistrate, Thiruvananthapuram to undertake visit to the site, verify the compliance status and file a factual and action taken report. It was further directed that if violations are found, the Project Proponent may be put to notice of these proceedings for its response, if any.

4.

The PP filed Review Application No. 08/2022, Benny Sebasstian vs. M/s. VKL Infrastructure Facilities (P)Ltd. & Ors. against the said order with the plea that no verification was necessary as matter had already been dealt with by the Kerala High Court. The Tribunal rejected the review application vide order dated 7.4.2022 with the observation that verification process will not cause any prejudice to the PP.

5.

Thereafter, report dated 23.5.2022 was submitted to this Tribunal that some of the EC conditions were violated. Considering the same, the Tribunal disposed of the matter with a direction that the State PCB may recover compensation for such violations on polluter pays principle, including interim compensation, following due process of law. The operative part of the order is reproduced below:

“xxx …………………………….xxx………………………………xxx

4.

The joint Committee has filed its report dated 23.05.2022 giving the compliance status of EC conditions as follows:-

“3.1 A. Compliance of Specific Conditions

No

Specific Conditions

Compliance Status

1

Considering the presence of a DTPC Building and intended use of the elevated hillock as a place  of  local  tourism,  a  buffer  distance  of 100 m must be left as a No Development Zone from the path connecting the top points on two rocky   knobs   of   Thampuranpara   and   the eastern edge of the DTPC building.

Not complied.

Physical  measurement  by  the  Survey Team indicated that the distance is only 79m  between  the  eastern  edge  of  the DTPC  building  and  Project  boundary. Therefore, the buffer distance of 100m is not maintained as a No Development Zone.

2

Top soil and overburden should be stored in a designated place on the lower slope away from the working  area (on  the eastern side) and provided with protective support walls.

Not complied.

There are two top soil and overburden dumps, one on the south-southwestern portion of the project area in the higher slope  and  the  other  on  the  eastern portion of the project area in the lower slope. Both are away from the working area    and    are    not    provided    with protective support walls. The one on the higher slope is relatively an old one and is somewhat stabilized with vegetative growth.  The  one  on  the  eastern  lower slope   is   subjected   to   severe

erosion.

3

A catch water drain to be provided all along the  lowest  part  and  channelized  into  a  pit that  is   supposed   to  function   as   a  RWH structure, Water must be clarified before it is let out

Partially complied

There is no catch water drain provided all     along     the    lowest    part    and channelized into a pit that is supposed to    function    as    a    RWH    structure. However,  a  portion  of  the  old  working quarry is used as a RWH structure.  No arrangement for  clarification  of  water prior to it’s letting out is found.

3.1 B. Compliance of General Conditions

No

General Conditions

Compliance Status

4

Maximum  possible  solar  energy  generation and utilization shall be ensured as an essential part of the project

Partially Complied

But maximum possible solar energy generation is yet to be achieved

6

Eco-restoration including the mine closure plan shall  be  done  at  the  own  cost  of  the  project proponent

Partially        complied.       Affidavit submitted.

Efforts are seen taken to grow trees in the land adjacent to the project site owned by the proponent. Mine closure is yet to be done

7

At least 10 percent out of the total excavated pit area should be retained as water storage areas and  the  remaining  area  should  be  reclaimed with  stacked  dumping  and  overburden  and planted with indigenous plant species that are eco-friendly,  if  no  other  specific  condition  on reclamation of pit is stipulated in the E.C.

Partially Complied

About 10% of the total excavated pit is retained as water storage. The remaining area is yet to be reclaimed as the validity of EC is live

16

Overburden  materials    should be  managed within  the  site  and  used  for  reclamation  of mine  pit  as  per  mine  closure  plan/specific conditions

Partially Complied

Overburden material is stored within the site; Mine closure is yet to take place

17

Height of benches should not exceed 5 m and width should not be less than 5 m, if there is no   mention    is    the   mining    plan/specific condition

Partially Complied

In  one pit,  benches  are  provided,  but the width is mostly less than 5m and height  is  mostly  more  than  5m.  In another pit, benches are not provided

20

No mining operations should be carried out at places having a slope greater than 450

Partially Complied

23

Garland drains with clarifiers to be provided in  the  lower  slopes  around  the  core  area  to channelize storm water

Not Complied

28

A minimum buffer distance of 100 m from the boundary of the quarry to the nearest dwelling unit or other structures, not being any facility for mining shall be provided

Not Complied

As per the certificate of Village Officer, the   distance   between    the   Project boundary   and   residential   house   is only 90m.

36

A copy of the clearance letter shall be sent by the proponent to          concerned          Grama Panchayat/District  Panchayat/Municipality/ Corporation/Urban Local Body and also to the Local NGO, if any       from                      whom suggestions/representations, if any, were received while processing the proposal, The Environmental Clearance shall also be put on the website of the company by the proponent

Partially Complied

At      present      the      Environmental Clearance details are not seen in  the website    of    the    VKL    Group    of Companies

37

The proponent shall submit half yearly reports on the status of compliance of the stipulated EC conditions including results of monitored data (both in hard copies as well as by e-mail) and upload   the   status   of   compliance   of   the stipulated  EC  conditions,  including  results  of monitored  data  on  their  website  and  shall update    the    same    periodically.    It    shall simultaneously   be   sent   to   the   respective Regional  Office  of  MoEF,  Govt.  of  India  and also    to    the    State    Environment    Impact Assessment Authority (SEIAA) office

Partially Complied

Last compliance report submitted was that for the period from April 2021 to September 2021. The District Collector issued  stop  memo  to  the  quarry  vide letter dated 13.10.2021

At present, the status of compliance of the stipulated EC conditions including results of monitored data is not found uploaded in the website of VKL Group of Companies

41

The  Project  proponent  shall  ensure  that  no natural water course and/or water resources shall   be   obstructed     due    to    anymining operations.     Necessary safeguard measures to   protect   the   first   order   streams,   if   any originating from the mine lease shall be taken

Partially Complied

The stream originating from  the mine lease  area  is  filled  with  silt  eroded from the dumping site

43

The top soil, if any, shall temporarily be stored at earmarked site(s) only for the topsoil shall be  used for land reclamation  and  plantation. The  over  burden  (OB)  generated  during  the mining    operations    shall    be    stacked    at earmarked  dump  site(s)  only.  The  maximum height of the dumps shall not exceed 8 m and width  20  m  and  overall  slope  of  the  dumps shall  be  maintained  to  450.  The  OB  dumps should be scientifically vegetated with suitable native species to prevent erosion and surface run          off.          In          critical          areas, use  of  geo  textiles  shall  be  undertaken  for stabilization of the dump. The entire excavated area   shall   be   backfilled.   Monitoring   and management  of  rehabilitated  areas  should continue  until  the  vegetation  becomes  self- sustaining

Partially Complied

The OB dump is seen deposited mainly at two places one on the top portion and the  other  on  the  lower  portion  of  the mining lease area. It is not stacked and protected properly and the dump at the lower portion is found eroded severely.

44

Catch drains and siltation ponds of appropriate size  shall  be  constructed  around  the  mine working, mineral and OB dumps to prevent run off of water and flow of sediments directly into the river and other water bodies. The water so collected  should  be  utilized  for  watering  the mine area, roads, green belt development etc. The      drains    shall    be     regularly desilted particularly after monsoon     and  maintained properly

Not Complied

A systematic drainage system is not found implemented.

49

The     funds    earmarked      forenvironmental protection measures and CSR activate should be kept in separate account and should not be diverted   for   other   purpose.   Year       wise expenditure should be reported to the State Environment   Impact   Assessment   Authority (SEIAA) office

Not Complied

61

Occupational  health  surveillance  program  of the workers should be under taken periodically to observe any contractions due to exposure to dust and take corrective measures, if needed

Not complied

5.

Action taken is mentioned as follows:-

“As a follow up of the enquiry conducted by the SEAC on the mass petition filed by the local people against the granite building stone mining projects of M/s. VKL Infrastructure Facilities (P) Ltd. and VKL Projects (P) Ltd., M/s. Al-Falah Metal Crusher and M/s. C.S. Rocks, the SEAC conducted a field inspection and recommended the following to SEIAA

1.

Functioning of the quarry of M/s. VKL Infrastructure Facilities (P) Ltd. and VKL Projects (P) Ltd may be closed with immediate effect

2.

Mining & Geology Department and Revenue Department may be requested to ensure compliance of the order no. B7-2372/2012 dated 17.4.2013 of the District Collector, Thiruvananthapuram

3.

Revenue Department may be requested to take a final decision on encroachment of puramboke/govt. land by the quarry owner before allowing further mining in the area.

4.

Measure aerial distance to nearby houses and assess the threat due to explosions considering the slope of the hill

It was also recommended that the quarry be allowed to resume operation only after the recommendations 2, 3 and 4 above are complied satisfactorily.

The SEIAA agreed in full to the recommendations of SEAC and requested the District Collector, Thiruvananthapuram accordingly. The District Collector vide letter dated 13.10.2021 issued Stop Memo to M/s. VKL Infrastructure (P) Ltd and VKL Projects (P) Ltd. Now the quarry is closed.”

6.

Compliance report of District Magistrate is mentioned to be as follows:-

3.1 D. COMPLIANCE REPORT OF DISTICT ADMINISTRATION

CONDITIONS

STATUS

Details pertaining to encroachment in

Government land.

Encroachment reported by Tahsildar.

Tahsildar  (LR),  Nedumangadu  in  his report     No.     K2-21220/2012     dated 27.04.2022 has reported encroachment of a total area of 54.18 Ares in Survey numbers 363/7,363/1,362/6,362/3,360/,

374/3 and 361/1. In this     encroached area, mining is   found to have done in an area of 14.62 Ares

7.

No response has been filed by the Project Proponent in response to the report which presumably has been served on it in view of directions of this Tribunal quoted earlier. We do not see any reason not to accept the report of the joint Committee comprising of credible senior functionaries representing statutory regulators. Accordingly, the report is accepted and action may be taken in terms of findings and recommendations. The State PCB may also assess and recover compensation on ‘Polluter Pays’ principle, following due process of law. Pending final assessment, the State PCB may also assess interim compensation, having regard to the estimated value of the mined material and damage to the environment. The amount recovered may be utilized for restoration of the environment by preparing an action plan. Compliance report be filed with the Chief Secretary, Kerala within three months and also placed on website of the State PCB.”

6.

Against the above order, the PP filed Civil Appeal No. 6571 of 2022, M/S VKL Infrastructure Facilities (P) Ltd. & Anr. vs. Benny Sebastian & Ors. before the Hon’ble Supreme Court which was disposed of on 23.9.2022 as follows:

“At this stage, while we are not inclined to interfere with the impugned order and leave it open to the appellant(s) to file an application for review before the National Green Tribunal, Principal Bench, New Delhi. However, we give liberty to the appellant(s) to challenge the impugned order, if required and necessary, post the decision of the review application.

Recording the aforesaid, the present appeal is dismissed.

Pending application(s), if any, stand disposed of.”

7.

It is in the above background that the present review application has been filed.

8.

We have heard learned Senior Counsel for the review applicant and perused the record.

9.

The ground for seeking review taken in the review application and IA Nos. 276 - 277 of 2022 filed by the PP is that there is violation of principles of natural justice. The review applicant did not have a copy of the report of the joint Committee which has been accepted by this Tribunal. The original applicant is not acting bonafide. The PP is compliant. During the hearing, learned Senior Counsel has further added that W.P. No. 8335 of 2022 filed by the PP against order of this Tribunal constituting joint Committee is pending before the Kerala High Court and thus the Tribunal has no jurisdiction to pass any further order in view of judgment of the Hon’ble Supreme Court in State of Andhra Pradesh vs. Raghu Ramakrishna Raju Kanumuru (2022) 8 SCC 156. He also relies upon State of Uttar Pradesh & Ors. vs. Uday Education and Welfare Trust & Ors. 2022 SCC OnLine SC 1469 to submit that in absence of bonafides of the applicant, violations of the PP be ignored.

10.

On due consideration, we do not see any merit in the review application. Argument about violation of principles of natural justice, as per PP, is that while as per notice of the State PCB dated 28.5.2022 only two violations were pointed out, the report covered other violations. Thus, PP had no opportunity to show compliance.

11.

Though may appear attractive, in substance the argument has no merit. The letter of the PCB in question, though refers to two violations, encloses copy of the report. In its reply, letter of the PP dated 13.6.2022, in the heading itself, report of the Committee is mentioned. The PP thus had opportunity to make any comment about other violations noted in the report. As the record shows, the PP moved an application before this Tribunal to vacate the order appointing joint Committee which was rejected on 7.4.2022. Thus, the PP was fully aware about the proceedings before the joint Committee and this Tribunal but it chose not to appear before this Tribunal or even to respond to the observations of the joint Committee. Thus, violation of natural justice is merely a convenient plea which is against record.

12.

The next point submitted by the review applicant is about the lack of bonafides of the applicant. In the facts and circumstances of the present case, violations of the PP cannot be ignored on that ground. According to the PP, the DTPC building was constructed after the consent granted to the PP. Consent was in 2014 while the building was completed in 2017. It was further submitted that at some places, the distance was found to be more than 100 meters. We find that the EC condition specifically mentions requirement of maintaining 100 meters distance from DTPC as follows:

“xxx ………………………………….xxx……………………………….xxx

8.

The proposal was considered in the 69th meeting of SEIAA held on 1st June 2017. The Authority accepted the recommendation of SEAC in its 71st meeting held on 20th and 21st April 2017 and decided to issue EC subject to general conditions in additional to the following specific conditions for mining.

1.

Considering the presence of a DTPC building and the intended use of this elevated hillock as a place of local tourism, a buffer distance of 100m must be left as a no development zone from the path connecting the top points on two rocky knobs of Thampuranpara and the eastern edge of DTPC building.”

13.

Thus, violation is patent. The mining activities of the PP involve blasting also. Violations are not only with regard to location but also with regard to proper management of overburden during the mining. According to the review applicant, the overburden management should be seen, as closure plan, not during currency of mining but only after mining activity stops. This is not acceptable as the Progressive Mine Closure Plan submitted by the PP itself annexed as Annexure A-33 to IA No. 277/2022 itself mentions that mine closure is a continuous series of activities which is integral to the process of mining itself. Relevant part thereof is quoted below:

“Projects- compiling plan

Mine Closure encompasses rehabilitation process as ongoing Programme planned to restore Physical, Chemical and Biological activity disturbed by the quarrying to a level of acceptable to all concerned.

Mine closure operation is a continuous series of activities. PMCP is an integral process of mining of minerals and the proposals of scientific mining have had included most of the activities to be included in the PMCP programs.”

13.

Violations also include failure to provide garland drains as per general condition no. 23 as mentioned in the report of the joint Committee. Even if we exclude other violations, it cannot be held that the PP is compliant. No ground for review is made out.

14.

With regard to writ petition before the High Court against appointment of Committee, we are unable to hold that mere filing of a writ petition in the High Court ousts jurisdiction of this Tribunal. Judgement relied upon only holds that law laid down by the High Court is binding on this Tribunal which is different from jurisdiction being ousted by mere filing of a petition. In this regard, we may refer to a three-judge bench judgment by the Hon’ble Supreme Court in Bhopal Gas Peedith Mahila Udyog vs UOI (2012) 8 SCC 326 noting that this Tribunal is a statutory and specialized forum to deal with any issues relating to environment. It was observed:

“40. Keeping in view the provisions and scheme of the National Green Tribunal Act, 2010 (for short "the NGT Act") particularly Sections 14, 29, 30 and 38(5), it can safely be concluded that the environmental issues and matters covered under the NGT Act, Schedule I should be instituted and litigated before the National Green Tribunal (for short "NGT"). Such approach may be necessary to avoid likelihood of conflict of orders between the High Courts and NGT. Thus, in unambiguous terms, we direct that all the matters instituted after coming into force of the NGT Act and which are covered under the provisions of the NGT Act and/or in Schedule I to the NGT Act shall stand transferred and can be instituted only before NGT. This will help in rendering expeditious and specialized justice in the field of environment to all concerned.

41.

We find it imperative to place on record a caution for consideration of the courts of competent jurisdiction that the cases filed and pending prior to coming into force of the NGT Act, involving questions of environmental laws and/or relating to any of the seven statutes specified in Schedule I of the NGT Act, should also be dealt with by the specialized tribunal, that is, NGT, created under the provisions of the NGT Act. The courts may be well advised to direct transfer of such cases to NGT in its discretion, as it will be in the fitness of administration of justice.”

(emphasis supplied)

15.

It is a matter of record that pursuant to setting up of NGT, even pending matters involving environmental issues have been transferred from Supreme Court and various High Courts to NGT, in view of NGT being the appropriate forum and venue.

16.

Further, the order of this Tribunal sought to be reviewed, has merely required the State PCB to assess and recover compensation on ‘Polluter Pays’ principle depending upon the nature and extent of violations and in the said process the viewpoint of the PP is also to be considered. Final order of the State PCB is subject to statutory remedies, including an appeal before this Tribunal.

In view of above, the review application is dismissed.

All pending IAs will also stand disposed of.