AI Structured Summary
Not yet generated for this judgment
Judgment
In this original application, the Applicant has raised the grievance that the Respondent No. 1, Vinod Sablok is illegally operating a borewell at Plot No. 44, Block-E adjacent to vault gym and in front of Max Showroom, Kamla Nagar Bungalow Road, Delhi 110009. The plea of the Applicant is that no permission from any competent authority has been taken by the Respondent No. 1 to dug up the borewell and extract the water from that borewell.
Learned Counsel for the Applicant has pointed out that the complaint dated 28.08.2026 Annexure-3 was made to the Chairman, DJB about the illegal operation of the borewell by the Respondent No. 1 but no action has been taken till now.
Learned Counsel for the Applicant has also placed reliance upon the order dated 27.01.2026 passed in OA No. 35/2026 in the matter of Arun Kumar Tomar vs. Lokesh Gupta & Ors. in similar circumstances.
Having due regard to the above order of the Tribunal and considering the nature of issue which has been raised by the Applicant, we are of view that the factual enquiry at the ground level and verification of the factum of the illegal operation of the borewell by the Respondent No. 1 is required to be done by the Respondent No. 4, DJB and the Respondent No. 9, SDM, Civil Lines. If the allegation of the Applicant is found to be correct, the action is required to be taken by them for sealing/dismantling the borewell in question.
If the above respondents reached to the conclusion that the borewell was illegally operated by the Respondent No. 1, they will also forward a copy of the report to the Respondent No. 6, Member Secretary, DPCC, who, on receipt of the same, will determine the environmental compensation for illegal drawal of ground water for the past period and will take appropriate steps to recover the same after duly following the principles of natural justice.
The respondents, DJB and SDM are directed to complete this exercise within a period of eight weeks by duly following the principles of natural justice and if required, the Respondent, DPCC will complete the exercise within another period of eight weeks from the date of receipt of the report.
The OA is accordingly disposed of.
