Judgment
This Misc. Application has been filed by the Applicant seeking revival of the OA No. 417/2023.
In the OA, the Applicant had raised the grievance against the SOP dated 07.07.2021 issued by the MoEF&CC. The Tribunal by the order dated 19.02.2024 had disposed of the OA taking note of the fact that the Hon'ble Supreme Court was considering the correctness of the SOP under challenge in the OA. The Tribunal while disposing of the OA had observed as under:
“xxx ……………………………………..xxx………………………………..xxx
3.In view of the fact that the Hon'ble Supreme Court is considering the correctness of the SoP under challenge in this OA and has granted stay of the said SoP, we do not intent to proceed further in this OA at this stage.
4.Hence, the OA is disposed of with liberty to the applicant to approach the Tribunal again after the order of the Hon'ble Supreme Court, if any grievance survives at that stage.”
The Applicant has filed this MA for revival of the OA in view of the judgement of the Hon'ble Supreme Court dated 29.07.2026 passed in W.P. (C) No. 1394/2023 in the matter of Vanashakti vs Union of India & Ors.
The Hon'ble Supreme Court in the aforesaid judgment has quashed the SOP dated 07.07.2021 by observing as under:
“xxx …………………………………xxx…………………………………..xxx
67.The second impugned instrument is the 2021 Office Memorandum, an executive instruction issued on 07.07.2021 by the MoEFCC, purportedly in compliance with the direction of the National Green Tribunal in Tanaji B. Gambhire (supra) that a Standard Operating Procedure be laid down for the grant of EC in cases of violation. Under the Office Memorandum, a project not permissible for clearance is liable to be demolished or closed. A permissible project is to remain closed until clearance is obtained, and such EC is to be granted only after assessment of ecological damage and preparation of plans for remedial measures and augmentation of natural and community resources, stated to be in line with the polluter pays principle. A completed project is to be appraised as if it were a new proposal and, if found permissible, granted clearance effective from the date of its issuance. The compensation is fixed at one per cent of the project cost, together with 0.25 per cent of the turnover during the period of violation where operations have commenced, and is halved where the violation is self-reported. The Office Memorandum does not prescribe any cut-off date or identify any class of eligible projects.
68.The challenge to the 2021 Office Memorandum is founded, at the threshold, on the source of power. It is contended that the Office Memorandum, being an executive instruction, could not alter, amend or dilute the 2006 Notification. Reliance is placed on Vanashakti-I, where it was observed that the Office Memorandum does not relate to exercise of any power under the 1986 Act or the Rules. The proposition of law underlying the contention is indisputable. Administrative instructions may supplement the statutory rules and notifications where they are silent on a particular matter, but they cannot amend, supersede, dilute or travel inconsistently with the statutory scheme already in force.1 Where there is a conflict, statutory rules and notifications must prevail.2
69.For similar reasons, the other OM dt. 19.02.2021 permitting post facto CRZ clearance being an administrative order could not have amended the CRZ notification requiring prior clearance and was rightly quashed prospectively in Fatima (supra).
70.The learned Additional Solicitor General further argued that the 2021 OM permitting post-facto EC occupies only a narrow interstitial space left unaddressed by the 2006 Notification. According to her, the 2006 Notification is silent as to the consequences of its breach, and the impugned 2021 OM was issued to occupy that limited unoccupied field of regularisation pursuant to the direction of the NGT in Tanaji B. Gambhire (supra). On this formulation, it was submitted that the 2021 OM operates only as a supplement to the 2006 Notification and does not run counter to it. To assess the validity of this proposition, the two instruments must be examined in juxtaposition.
| Feature | 2006 Notification (prior clearance regime) | 2021 Office Memorandum (post facto regularisation) |
|---|---|---|
| Source and character | A delegated legislation under Sections 3(1) and 3(2)(v) of the 1986 Act read with Rule 5(3)(d), preceded by the draft notification S.O. 1324(E) dated 15.09.2005 and the consideration of objections. | Executive instruction issued by an officer of the Ministry. Its SOP and penalty (paragraphs 10 to 12) recite no exercise of the notification-making power under Section 3(2)(v) read with Rule 5(3)(d). Only the power to issue directions under Section 5 is invoked, and that only to identify violations (paragraph 13). |
| Point in time | Operates before the activity commences. Prior clearance under paragraph 2 is a condition precedent to any construction or preparation of land, except securing the land. | Operates after the activity has been commenced or completed. The appraisal under paragraph 11, Step 3 is of a project already built. |
| Screening and scoping | Screening (Stage 1, Form 1) and scoping (Stage 2, Terms of Reference within sixty days), under paragraph 7, are antecedent to and govern the activity. | No genuine screening or scoping is feasible. Under paragraph 11, Step 3(B) the Committee appraises the completed project “as if it was a new proposal”, the determinants having already been altered. |
| Siting and alternatives | Form 1 and the EIA report (Appendix III) require examination of alternative sites, technology and layout before approval. | No alternative site can be examined. The project stands where it has been built. |
| Public consultation | Mandatory for Category A and B1 projects before the decision (Stage 3, paragraph 7, Appendix IV), when objections may still shape or defeat the project. | Ex ante consultation is impossible. Under paragraph 11, Step 3(B)(vii) the Committee “may insist upon” a hearing, at best a post-mortem upon a settled state of affairs. |
| Nature of assessment | Prospective and preventive. Assesses the likely impact of the activity against an undisturbed baseline. | Retrospective (paragraph 11, Step 3). Assesses only the damage already caused, not the comparative harm of removal. |
| Monetary consequence | None as a price of clearance. Clearance follows a clean prior appraisal. | A penalty under paragraph 12 (one per cent of project cost plus 0.25 per cent of turnover during the violation period, halved where self-reported), with a remediation bank guarantee (paragraph 11, Step 3(B)(viii)). A foreseeable, fixed proportion of cost. |
| Duration and class | A permanent statutory regime of general application. | Open-ended with no cut-off date unlike the six-month, fixed-date window of the 2017 Notification. |
| Effect of clearance | Permission to begin a project not yet begun (grant of prior EC under paragraph 8). | A clearance “effective from the date of issue” (paragraph 11, Step 3(B)(iv)) upon a project already begun. |
This comparison exposes a glaring incompatibility between the 2006 Notification and the 2021 OM. The former rests on the premise that environmental impact assessment must precede the first irreversible act on site. The latter operates at the opposite end of the timeline, beginning after the very act prohibited by the 2006 Notification has taken place. By the time the appraisal under the 2021 OM begins, the project is not a proposal awaiting scrutiny but an existing fact on the ground. The Appraisal Committee is asked to appraise it “as if it was a new proposal”, but that fiction cannot restore the setting in which a new proposal is meant to be examined. There is no genuine screening or scoping left, no alternative site to compare and no public consultation that can still shape the environmental impact of the project. The OM changes the contours and dynamics of assessment, namely what is to be assessed, along with the criteria for the grant of EC under the 2006 Notification. Therefore, the OM supplants the 2006 Notification and does not merely supplement it.
Unlike the 2017 Notification, the 2021 OM abysmally fails the proportionality test. The former confined its appraisal of violator applicants to a time-limited window. The latter has no cut-off date and no finite class. It therefore converts an exceptional violation management response into a permanent parallel route, allowing a proponent to commence first and seek appraisal later upon payment of the stipulated costs. Upon the proportionality framework set out above, the instrument fails at the tests of rational connection and necessity. A measure unlimited in time and class, hedged with a capped and foreseeable compensation, travels beyond what the object of compliance requires and loses its nexus with the abatement of pollution.
An amnesty-regularisation scheme, as held above, is an exception, not a right. A proponent who has built in breach stands upon no footing of entitlement, and the departure can be justified only by a supervening public interest, never that of the proponent. Even then, such a departure must be effected through a measure authorised by, and answerable to, the law from which it departs. The 2021 Office Memorandum meets neither requirement. It is not so authorised, being an executive instruction and not a notification. And in allowing every permissible industry to be regularised upon no more than meagre compensation, it fails the test of reasonable classification noticed earlier. It selects no class upon any supervening public interest, and the only differentia it knows is the permissible character of the project. Permissibility of the activity is a lower threshold as compared to supervening public interest. It only asks whether the project could have been considered had the law been obeyed but does not explain why a project built in breach should be preserved despite the breach. It thus equates the compliant and the defiant, treats unequals as equals and to that extent offends Article 14. It yields to a principle of ‘pollute and then pay’ rather than to sustainable development. A project must survive upon its own strength, and not because the polluter has paid.
The 2021 OM also cannot derive legitimacy from the NGT’s direction in Tanaji B. Gambhire (supra), which it invokes as its warrant. The Tribunal directed only that “a proper SOP be laid down for grant of EC in such cases so as to address the gaps in binding law and practice being currently followed”.3 That direction must be read in context. The Tribunal was considering what the regulator ought to do after a violation had already occurred, in light of decisions where completed constructions received calibrated, case specific relief rather than wholesale demolition. It was authorising a procedure for identifying violators, assessing damage and securing remediation within the discipline of the prior clearance regime. It does not authorise, and could not have authorised, an open-ended mechanism for regularising violations yet to occur, and that too by an administrative instruction. Its object was to plug enforcement gaps in the existing regime, not to supplant it by a standing ex post facto dispensation.
The decriminalisation of the offence does not improve the position. The Jan Vishwas amendments, as observed earlier, are confined to the penal consequences of breach. They cannot and do not authorise an administrative instruction to convert a mandatory prior clearance regime into a perpetual post facto clearance mechanism. A lax implementation regime, coupled with a regularisation scheme unlimited in time and subject to capped environmental compensation at a flea-bite level, renders the prior EC regime otiose, in fact and in law.
76.A further concern arises where the State is itself the project proponent and has violated the prior EC regime without justification. In such a case, the preserver of the rule of law is seen violating the law. The urgent need to fix accountability has now been statutorily addressed in the Jan Vishwas Act, 2023, which inserted Section 15B, making the Head of the Department liable in cases of breach. Any violation regularisation mechanism must further that legislative intent by fixing accountability and imposing individual costs, upon inquiry, on the officers responsible for wanton and unjustified violation. Future amnesty schemes, if any, should provide effective deterrent measures against individual public servants, including disciplinary action and personal liability for environmental damage, wherever the State or its instrumentalities, as project proponents, violate the prior EC regime.
77.In light of the above discussion, we hold the 2021 OM to be invalid and quash it with prospective effect. We do so using our powers under Article 142, taking into account two distinct reasons. First, considerable legal uncertainty prevailed regarding the validity of the impugned instruments and the processing and grant of ECs under them. By an interim order dated 02.01.2024, this Court initially stayed the operation of the 2021 OM. Thereafter, by orders dated 06.01.2025 and 19.02.2025, this Court permitted processing of applications already made for grant of ex post facto EC under the 2021 OM but withheld the final grant until further orders. On 16.05.2025, Vanashakti-I quashed both the 2017 Notification and the 2021 OM. In paragraph 35, the Bench extended the benefit of the ECs already granted under both instruments but did not extend such benefit to the pending applications. On 18.11.2025, the Review order recalled Vanashakti-I. Although Bhuyan J. did not agree with the majority to allow the review, in paragraph 55 of his dissenting opinion he opined that an accommodation could be made for individual project proponents whose applications were pending, by modification/clarification of paragraph 35 of Vanashakti-I.4 Post the Review order, the MoEFCC by OM dated 20.01.2026 directed that all applications pending under the 2017 Notification and the 2021 OM be processed, the final grant remaining subject to further orders of this Court.
78.Second, supervening public interest is involved in several projects which have already been undertaken or substantially progressed in reliance upon the prevailing regulatory position. These include the AIIMS Medical College and Hospital building in the State of Odisha, the Centre of Excellence for Cancer Diseases in Tamil Nadu, several medical colleges, Vijayapura Airport in Karnataka, slum rehabilitation projects and irrigation projects intended for drought prone areas. Unless the 2021 OM is prospectively overruled, projects already undertaken would have to be undone adversely affecting the overarching public purpose they serve.”
The Applicant submits that the Hon'ble Supreme Court has quashed the OM dated 07.07.2021 prospectively. Therefore, the issue of applicability of the OM in respect of the pending project arises. Any alteration or change in the OM dated 07.07.2021 will affect the pending projects, but in the present MA, none of them, even in the representative capacity, have been impleaded. That apart, the Tribunal by the order dated 19.02.2024 had not granted any liberty to the Applicant to seek revival of the OA, but had granted liberty to approach the Tribunal again after the order of the Hon'ble Supreme Court. Hence, the Applicant can avail that liberty and file a fresh OA by impleading the proper parties and by putting forth surviving issues.
Hence, no case is made out for allowing the prayer made in the MA for revival of OA No. 417/2023. The MA is accordingly disposed of.
Footnotes
- 1.Sant Ram Sharma v. State of Rajasthan, AIR 1967 SC 1910, ¶ 7 (Constitution Bench). In a writ petition by an officer of the Indian Police Service challenging his supersession in promotion to the selection grade posts of Inspector General and Additional Inspector General of Police in Rajasthan, the statutory rules being silent on the principles of promotion to selection posts, it was held that “It is true that Government cannot amend or supersede statutory rules by administrative instructions, but if the rules are silent on any particular point Government can fill up the gaps and supplement the rules and issue instructions not inconsistent with the rules already framed”.
- 2.Employees’ State Insurance Corporation v. Union of India, 2022 SCC OnLine 69. Teaching faculty of an ESIC medical college claimed promotion upon two years of service under the Dynamic Assured Career Progression Scheme contained in an office memorandum of the Central Government, though the ESIC (Medical Teaching Faculty Posts) Recruitment Regulations, 2015 required five years. It was held that “In the event of a conflict between an executive instruction, an office memorandum in this case, and statutory regulations - the latter prevail”.
- 3.Tanaji B. Gambhire (supra), order dated 24.05.2021, extracted in D. Swamy (supra), ¶ 30.
- 4.The Review, per Bhuyan J., ¶ 55. The applicants in Miscellaneous Application (Diary) No. 46855 of 2025 and Miscellaneous Application (Diary) No. 52650 of 2025, along with several similar applicants, sought a clarification and a declaration that the benefit of protection extended to the ECs already granted under the 2017 Notification in Vanashakti-I should apply to their projects also. Bhuyan J. opined: "I am of the considered opinion that the concerns of the individual applicants are capable of being accommodated by way of appropriate clarification and/or modification of paragraph 35 of the Vanashakti judgment. For that, the entire judgment in Vanashakti is not required to be recalled."