Solar Power Plants Under GST: Supreme Court Quashes ₹53 Crore Demand on Sterling and Wilson, Says 70:30 Split Cannot Apply Before 1 January 2019

Solar Power Plants Under GST: Supreme Court Quashes ₹53 Crore Demand on Sterling and Wilson, Says 70:30 Split Cannot Apply Before 1 January 2019

Case at a Glance

Sterling and Wilson, which builds solar power generating (SPG) systems on a turnkey basis, paid 5% GST on supply and installation of SPG systems between 1 July 2017 and 31 December 2018. Tax authorities at Thane treated the contracts as works contracts and demanded tax on a 70:30 goods-to-services split, with penalties, totalling about ₹53.36 crore. The Supreme Court held that the 70:30 mechanism applied only from 1 January 2019, that Circular No. 163/19/2021-GST gave assessees an option rather than a mandate for earlier supplies, that SPG systems are not immovable property and so not works contracts, and that the extended limitation under Section 74 could not be invoked. The demand orders were set aside.

The appellant executes solar power projects across several States on an engineering, procurement and construction basis. For the period 1 July 2017 to 31 December 2018 it paid tax at 5% (CGST and SGST together) under Serial No. 234 of Schedule I to Notification No. 1/2017-Central Tax (Rate), which covered the solar power generator system as one item.

By an order dated 17 January 2025 and a summary order dated 24 January 2025, the Joint Commissioner of CGST and Central Excise, Thane, demanded CGST of ₹13,33,95,241 with penalty and an equal amount of SGST with penalty, taking the total to ₹53,35,80,964. The Revenue treated the transaction as a works contract to be taxed with 70% as goods at 5% and 30% as services at 18%. The Bombay High Court dismissed the writ petition on 28 July 2025 on the ground of alternative remedy. The Supreme Court stayed the demand on 25 August 2025.

The Key Question Before the Court

Could the GST authorities apply the 70:30 valuation split, treat SPG system contracts as works contracts and invoke the extended limitation under Section 74 of the CGST Act for supplies made before 1 January 2019?

Option, not mandate — and why a solar plant is not immovable

Justice Sanjay Kumar first held that the High Court should not have dismissed the writ petition in a cursory way, since the bar of alternative remedy “is not a straitjacketed formula to be applied without exception”; the Court therefore decided the merits itself. It then traced the notifications: the 70:30 Explanation was added by Notification No. 24/2018-Central Tax (Rate) only with effect from 1 January 2019. Circular No. 163/19/2021-GST dated 6 October 2021 did not make that split compulsory for earlier supplies. In the Court’s words, “only an option was given to assessees who wanted to take recourse to the new scheme”, and there was “no mandate, either in the Notification or in the Circular” to apply it to pre-2019 transactions.

On the works-contract question under Section 2(119), the Court applied the immovability tests from cases such as Commissioner of Central Excise, Ahmedabad v. Solid and Correct Engineering Works, (2010) 04 SC CK 0039, Sirpur Paper Mills Ltd. v. Collector of Central Excise, Hyderabad, (1997) 12 SC CK 0088 and Bharti Airtel Ltd. v. Commissioner of Central Excise, Pune, (2024) 11 SC CK 0008. SPG panels can be detached from their civil foundations and used elsewhere, and “affixation to something embedded in the earth would not per se qualify the object so affixed as immovable property”. It endorsed the Andhra Pradesh High Court’s view as “the correct view”. Because the 70:30 regime did not exist for the period, there was no basis to allege fraud or suppression, so extended limitation under Section 74 was unsustainable; and the later change of wording in Serial No. 201A (inserted by Notification No. 8/2021) from “solar power generator system” to “solar power generator” could not be applied retrospectively.

What the Court Actually Held

  • The appeal was allowed and the Thane Joint Commissioner’s order dated 17 January 2025 and the consequential summary order dated 24 January 2025 were set aside; parties bear their own costs.
  • The 70:30 goods-services split for SPG systems applies only from 1 January 2019; Circular No. 163/19/2021-GST merely gave an option for earlier supplies.
  • Supply and installation of SPG systems is not a works contract under Section 2(119) of the CGST Act, as the systems are not immovable property.
  • With no 70:30 regime in force for the period, allegations of fraud or suppression could not stand, so the extended limitation under Section 74 was not available.

Why This Judgment Matters

  • Solar EPC contractors facing similar demands for July 2017–December 2018 now have a direct Supreme Court ruling to rely on.
  • It clarifies that a later circular cannot convert an optional mechanism into a retrospective tax demand.
  • It reinforces that Section 74 needs a real foundation of fraud or suppression, not a change in the Revenue’s view.

What Should Advocates Take Away From the Judgment?

For Taxpayers

  • Check whether your pre-2019 solar contracts were taxed at 5% under Serial No. 234 of Schedule I.
  • A show cause notice relying only on the 70:30 split for that period is open to challenge.
  • Extended limitation needs specific allegations of fraud or suppression.

For Counsel

  • Cite this ruling on the option-not-mandate reading of Circular No. 163/19/2021-GST.
  • Argue immovability on the facts: detachability and purpose of fixing to a foundation.
  • Alternative remedy is not an absolute bar to writ relief in clear cases.

Key Takeaways

  • 70:30 valuation for SPG systems runs only from 1 January 2019.
  • A circular giving an option cannot be enforced as a mandate for past periods.
  • Solar panels fixed to foundations but detachable are not immovable property.
  • Section 74 cannot be invoked where there is no basis for alleging fraud or suppression.

Frequently Asked Questions

Is solar power plant supply a works contract under GST?

In this case the Supreme Court held that supply and installation of SPG systems was not a works contract under Section 2(119) of the CGST Act because the systems are not immovable property.

Does the 70:30 split apply to solar supplies made in 2017–2018?

No. The Court held that the 70:30 regime applied only from 1 January 2019 and that the 2021 circular gave only an option for earlier supplies.

What happened to the ₹53 crore demand on Sterling and Wilson?

The Supreme Court set aside the demand orders dated 17 January 2025 and 24 January 2025 and allowed the appeal, with parties bearing their own costs.

Conclusion

The ruling brings clarity to a recurring dispute for India’s renewable energy sector. Tax at 5% on SPG systems for the first eighteen months of GST cannot be reopened by applying a valuation rule that came later.

Practical takeaway: If you received a demand for pre-2019 solar EPC supplies based on the 70:30 split, examine it against this judgment before paying or appealing.

Read the full judgment on CourtKutchehry: View judgment →