High Courts(2026) 11 DEL CK 3515

Ms Narendra Builders In Jv Vs National Highways And Infrastructure Development Corporation Limited

Delhi High Court · 19 Nov 2026 · Vinod Kumar, J

Open full page

Judgment

25 paragraphs · 571 words

I.A. 28577/2026 (Exemption)

1.

Exemption is allowed, subject to all just exceptions.

2.

The application is disposed of.

I.A. 28578/2026 (under Section 151 CPC filed on behalf of petitioner seeking permission to file lengthy synopsis and list of dates)

3.

For the reasons stated in the application, lengthy synopsis and list of dates are allowed.

4.

The application is disposed of.

O.M.P.(I) (COMM.) 482/2026

5.

This is a petition under Section of 9 of Arbitration and Conciliation Act, 1996 seeking interim measures of protection.

6.

Issue notice.

7.

Learned Counsel for the respondent accepts notice on behalf of respondent.

8.

Reply be filed within four weeks. Rejoinder thereto, if any, be filed within two weeks thereafter.

9.

Re-notify on the next date of hearing.

I.A. 28575/2026 (under Section 151 CPC for ad-interim and ex-parte stay/order for interim measure of protection.

10.

This is an application under Section 151 CPC filed on behalf of petitioner for ad-interim and ex-parte stay/order for interim measure of protection praying to stay the operation, implementation and effect of temporary suspension order bearing No. NHIDCL/Tripura/Mtc./2026-27/2153 dated 25.09.2026 issued by the Respondent-National Highways and Infrastructure Development Corporation Limited (in short ‘NHIDCL’).

11.

Vide the aforesaid notice, the Respondent has temporarily suspended the Petitioner from participating in ongoing and future bidding process of NHIDCL, Ministry of Road, Transport and Highways (in short ‘MoRTH’).

12.

The case of Petitioner is that the Petitioner is an Engineering, Procurement and Construction (in short ‘EPC’) contractor in respect of improvement and widening of two lanes with paved shoulder of road on Fultali-Jurichhara Section of NH-208 (Package-II), State of Tripura. This contract was awarded to the Petitioner vide Letter of Acceptance dated 24.11.2020.

13.

It is submitted by the Learned Counsel for the Petitioner that the project was completed on 02.02.2023 and completion certificate, thereafter, was issued by the Respondent. The project is under the Defect Liability and Maintenance Period. It is submitted that the Respondent observed certain defects and issued a cure notice of sixty days to carry out.

14.

Vide impugned temporary suspension notice dated 25.09.2026, in view of failing to complete rectification within the prescribed time and failure to start the maintenance and repairs, in exercise of powers conferred by MoRTH circular dated 06.10.2021, the Petitioner was temporarily suspended from participating in ongoing and future bidding of NHIDCL, MoRTH.

15.

The Learned Counsel for Petitioner has drawn my attention to the MoRTH circular dated 06.10.2021. Clause 5 of the said circular enjoins upon Respondent to issue a notice to the contractor by giving 15 days time to furnish its written reply and allow personal hearing before the Competent Authority before passing an order of barring the contractor from bidding for other construction.

16.

It is further submitted by the Learned Counsel for the Plaintiff that without any such show cause notice, the impugned order has been passed, suspending the Petitioner from participating in ongoing/future bidding of NHIDCL, MoRTH for one month.

17.

The Learned Counsel for the Respondent submits that he requires to seek the instructions from the Department.

18.

I have carefully perused the MoRTH circular dated 06.10.2021.

19.

I agree with the Learned Counsel for Plaintiff that a 15 days notice was required to be given to the Petitioner before suspending him for participating in ongoing future bidding of NHIDCL, MoRTH.

20.

Accordingly, I stay the operation of impugned order dated 25.09.2026 till further orders.

21.

Re-notify on 28.01.2027.