M/s. Prestige Estates Projects Pvt. Ltd. & Anr. Vs Ann. George Edathuruthukaran
National Consumer Disputes Redressal Commission · New Delhi · 14 Feb 2025 · Subhash Chandra, Presiding Member · AVM J. Rajendra, AVSM VSM (Retd.), Member
Judgment
Learned counsel for the appellant fairly states that there has been delay in handing over the possession of the project for about two years and four months and thus complainants are entitled for certain compensations. At the same time, the learned State Commission has granted relief well beyond what has been prescribed under law. It is established position in DLF Homes Panchkula Pvt. Ltd. Vs. D. S. Dhanda, in CA Nos. 4910-4941 of 2019 decided on 10.05.2019 that for single cause of action constituting deficiency in service, multiple relief cannot be granted. However, the learned State Commission by the following order went well beyond the scope of law established:-
"(a)The opposite parties are directed to pay to the complainants interest @8% per annum on the amount of Rs. 1,20,33,760/-(Rupees One Crore Twenty Lakhs Thirty Three Thousand Seven Hundred and Sixty only) for the period from 14.05.2010 to 30.10.2012, within a period of one month from the date of receipt of a copy of this judgement;
(b)The opposite parties are directed to pay an amount of Rs.2,50,000/- (Rupees Two Lakhs Fifty Thousand only) to the complainants as compensation for the mental agony, hardships and losses caused to them due to the delay in completion of the construction as agreed in Exhibit A2, within a period of one month from the date of receipt of a copy of this judgement;
(c)The opposite parties are also directed to pay to the complainant an amount of Rs. 50,000/- (Rupees Fifty Thousand only) as costs of this litigation within a period of one month;
(d)If the amounts in (a) and (b) are not paid within a period one month from the date of receipt of a copy of this judgement, the amounts shall carry interest (@9% per annum."
Considering the submissions made and careful perusal of records, we consider it appropriate to modify the order of learned State Commission dated 02.09.2024 and direct the OPs/Appellants to pay delay compensation in the form of simple interest @ 8% per annum on Rs. 1,20,33,760/- paid as consideration for the period from 14.05.2010 to 30.10.2012. Appellants/OPs is also directed to pay costs of Rs. 50,000/-.
However, in view of the order of Hon'ble Supreme Court in DLF Homes Panchkula Pvt. Ltd. Vs. D. S. Dhanda, in CA Nos. 4910-4941 of 2019 decided on 10.05.2019, the order of learned State Commission granting Rs. 2,50,000/- to be paid by the OP to the complainant as compensation for mental agony, hardships and losses is set aside.
The above mentioned amount shall be paid within a period of two months from today, failing which the simple interest applicable shall be @ 12% per annum.
With these directions, FA/1034/2024 is disposed of.