AI Structured Summary
Not yet generated for this judgment
Judgment
This is a complaint filed in Form ‘M’ on 29 July 2020 by Shri Vivek Gupta (the Complainant) against M/s. Jeevan Ashray Welfare Society. (the Respondent) seeking a refund of Rs.11,11,000/- (Rupees eleven lakh eleven thousands only) paid by him to the Respondent Society towards booking and other costs relating to a 4 BHK apartment (admeasuring super area of 2300 sq. ft.) along with 2 car parking at P-II Zone, MPD-2021 under DDA’s Land Pooling Policy Scheme along with interest. Further, the Complainant has prayed for restraining the Respondent from collecting funds from public being an illegal entity and also for registration of an FIR for cheating public.
The brief facts of the case are that in October, 2012 the Complainant booked a 4 BHK apartment with a super area of 2300 sq. ft. and with 2 car parking at P-II Zone under MPD-2021 under Land Pooling Policy of DDA to be developed by the Respondent Society M/s. Jeevan Ashray Welfare Society; that the total cost of the apartment was as Rs.43,51,000/- including the cost for 2 car parking as Rs. 2,00,000/-. This cost included the cost of land as Rs. 9,31,500/-; that as per Brochure of the Society total land cost as Rs. 9,31,500/- was to be deposited along with the application form for a 4 BHK apartment with 2 car parking.
The Complainant paid total amount of land cost as Rs. 9,31,500/- by way of two cheques of equal amount dated 29 October,2012 and 02 December,2012. The Complainant has also paid Rs. 1,65,000/- vide cheque dated 9 December, 2013 to buy extra land as per demand from Respondent. Thus, the Complainant has paid Rs. 10,96,500/- towards total land cost. Apart from land cost, the complainant has also paid Rs. 100/- as Share Money and Rs. 14,400/- towards annual subscription charges up to July 2018 (totaling to Rs. 11,11,000/-); that at the time of booking the apartment in October,2012 he was assured that the construction work relating to the project would start by early 2014 and the project will be completed in a completion time of 36-48 months meaning thereby, by December,2018 but not even a single brick has been laid in last 8 years.
The Complainant has further stated that the Society is being promoted by employees of Life Insurance Corporation of India (LIC) and some builders by prefixing the keyword as ‘Jeevan’ to cheat people as if it is being promoted by LIC.
Further, an additional demand of Rs. 12,65,000/- was raised vide letter dated 14th March,2019 by the Respondent for purchase of more land due to reduction in FAR by the Government. The Respondent Society has also given option for exit from the scheme for those who choose not to pay enhanced price for land and the Complainant opted for exit option and informed the Respondent through email on 6 May, 2019.
The Complainant further submitted that there has been no response from the Respondent Society thereafter. Even no reply to the legal notice served on 12 July 2019 on Mr. Subhash Nair, Treasurer of the Respondent Society has been received.
After hearing the Complainant on 03 September 2020, a notice was issued to the Respondent Society along with copy of complaint returnable on 08 October 2020. On 08 October 2020, no one was present for the Respondent despite service of notice and a fresh notice was issued to the Respondent for 03 November 2020.
On 03 November 2020 Shri Shyamal Kumar, Advocate appeared for Respondent and submitted that his services has recently been engaged in two cases (36/2020 and 42/2020) and requested for two weeks time to file a reply in other case as well, to enable the Authority to hear both cases together. Upon enquiry, the Counsel for the Respondent submitted that the reply in this case has already been filed by the Respondent on 07 October, 2020 with a copy to the Complainant.
The Respondent in their reply dated 07 October 2020 to the complaint have made submissions as under :
That the complainant has not approached this Hon’ble Authority with clean hands and is guilty of suppressing the material facts as well as misleading the Hon’ble Authority on vital facts. M/s Jeevan Ashray Welfare Society is a Welfare Society duly registered under the Society Registration Act, 1860.
That there is no agreement to develop or sale the agricultural land parcels as purchased in the name of the society or any lapse on the part of society and the purchase of agricultural land cannot be held to be an ongoing project at this stage by any stretch of imagination.
That the complaint, as filed is even not otherwise not maintainable for misjoinder of parties; The agricultural land purchased was required to be surrendered with the Land Pooling Authority of DDA who is responsible for allotting the proportionate developed land in the name of the society as per the aforesaid policy after which construction of a residential complex could be undertaken. The society has already surrendered the land as per the policy with DDA and there is no breach of understanding between the members.
The status of all the members of the society including complainant herein are the same and the present office bearers cannot be held to be promoters of the Society. The Complainant himself is an accomplice who voluntarily participated in the Land Pooling Policy. The annual General Body Meeting of the Respondent Society was held on 29th July, 2018 at the Constitution Club of India attended by several members, in which the activities of the society as well as progress in land policy was discussed at length. The election for the office bearers was also held, however, none of the members came forward and unanimously decided to continue with the present office bearers of the society.
The allegation that society registered under the Society Registration Act, 1860 cannot participate as Development Entity is absolutely wrong, the action initiated by the Revenue department of Delhi Govt. pursuant to letter dated 19.11.2019 has been stayed by the Hon’ble High Court of Delhi. Hence the contention raised in the complainant in this regard is liable to be rejected.
Thereafter on 28 October 2020, the Complainant filed his replication and made submissions as under :
That as per Caution Notice issued by DDA and EOW in leading newspapers across Delhi, every real estate project has to be registered with RERA Delhi but till date, Respondent has not got registered with RERA, Delhi.
That the RERA, Delhi has also taken suo moto cognizance against the Respondent.
That the respondent has failed to tell the purpose for which land was purchased and they also submitted that the land purchased has been surrendered to the DDA for Land Pooling.
That the aim and objective of the society shall be purely for charitable purpose which includes relief of the poor, educational, social, medical relief and the advancement of any other objects of general public utility. The Respondent, being a welfare society, has failed to incorporate a list of charitable works undertaken and completed by the society, rather the management of society has worked as builders. The Respondent has not replied about floating of more than 10 societies by the same management and all these societies are registered at the same address.
Misjoinder of parties; Complainant submitted that he has filed the copy of letter sent by Dy. Director, DDA to Delhi Police EOW for taking action against Respondent society. Further submitted that he has already filed the copies of such advertisements wherein EOW Delhi Police has asked the public to report them such frauds.
That Jeevan Ashray Welfare Society purchased the same land for the society whose value of land was Rs. 1.5 Crores on 20-01-2014 and it rose 6 times to Rs. 9 Crores within a span of just nine days and they paid Rs. 54,00,000/- as stamp duty putting the members at a great loss and enriched the seller by whopping profit in the deal.
That the complainant also annexed the copy of Letter from Hon’ble Chairman RERA, Delhi to the Chief Secretary, Delhi that number of societies that bear registration in Delhi under the Societies Registration Act,1860 may be indulging in the activities of promoting housing projects, DDA’s and Delhi Police’s Caution Notice in newspapers and latest on 27-08-2020 on their twitter official website which put members of the society at loss.
On 02 November 2020, the Respondent filed a reply to replication whereby Respondent raised objections to the replication filed by the complainant as under :
No new plea can be allowed to be introduced or placed on record by way of replication after filing of the written statement/reply.
The complainant has raised the issues of transaction related to sale and purchase of land between M/s Nirmal Suppliers Ltd. and M/s Micro Abrasives Pvt. ltd. Both the companies are duly registered under the Companies Act having various business activities and are separate legal entities and having nothing to do with the captioned complaint in which new averments have been made by the complainant by way of replication and which is not the part of original complaint.
The information regarding the society is not in the public domain and is its privileged information. The complainant is misusing the same to spread false and frivolous information with the malafide intention of defaming the respondent thus the same cannot be taken on record.
During the hearing held on 03 November, 2020, the Complainant was also present in person and he reiterated his prayer for refund of amount deposited by him. The Complainant was also directed to file a complete set of the 26 page brochure published/ circulated by the Respondent Society with regard to the housing project.
On 25 November, 2020, the complainant filed reply to the objections raised by Respondent on 02 November, 2020 along with a copy of Brochure circulated by the Respondent Society and he made the submissions in reply to objections raised for replication as under :
The respondent instead of replying to the submissions to the complainant deliberately and intentionally avoiding those issues.
It is correct that M/s Nirmal Suppliers Pvt. Ltd. and M/s Micro Abrasives Pvt. Ltd. are legal entities but it is incorrect to say that both the companies are not known to the respondent society and they are unrelated.
That the plea of the respondent that the sale deed is not public document is incorrect. Every member has a right to inspect every documents of the society as the land purchased is from the funds deposited by them. The society has no business to say from which sources the details have been procured.
The pleadings of both the parties were heard at length on 02 February, 2021. On the merits of the case, the Respondent Society submitted that it had not violated any of the provisions of the Real Estate (Regulation and Development) Act, 2016; that the Complainant has tried to mislead this Authority by not providing full facts including the application made by the Complainant for membership of the society in the prescribed forms and the terms and conditions mentioned in such application form; that the payments made by the Complainant were towards land cost and not for the flat or apartment; that the land pooling policy is under active consideration of DDA; the Respondent Society sought the dismissal of the complaint.The Counsel for the Respondent Society further contended that the complaint in its present format is not maintainable under the provisions of the Real Estate (Regulation and Development) Act, 2016 read with Rule 33 of the National Capital Territory ofDelhi RERA (General) Rules, 2016.
The Counsel for the Respondent Society further contended that the refund and interest sought in the complaint filed in form M is not maintainable before this Authority. The Counsel for the Respondent Society further contended that the Complainant had paid only cost of the land and membership fee of the society and that the Complainant had not paid any amount towards the construction of the flat.
M/s. Jeevan Ashray Welfare Society is a society registered under the Societies Registration Act, 1860 and it has been granted a registration certificate No. S/ 1307/SDM/NW/2012 by Registrar of Societies, District North-West, Govt. of NCT of Delhi on 21 September 2012.
The Respondent Society appears to have floated this project in which the Complainant Shri Vivek Gupta has booked a flat. The Respondent Society has prepared a common Membership Application Form for all its members. While the membership application form duly filled in by the Complainant has not been placed on record by either side, it has been brought to notice that such application forms bears the stamp and signature on behalf of the Respondent Society and provides details such as the payment schedule andannual operation charges etc.
Since the application form above referred are part of the documents prepared and printed by the Respondent Society and the application form duly filled in by the members bears the stamp and signature on behalf of the Respondent Society, it becomes abundantly clear that the Respondent Society is aware of the applicability of the Real Estate (Regulation and Development) Act, 2016 to its project; and that its contentions to the contrary are quite futile.
The Complainant clearly state that the unit booked by him will have a super area of 2300 sq. ft. and 2 car parking and break-up of the cost of the flat. Any payment made by the members would accordingly be counted towards the cost of the flat and the various components are integral to the total cost of the flat and have no existence or meaning as individual components. The contention of the Respondent Society that the Complainant has paid only towards land cost and not towards the cost of the flat has accordingly to be rejected squarely.
Further, from the reading of the Act, it becomes abundantly clear that the Respondent Society is covered within the meaning of the term ‘Promoter’ as defined in Section 2 (zk) of the Act as under :
2(zk)
“……..
(iv)an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or”.
The Respondent Society has not contested the claim made by the Complainant that he repeatedly demanded a refund of the deposits since May 2019;. The Respondent Society has also not contested the claim of refund made by the Complainant; and that even after more than eight years of receiving the deposit, it has not provided any correct and updated information as to current state of the project and the likely date by which the project will be completed. The Respondent Society is duty bound to provide to all its members including the Complainant, correct and updated information with regard to the project in a transparent manner and failure to discharge these obligations attracts the provisions of Section 12 of the Act, which reads as under:-
“Section 12. Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
In view of the above, we are of the considered opinion that M/s. Jeevan Ashray Welfare Society (the Respondent) must return the entire amount of Rs.11,11,000/- (Rupees eleven lakh eleven thousand only) to Shri Vivek Gupta (the Complainant) within forty five days of issuance of this order, along with interest calculated at the rate of 9.30 per cent per annum (MCLR + 2%) from the date of payment of each amount until the date of its actual return.
Ordered accordingly.
No orders as to costs.
This order may be served upon the Complainant Shri Vivek Gupta and the Respondent M/s Jeevan Ashray Welfare Society in normal course via Speed Post and over email. A copy of the order may also be uploaded on the RERA web-portal as per norms.