Judgment
Adv. Shobit Dimri appeared on behalf of the Complainant.
The Complainant submitted that he has been paid a sum of Rs. 24,65,110/- to the Respondent Society for their upcoming housing project in L-zone, Dwarka, under Land Pooling Scheme of Delhi Development Authority.
However, it is submitted that the project has not yet started and there is no allotment of the land by DDA.
The Respondents had misled the Complainant by giving the wrong advertisement regarding the nature of the project.
Let a notice of the complaint be issued to the Respondents with a direction to file their reply by 15.03.2024 with copy served on the Complainant.
The Complainant shall file rejoinder, if any, by 30.03.2024 with copy served on the Respondents.
It is noted that Ms. Sangeeta is also a co-allottee along with Sh. Vikas Yadav. However, name of Ms. Sangeeta is not reflected in the title in Form ‘M’.
Ld. Counsel for the Complainant seeks liberty to make necessary amendments.
Request allowed.
Office is directed to provide the edit mode to the Complainant within two days from today. The Complainants shall make necessary amendments in Form ‘M’ within 7 days.
Matter be listed for further hearing on 18.04.2024 at 11:30 am.