High CourtsSINGLE BENCH(2017) 05 RAJ CK 0137

Urban Improvement Trust vs Nand Lal Kumawat S/o Shri Kalu Lal Kumawat

Rajasthan High Court · Decided on 29 May 2017

HON’BLE JUDGES
G.R. Moolchandani
CASE NUMBER
224 of 2008

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

129 paragraphs · 1,316 words
1.

The instant second appeal is filed by the appellant

defendant against the judgment dated 18/04/2007 passed by

learned Additional District Judge No.2, Udaipur in Civil Appeal

No.9/2002 and judgment dated 09.10.2001 passed by Civil Judge

(Junior Division), City North, Udaipur in Civil Original Case

No.254/96. The trial Court has decreed the suit of the plaintiff-

respondent Nand Lal by granting permanent injunction and

learned First Appellate Court has dismissed the appeal of

defendant/appellant Urban Improvement Trust on ground of delay

of forty eight days without deciding the first appeal on merit.

2.

Heard the submissions of both the sides, learned

counsel for the appellant has submitted that the first appellate

Court has committed grave illegality, while dismissing the first

appeal sheer on the ground of delay of forty eight days, the

appeal was of Urban Improvement Trust, a Local Body. Relying

upon the judgment in case of State of Nagaland vs. Lipok Ao

and Others, RLW 2005(3) 357, learned counsel has submitted

that delay of forty eight days was not wilful, which was explained

and it was expected to be condoned by first appellate Court, but

ignoring the mandate of law without any cogent reason, learned

trial Court has passed wrong judgment by rejecting the appeal on

the ground of delay, which is not tenable under the law. Public

land of crores of rupees of the UIT is involved, which has wrongly

been trespassed and construction is being undertaken over the

land illegally. Referring extracts of evidence, it has been further

argued that the respondent-plaintiff has himself accepted that he

was allotted plot No.38B having a dimension of 1250 sq. feet but

apparently grabbing the another land having more than double

area construction is being illegally undertaken on another plot

number 47-B. It has further been contended that learned trial

Court has exceeded its jurisdiction by granting relief without any

prayer and no such order could be passed for regularization of the

land, on which the plaintiff-respondent was a trespasser and

finding of learned trial Court is apparently bad, notwithstanding,

the first appellate Court did not consider it and dismissed the first

appeal on technical ground of delay of forty eight days, whereas

delay caused was explained and was liable to be condoned, since

government cannot be treated on the same footing of an

individual and it has been contended to allow the appeal.

Learned counsel for the respondent, while taking

support of Pundlik Jalam Patil (D) by LRs vs. Exe . Eng.

Jalgaon Medium Project & Anr, 2008 (17) SCC 448, P.K.

Ramachandran vs. State of Kerala & Anr ., AIR 1998

Supreme Court 2276, Cheelaram vs. Manak, AIR 1997

Rajasthan 284, Shankarlal vs. Mangilal, 2006(3) DNJ (Raj.)

1347) has contended that there is no illegality in the judgment

impugned, both individual and government are to be treated

equally on the point of delay, wilful delay can never be condoned

and it is an admitted position that the plaintiff-respondent was

given possession over 47-B and bonafidely permission was sought

by him for construction of the premises, which was wilfully kept

prolonged, so under impression of implied sanction, bonafide

construction was undertaken, respondent is prepared to pay the

dues as ordered by the learned trial Court for the regularisation of

the land found in excess, the finding of learned trial Court as well

as of first appellate Court are not bad at all, so appeal be

dismissed.

3.

Perused the record and examined the impugned

judgment/s.

4.

Pleadings reveals that Plot No.38B possessed by the

plaintiff was regularized by the defendant UIT, which was allotted

to plaintiff after deposit of Rs.282.78 vide receipt No.137026/12

dated 06/11/71, but despite applying for the approval of the map,

the same was not sanctioned by the UIT. Later on, the scheme

was revised by the defendant UIT and numbers were altered,

whereas the possession was kept static and the plot of the plaintiff

became 47B in place of 38B.

UIT, while filing the written statements, refuted

the pleadings and pleaded that plaintiff was allotted plot No.38B

and plot No.47B was allotted to Ramlal Mathur and both the plots

were having different dimensions, so plaintiff was not entitled to

undertake construction on another''s plot and he is a trespasser

thereon.

5.

The trial Court framed following issues :-

"VERNACULAR MATTER OMITTED"

and decided the suit in favour of the plaintiff with

a direction that if the area of plot No.47B is found more than that

of 38B, then UIT to recover cost of it, at prevailing rates, thence

the plot be recorded in the name of the plaintiff.

6.

Perusal of the judgment of trial Court relating to

issue No.1 at page 6, which refers to the evidence of defendant

urban improvement trust narrates:-

"VERNACULAR MATTER OMITTED"

and plaintiff Nand Lal has admitted in his

evidence that he was allotted plot No.38B and was

constructing plot No.47B, which is of about 3600 sq. feet

and has asserted in his cross-examination that he was not

delivered documents pertaining to plot No.47B.

7.

Application preferred under Section 5 of the

Limitation Act by appellant UIT contains following reasons:-

"VERNACULAR MATTER OMITTED"

Sudhanshu Singh, tehsildar of UIT, Udaipur, which has been

rejected by the first appellate Court.

8.

Indisputably, the appellant is a local body and

both the plot i.e. Plot No.38B and 47B are different plots and

having different dimensions and measurements besides,

respondent/plaintiff has admitted that he was not given title

documents pertaining to plot No.47B.

9.

The trial Court decreed the suit of the plaintiff

Nand Lal on 09/10/2001 and the appeal has been preferred on

08/01/2002 and reason of delay of forty eight days, explained in

the application, does not appear to be non-bonafide because delay

of forty eight days for which explanations have been given in the

application, which is supported by an affidavit of Tehsildar may not

be said to be unexplained, moreover the delay is also not

protracted but is of forty eight days, besides it the lis involves

stake of pubilc land involving crores of rupees, which has

remained undecided on merit.

10.

Hon''ble Supreme Court in State of Nagaland

vs. Lipok Ao and Others (supra) has observed that pragmatism

in justice oriented approach be there and has held in para 21 that

Government decisions are proverbially slow encumbered, as they

are, by a considerable degree of procedural red-tape in the

process of their making and in Pundlik Jalam Patil (D) by LRs

vs. Exe . Eng. Jalgaon Medium Project & Anr (supra), Hon''ble

Supreme Court has observed in para 25 :-

25.It is true when the State and its instrumentalities are the applicants seeking condonation of delay they may be entitled to certain amount of latitude but the law of limitation is same for citizen and for Governmental authorities. Limitation Act does not provide for a different period to the government in filing appeals or applications as such. It would be a different matter where the Government makes out a case where public interest was shown to have suffered owing to acts of fraud or collusion on the part of its officers or agents and where the officers were clearly at cross purposes with it.

11.

Upon considering all the facts and in the aforesaid

backdrop, it appears to be just and reasonable to allow the appeal

and remit back the appeal to the first Appellate Court to decide

the appeal on merit. Therefore, application seeking condonation of

forty eight days delay preferred by the appellant before the first

Appellate Court is hereby allowed and the matter is remanded to

the first Appellate Court for hearing and deciding it afresh after

affording hearing opportunity to both the sides. Both the parties

may appear before the first appellate Court on 15th July, 2017.

Copy of the judgment and record of the court/s

below be sent back forthwith. The appeal stands disposed of in

aforesaid terms.