The petitioner who conducts quarry in 96.60 Ares of land in Survey No.75/4 of Pirayiri Village of Palakkad Taluk, has filed this writ petition seeking the following reliefs:
“i.issue a writ of mandamus or any other appropriate writ, order or direction commanding the respondent to issue forthwith transit pass/ movement permit through the KOMPAS portal to the petitioner in respect of the quarrying permit granted to the petitioner, without any further delay;
ii.Declare that the action of the respondent in withholding the issuance of the transit pass/movement permit to the petitioner, despite the subsistence of a valid renewed quarrying permit and in the absence of any subsisting order lawfully suspending the same, is arbitrary, illegal and unsustainable in law and Geologist is liable to compensate the loss caused to the petitioner.
iii) grant such other reliefs as this Hon'ble Court may deem fit and proper in the interests of justice. &
iv) To dispense with production of English translation of documents.”
Alleging that the second respondent Geologist unnecessarily rejected the renewal of permit of his quarry unit, the petitioner instituted W.P(C) No.12160/2026 before this Court. As per Ext.P7 judgment, this Court set aside the aforesaid order of rejection of the application for renewal, and directed the second respondent to consider the application for renewal of permit afresh, in accordance with law, after affording an opportunity of being heard, to the petitioner. It was further directed in the aforesaid order that a study report dated 10.03.2025 from Dr.T.Thimmaiah Institute of Technology, Karnataka, upon the blast-induced ground vibration at the quarry of the petitioner shall be borne in mind by the second respondent, while considering the renewal application. Thereafter, the quarry permit of the petitioner was renewed by the second respondent, but no transit pass was issued. In the meanwhile, the petitioner had approached this Court by filing W.P(C) No.25830/2026 for police protection alleging obstruction caused by certain persons to the lawful quarrying works conducted by him. As per Ext.P14 order, this Court directed the SHO of Police, Town North Police Station, Palakkad, to afford adequate police protection for the conduct of activities in the quarry of the petitioner, which are approved by the authorities concerned. Again, the petitioner approached this Court by filing W.P(C) No.28475/2026 alleging that the second respondent is unnecessarily refusing to issue transit pass to the petitioner stating the reason that the blasting operations in the quarry of the petitioner had caused damages to a water tank situated at a distance of 161 metres from the quarry. As per Ext.P15 judgment, this Court directed the second respondent to issue transit pass within a week from the date of production of the judgment in that case. Thereafter, the second respondent issued Ext.P16 transit pass to the petitioner. While so, the second respondent issued Ext.P17 e-mail communication, calling upon the petitioner to appear before the second respondent for hearing at 11:00 a.m on 05.09.2026, in connection with a complaint received at that office. Due to medical urgency, the petitioner sought two days’ time for his appearance before the second respondent. Thereupon, the second respondent issued Ext.P18 notice directing the petitioner to stop all the quarrying operations for the reason that a site inspection conducted at the quarry revealed that the permit conditions of State Environment Impact Assessment Authority (SEIAA) were not implemented. As per Ext.P21 interim order passed by this Court on 18.09.2026 in W.P(C) No.30815/2026, this Court directed the second respondent to withdraw Ext.P18 stop memo. The petitioner was also directed to address the objections noted in the site inspection report, and to ensure that such objections are done away with, by ensuring compliance with the requirements of law. Alleging that the second respondent is still denying the issuance of movement pass, the petitioner has instituted this writ petition seeking the aforesaid reliefs.
The second respondent filed counter affidavit stating that the direction of this Court in Ext.P21 was duly complied by the second respondent by issuing Ext.R2(a) order, withdrawing Ext.P18 stop memo. However, it is stated by the second respondent that the petitioner had violated the permit conditions and illegally quarried granite building stone at the buffer zone extending to an area of 10 metres in length, 4 metres in width and 1.5 metres in height. It is also stated that the petitioner transported granite building stones from the quarry in vehicles carrying loads in excess of the permitted limits, and that the police authorities have seized those lorries, and forwarded the same to the office of the second respondent. Thereafter, the Motor Vehicles Department is said to have imposed fines for overloading, and the Department of Mining and Geology realised royalty and compounding fee at the rate of Rs.11,200/-each, in connection with four instances of transportation of excess quantities of building stone. The other contentions raised by the second respondent in the objection is that the petitioner defied the e-mail communication to stop quarrying operations and transportation of granite building stone on 24.10.2026 and 25.10.2026, on account of the orange alert declared by the Meteorological Department, and transported 78 loads of granite stones on 24.10.2026. The Chair Person of the District Disaster Management Authority is stated to have convened meetings, and initiated proceedings in connection with the allegations pertaining to permit violations by the petitioner, and causing damage to the houses and property of the nearby residents of that quarry. The Kerala State Pollution Control Board is said to have reported various violations on the part of the petitioner. A joint inspection conducted by the authorities concerned as per the directions of the District Disaster Management Authority, is said to have revealed cracks and fissures in 34 nearby houses as well as upon the slab of a high level water tank of the Kerala Water Authority. The meetings of the District Disaster Management Authority presided by the Chair Person/District Collector, are said to be in progress in connection with the aforesaid complaints of property damage of the nearby residents, due to the illegal quarrying conducted by the petitioner. For the above reasons, the second respondent seeks a dismissal of the writ petition.
Heard the learned counsel for the petitioner and the learned Government Pleader representing the State of Kerala.
The learned counsel for the petitioner argued that the second respondent had been haunting the petitioner like anything to try whether the lawful quarrying activities conducted by the petitioner could be stalled one way or another. It is further pointed out that, on all such occasions, the effective intervention of this Court had frustrated the malicious designs of the second respondent. According to the learned counsel for the petitioner, Ext.P18 is the latest act of misuse of the relevant provisions of law by the second respondent. As per Ext.P18 communication, the second respondent directed the petitioner to stop all the mining operations for the reason that the site inspection conducted at the quarry of the petitioner revealed that the petitioner has not implemented the guidelines of SEIAA, while granting environmental clearance. It is stated thereunder that blasting mats were not being used at the quarry of the petitioner, and that the services of Mines Manager were not availed in that quarry. Another violation pointed out in Ext.P18 is that the construction of fencing around the quarrying area is not completed. In Ext.P18, it is also stated that, though the petitioner was called upon to appear for hearing at 11:00 a.m on 05.09.2026, he had conveyed his inconvenience, and hence the hearing was deferred to another day. However, the mining operations in the quarry of the petitioner were ordered to be stopped even before hearing the petitioner. As per Ext.P21 order, this Court directed the second respondent to withdraw Ext.P18 stop memo, taking note of the submission of the learned Government Pleader that two of the specific requirements of Ext.P18 were complied by the petitioner. However, it was made clear by this Court in the aforesaid order that the petitioner will have to address the objections made mention in the site inspection report, and ensure that the necessary acts in accordance with law, are done to avoid legal objections against the conduct of the quarry. In strict compliance with the directions in Ext.P21, the second respondent had withdrawn Ext.P18 stop memo vide Annexure-R2(a). The further developments which took place leading to the intervention of the District Disaster Management Authority, appear to be the reason why the petitioner could not conduct the quarrying operation.
Annexure-R2(b) would reveal that the second respondent had directed to stop the mining activities due to the orange alert declared at Palakkad District on 24.10.2026 and on 25.10.2026. However, the petitioner is alleged to have ignored the above direction, and transported 78 loads of granite building stone on 24.10.2026. The summary of stock released by the Department of Mining and Geology Directorate, Thiruvananthapuram (Annexure-R2(c)) is relied on by the second respondent to show that on 24.10.2026, the petitioner had obtained 78 transit passes for the transportation of granite building stones. In addition to the above violation, the petitioner is alleged to have flouted the transit pass conditions by carrying loads, in excess of the permitted limits, leading to the seizure of his vehicles by the police, and the initiation of penalty proceedings. A joint inspection conducted at the quarrying site of the petitioner by various agencies like the Kerala State Pollution Control Board, District Geologist, the Executive Engineer of Water Authority etc. is said to have unravelled further violations on the part of the petitioner in the conduct of quarry. In Annexure-R2(e), the Assistant Engineer of the Kerala State Pollution Control Board has enumerated various violations of the conditions imposed by the said Board. So also, the joint inspection is said to have revealed that the blasting operations at the quarry of the petitioner have been causing damage by way of cracks and fissures in the houses of 34 nearby dwellers. A water tank maintained by the Kerala Water Authority is said to have suffered crack as a result of the impact of the blasting operations in the quarry of the petitioner. To make matters worse, the petitioner was found to have indulged in blasting and removal of granite building stone from the buffer zone. Due to the aforesaid deleterious consequences of the quarrying operations, the local residents are said to have started agitations in front of the Panchayat Office and the District Office of the Department of Mining and Geology. It is in the backdrop of the above delicate situation that the District Disaster Management Authority is said to have intervened in the issue, which obviously resulted in the stay of operations in the quarry of the petitioner.
The learned counsel for the petitioner would contend that there is absolutely no justification for stalling the quarrying operations undertaken by him in strict compliance with the rules and regulations. According to the petitioner, he had already remitted the compounding fee and penalty for blasting and removing granite stone from the buffer zone, and hence the above violation cannot be a reason to interfere with his quarrying operations. As regards the allegation of cracks and fissures suffered by 34 houses of that locality and the water tank maintained by the Kerala Water Authority, the petitioner would contend that all those houses as well as the water tank are located far beyond the prohibited distance, and hence there was no justification in resorting to the stalling of operations of the petitioner’s quarry. The violations alleged to have been noted by the Pollution Control Board are said to be trivial and flimsy. The petitioner would also deny the allegation that he willfully violated the prohibitory orders pursuant to the declaration of orange alert. According to the petitioner, he had already removed 78 loads of granite building stone by the time when he received the alert from the second respondent.
In the aforesaid factual scenario of this case, the legal obligation of the second respondent to issue the necessary permits and transit pass upon fulfilment of the conditions of the relevant rules, has to be taken on a different pedestal from the legal obligation of the District Disaster Management Authority to interfere with the issue when it is shown that there is likelihood of a threatened disaster situation. In the case on hand, the second respondent is legally obliged to issue the requisite transit pass if it is shown that the petitioner had cured the drawbacks noted by the said respondent in Ext.P18 stop memo, and made all arrangements for the conduct of the quarry in strict compliance with the relevant rules and regulations. At the same time, if the District Disaster Management Authority headed by its Chairman/District Collector finds that the quarrying activities of the petitioner are liable to be interfered with to protect the larger interests of the society by taking adequate precautionary measures against disasters that might be caused due to natural calamities, the said Authority is empowered to issue appropriate directions in exercise of its powers under Sections 33 & 34 of the Disaster Management Act, 2005. All Departments including the Department which the second respondent represents, are bound to follow the aforesaid directions of the District Disaster Management Authority. When viewed in the above perspective, the reliefs sought for in this writ petition could be granted only subject to the aforesaid rider.
As a conclusion to the aforesaid discussion, I deem it appropriate to dispose of this writ petition as follows:
Subject to the directions of the District Disaster Management Authority, the second respondent shall issue transit pass/ movement permit to the petitioner in respect of the quarrying permit granted to him, if the petitioner has set right the drawbacks noted in Ext.P18 communication and complied with the terms and conditions of the relevant permits and licences for the conduct of quarrying.
In case of fulfilment of the requirements as stated above, the transit pass/movement permit shall be issued to the petitioner forthwith.
It is made clear that the right of the petitioner to conduct mining operations in his quarry will be subject to the lawful orders issued by the District Disaster Management Authority to protect the life and property of the nearby residents.