High CourtsSingle Bench(1999) 07 MAD CK 0106

Union of India vs R. Karthikai Rajan and 16 others

Madras High Court · Decided on 22 July 1999

HON’BLE JUDGES
P. Shanumugham, J
CASE NUMBER
Civil Revision Petition No. 559 of 1999 and C.M.P. No''s. 2815 and 2816 of 1999

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

151 paragraphs · 3,456 words

P. Shanumugham, J.—The Union of India, Atomic Energy Division, Hyderabad has filed this Civil Revision Petition under Article 227 of the

Constitution of India against the interim orders passed in I.A. No. 7 of 1999 in O.S. No. 2 of 1999 (I.A. No. 127 of 1999 in O.S.No32 of 1999),

by the Principal District Judge, Tuticorin. Brief facts are as follows: The Union of India had issued a notification u/s 4(1) of the Land Acquisition

Act (in short as ''the Act'') during the year 1989 for acquiring 1158 acres of land in Pazhayakayal village, Srivaikuntam Taluk, Thoothukudi District

for the purpose of setting up a new Zirconium and Titanium Sponge Plant. After due enquiry as contemplated under the Act, possession of the land

was handed over to the Union of India and thereafter various awards were passed, awarding compensation to the owners of the lands. From year

1990 or so, the Union of India was in possession of the property including the trees thereon. It is also stated that the Union of India have

commenced the work of setting up of a new plant and raising of a compound wall in and around the lands so acquired. While so, the respondents

numbering 15 filed O.S. No. 215 of 1998 on the file of the Principal District Munsif, Tuticorin for a permanent injunction, restraining the petitioner

herein from cutting and removing the trees standing in the plaint schedule property. The Interlocutory Application No. 1054 of 1998 taken out by

the respondents was dismissed on 8.1.1999. As against the said order made in the said Interlocutory Application, the respondents preferred a

C.MA.No3 of 1999 before the Principal District Court, Tuticorin on 11.1.1999 but no orders were made thereon.

2.

Without disclosing the earlier proceedings, the respondents have filed another suit, O.S. No. 2 of 1999 for an identical relief before the Sub-

Court, Tuticorin and since the concerned presiding officer of the Court below was on leave on 12.2.1999, the same was transferred and heard by

the District Judge, Tuticorin and the respondents obtained an order of temporary injunction, restraining the petitioners herein from interfering in any

manner as to the cutting and removal of the trees standing in the schedule mentioned properties. The present Civil Revision Petition is filed against

the order granted by the learned Principal District Judge, Tuticorin on the ground that the same has been obtained by the respondents herein by

abuse of process of Court and as against the mandatory requirement of Section 80(2) of the CPC and quite contrary to the procedure

contemplated under Order 39 Rule 3 of Code of Civil Procedure.

3.

Learned Additional Central Government Standing Counsel appearing for the petitioner contended that the orders made and plaint and

entertained by the Lower Court are liable to be struck off, since a clear fraud was committed by the respondents in obtaining such an order before

the Court below by suppressing the material facts before the Court below.

4.

Notice of motion was ordered and the respondents had entered appearance and the matter was heard at length both at the interlocutory stage

as well as at the main revision stage.

5.

The main question that arises for consideration in this revision is whether the plaint itself should be struck off on the ground of suppression of the

material facts by the respondents before the Court below?

6.

Learned counsel appearing for the respondents conceded the suppression of material facts in the earlier suit by the respondents before the Court

below, while obtaining interim orders. However, according to learned counsel for the respondents, the cause of action in the latest suit for totally

different from that of the earlier one and the relief in the earlier suit also differs from that of the relief in the later suit. He further submitted that in the

award enquiry, the officers concerned have clarified that the respondents have every right of cutting and removing the trees in the schedule

mentioned property. The respondents have fairly admitted their guilty of non-mentioning of the facts in the earlier suit before the Court below at the

time of obtaining - interim orders, but such non-mentioning of material facts before the Court below was not intentional. Further, according to the

respondents, it was only a mistake and they do not want to put the blame on anybody other than themselves.

7.

Learned Additional Central Government Standing Counsel appearing for the petitioner has contended that though the remedy of the Union of

India is not under the provisions of Article 227 of the Constitution of India and though the Union of India had every liberty to approach the Court

below for vacating the interim orders made against them, the Union of India has chosen to file this revision under Article 227 of the Constitution of

India on the simple ground that the respondents themselves have admitted that it is a clear case of abuse of process of Court, as they have

suppressed the material facts before the Court below while obtaining interim orders.

8.

I do not find any difference in the relief''s sought for in O.S. No. 2l5 of 1998 and in O.S. No. 2 of 1999. The prayers in both the suits are

identical in nature. Therefore, the respondents having failed in their attempt to obtain any interim order in the earlier suit appears to have moved the

learned Subordinate Judge initially and then the District Judge for obtaining interim orders. The non-mentioning of the material facts in the earlier

suit filed by them before the Court below at the time of filing the subsequent suit is nothing but intentional.

9.

Civil Miscellaneous Appeal No. 3 of 1999 was filed by respondents 1 to 15 on 11.1.1999 against the order of dismissal of Interlocutory

Application No. 1054 of 1999. The subsequent suit viz, O.S. No. 2 of 1999 was filed by respondents 1 to IS since there was no ex parte interim

order in the Civil Miscellaneous Appeal referred to above. The respondents have also thought of filing of a separate suit before the Sub-Court,

Tuticorin, which was subsequently transferred to the file of the District Judge, only for obtaining an interim order. The plea of learned Counsel for

respondents 1 to 15 is that the suppression of material facts by the respondents in the earlier suit before the Court below is only an omission and

there was absolutely no intention for the respondents for doing so and therefore it cannot be given much credence.

10.

Per Contra, according to learned Additional Central Government Standing Counsel appearing for the Union of India the suppression of

material facts by the respondents in the earlier suit before the Court below which went to the root of the interim order is very relevant and the Civil

Revision Petition is liable to be allowed.

11.

I have heard learned Additional Central Government Standing Counsel appearing for the petitioner and the learned Counsel appearing; for all

the respondents. I have also perused the materials available on record. I find there is absolutely no cause of action for obtaining an order of

permanent injunction by the respondents. The subsequent suit filed by the respondent is liable to be dismissed on the ground of suppression of

material facts by them with regard to the filing of the earlier suit before the Court below. The only averments made in the plaint in O.S. No. 215 of

1998 is that the plaintiffs are maintaining the trees and they are ripe for removal for being used as firewood and the plaintiffs are entitled to cut and

remove them for being sold. It is further stated that the plaintiffs have made an attempt to remove some of the odai trees on 7.9.1998 for being

used as firewood and the local village Administrative Officer has raised some objections, which necessitated the filing of the subsequent suit. But it

is not stated as to how the plaintiffs are maintaining the trees in respect of the lands with the trees which were acquired in the year 1990 and as to

how they are entitled to cut and remove those trees. The mandatory requirement as provided u/s 38 of the Specific Relief Act, 1963 for obtaining

an order of permanent injunction is not satisfied by the respondents herein. Section 38 of the Specific Relief Act contemplates the prevention of

breach of an obligation existing in favour of the plaintiffs. The term obligation includes every duty enforceable by laws. In this case there is no

obligation existing in favour of the plaintiffs and there is no duty that can be enforced against the petitioner herein. Consequently, the plaintiffs have

not proved their rights with regard to their enjoyment of the property in question and for seeking an order of permanent injunction.

12.

I have called for the papers relating to the suit O.S.No32/99 and the connected records. The respondents have filed I.A. No. 7/99 and the

learned District Judge, while granting an interim injunction,

The award produced and the learned counsel refers to page 16 of the award where trees are scheduled in valuation. Hence, interim injunction

against R-2 is granted till 25.2.99.

The award said to have been produced is a photocopy in reference to 119.79.0 hectares in Award No. 1/90-91 page 16 of the said award, which

the learned District Judge relied upon, is as follows:-

TREES: There are one withered palmyrah tree and one Margosa tree in S. No. 294. The scattered thorny plants and bushes of scattered growth

are in all lands. The owners are willing to remove trees and thorny plants and bushes.

Therefore, the order refers to S. No. 294 and refers to only two trees. From the records furnished by the learned Central Government Standing

Counsel, there were three notifications u/s 4(1). All these notifications were of the year 1989. There were four awards. Of these, three awards

were of the year 1990. Award No. 1/91-92 is dated 23.1.92. The respondents/plaintiffs claim to be the owners of the properties mentioned in the

scheduled below. They have a total extent of the land, but there are 100 items of survey numbers. But, S. No. 294, which is found in page 16

furnished by the respondent before the learned District Judge, is not found in the schedule of properties. Therefore, I am unable to comprehend as

to how S. No. 294, where there are two trees, was relied upon for the purpose of granting injunction in reference to 100 items of properties

referred in the plaint schedule. Therefore, there is a total non-application of mind. The learned Judge, without regard to the basic requirement, has

simply granted an injunction not to interfere with the right to cut and remove the trees..

13.

Another important aspect is that the respondents appear to have proceeded that there was no valuation of the trees. On the contrary,

according to the award papers furnished by the learned Central Government Standing Counsel in reference to Award No. 2/90-91, trees appear

to have been valued at pages 13, 19, 27, 35, 43, 47, 55, 61, and 67. The trees were valued separately and compensation awarded. Therefore,

there is no cause of action for the petitioners/defendants to object to the cutting and removing of the trees, since the property absolutely vests with

the petitioner Union of India and there is no scope for the Union of India to permit them to cut and remove the trees. Therefore, on the face of it,

the plaint averment cannot be accepted. Secondly, the interim order of the learned District Judge was passed in utter violation of Section 80(1)

C.P.C. No reason has been given and the learned District Judge did not take note the mandatory requirement for having failed to give notice to the

Union of India before filing the suit. After calling for the records considering the implications of the interim order passed, which is per se illegal, I

was informed that the learned Judge retired from service on 31.3.99.

14.

In the decision reported in Hindustan Photo Films Manufacturing Co. Ltd. v. R. Lakshmanan (1998(II) CTC 474), a learned single Judge of

this Court exercising powers under Article 226 of the Constitution of India struck off the suit on the ground that two different suits were filed on the

same set of facts based on same cause of action and the learned single Judge struck off the latter suit on the ground that the riling of the latter suit is

clear abuse of process of Court.

15.

In Ramiah Asari Vs. Smt. Kurshad Begaum and another, a learned single Judge of this Court has held that inherent powers are available to

struck off a plea which is made in abuse of process of Court.

16.

In the decision reported in S.P. Chengalvaraya Naidu (dead) by L.Rs. Vs. Jagannath (dead) by L.Rs. and others, , the Supreme Court has

held that fraud is an act of deliberate deception with the design of securing something by taking unfair advantage of another. It is a deception to

gain by another''s loss. It is cheating intended to get an advantage. In that case, the plaintiff purchased a property at Court auction and executed a

registered deed of release regarding the property in dispute. Without disclosing those facts the plaintiff filed a suit for partition of the property on

the ground that he has purchased the property on his own behalf. The non production and non-mentioning of the release deed at the trial stage

tantamount to playing fraud on the Court The Supreme Court has further observed that a litigant, who approached the Court is bound to produce

all the documents executed by him which are relevant to the litigation. If he withholds a vital document in order to gain advantage on the other side,

then he would be guilty of playing fraud on the Court as well as on the opposition party. In this case, the respondents as owners of the property

whose lands were acquired by the Union of India for setting up of a new Sinconium and Titanium Sponge plant, through various notifications have

received adequate compensation for the lands including the trees thereon. When that being so, they filed the suit, O.S. No. 215 of 1998 before the

Principal District Munsif Court, claiming that they are entitled to get the possession of trees standing in the plaint schedule properties and in an

Interlocutory Application filed by them they obtained an order of injunction restraining the Government from cutting and removing the trees worth

several lakhs of rupees standing in the plaint schedule properties. The respondents have suppressed the material facts before the Court at the time

of obtaining the orders. Therefore, in this Case they have committed fraud.

17.

In the case reported in Tiruchirapalli District Central Co-operative Bank Ltd., etc, and another v. hi. Krishnasami (1994 2 LW 266),

Srinivasan, J (as he then was) has held that it is true that in normal circumstances this court will not entertain any revision petition against an ad

interim ex parte order under which notice is also directed to the opposite party. But, in cases of gross injustice and patent violation of elementary

principles of law, this Court will not hesitate to interfere with such orders. This case is one of such nature. Before ordering interim injunction, the

Court below failed to see the rights of the petitioners vis-a-vis the rights of the respondents. The Court below ought to have seen the necessary

pleadings before granting such orders. The Court below has failed to see whether the requirements of Section 39 of the Specific Relief Act have

been complied with by the respondents and has also failed to visualise the consequence of the orders. Therefore there is a clear violation of

principles of natural justice, where the interference of this Court under Article 227 of the Constitution of India is necessary. In the case reported in

Rathinam and Others Vs. Pavathal, Venkataswami, J (as he then was) has held that it is true that the petitioners have remedies available under the

CPC and as they could not get justice speedily, they have filed the revision under extraneous situation. Order 39, Rule 3 of CPC directs the issue

of notice to the opposite party before granting injunction and in the event of grave urgency requiring grant of injunction without notice, the Court

shall record the reason explaining the object of granting the injunction. In this case, Section 18 notice also had been dispensed with. Learned Judge

in the order impugned has stated thus: ""The learned counsel for the respondents had submitted that the trees were agreed to be removed by the

respondents at the time of award and the award was also produced and the learned counsel shows page 16 of the award, where trees are

scheduled in valuation. Hence interim injunction against the second respondent is granted till 25.2.1979"". In my view, the said order was passed in

total non application of mind. There is no possibility of the respondents themselves agreeing to remove and cut the trees at the time of the award

and there was no award to that effect. Even according to the said order, the trees are scheduled in valuation. Therefore, as the trees were valued,

the respondents had only the right of compensation. In the above circumstances, the order granting interim injunction is clearly a non-speaking

order and in total violation of basic principle of law.

18.

In the case reported in Patasibai and Others Vs. Ratanlal, the Supreme Court has held that the trial should not proceed when there is no

controversial issue but the trial Court failed to perform its duty and proceeded to issue summons without carefully reading the plaint. Since the

plaint suffers from that fatal defect, the mere issuance of summons by the trial court did not require that the trial should proceed even when no

triable issue is shown to arise; permitting the continuance of such a suit is tantamount to licensing frivolous and vexatious litigation, which cannot be

done. The Supreme Court has I also held that it is not necessary to adopt the technical course of directing the trial Court to make the consequential

order of rejecting the plaint. The practical course of making that order in the proceedings itself to avoid any needless delay in conclusion of futile

litigation should be adopted. In this case, the course adopted by the Court is clear non-application of mind to the facts and as stated above, there

is no cause of action and no right, title or interest accrued to the respondents for getting the relief. That apart, they have suppressed material facts

before the Court of law. In that'' view of the matter, I am of the opinion that the plaint itself suffers from fatal defect, and it has to be struck off to

avoid any needless delay in conclusion of the futile litigation between the parties.

19.

The decision reported in Sudarsan Swain and Others Vs. Jagannath Routh and Others, , referred to and relied on by learned counsel for the

respondents has no relevance. In that case the learned Judge of Orissa High Court held that dismissal for default under Order 9, Rule 8 of prior

suit based on defective title deed will not bar under Order 9, Rule 9 if a subsequent suit for title and partition is based on rectified title deed, as the

subsequent suit is not based on the same cause of action, Learned Counsel for the respondents also referred to the decision of the Supreme Court

in Sidramappa Vs. Rajashetty and Others, , wherein it was held that where the cause of action on the basis of which the previous suit was brought

does not form the foundation of the subsequent suit and in the earlier suit the plaintiff could not have claimed the relief which he sought in the

subsequent suit. That judgment also will not apply to the facts of this case. In the instant case, the relief claimed by the respondents before the

Court below are identical and the case of action is also one and the same. Therefore, there is clear abuse of process of Court in the present case

by the respondents.

20.

Therefore for all the foregoing reasons, the interim ex parte order granted by the Court below is set aside. The suit filed by the respondents

viz., O.S. No. 2 of 1999, on the file of the Principal District Court, Tuticorin is liable to be dismissed and accordingly, it is dismissed.

21.

Revision Petition is allowed with exemplary costs of Rs. 25,000/- (Rupees twenty five thousand only). The order passed by this Court in

C.M.P. No. 2815 of 1999 is made absolute.