High CourtsSingle Bench(2010) 03 MAD CK 0092

The Superintending Engineer Madurai Electrical Undertaking Acquisition Circle Tamil Nadu Electricity Board vs M. Kumar, The Deputy Commissioner of Labour (Appellate Authority under Tamil Nadu Payment of Subsistence Allowance Act) and The Assistant Commissioner of Labour (Authority under Tamil Nadu Payment of Subsistence Allowance Act)

Madras High Court · Decided on 30 March 2010

HON’BLE JUDGES
K. Chandru, J
RESULT
Dismissed
CASE NUMBER
Writ Petition No. 23428 of 2001

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

74 paragraphs · 1,536 words

K. Chandru, J.—The Superintending Engineer, Madurai Electrical Undertaking Acquisition Circle, Tamil Nadu Electricity Board, Madurai is

the writ petitioner. The writ petition is filed against the order passed by the second respondent/Appellate Authority under the Tamil Nadu Payment

of Subsistence Allowance Act (for brevity ""Act 43 of 1981"") dated 18.4.2000 made in P.S.A. No. 2 of 1999, confirming the order of the third

respondent/Authority under Act 43 of 1981, dated 28.6.1999 in P.S.A. No. 40 of 1998.

2.

The writ petition was admitted on 29.11.2001 and pending the writ petition, this Court granted interim stay. Subsequently, the interim stay was

modified on 23.9.2003, directing the petitioner/Board to deposit a sum of Rs.45,000/- to the credit of P.S.A. No. 2 of 1999 on the file of the

second respondent, failing which it was indicated that the stay will stand vacated automatically. The counsel for the petitioner is unable to state

whether the amount has been deposited or not.

3.

The facts leading to the case are as follows: The first respondent was employed as Inspector of Assessment in the office of the Assistant

Engineer, Thallakulam. He was placed under suspension with effect from 14.10.1996 on certain alleged misconduct. The suspension came to be

made on the basis of Certified Standing Orders applicable to the workmen. Since the first respondent was not paid subsistence allowance, he filed

an application before the third respondent authority under the provisions of Act, 43 of 1981 claiming subsistence allowance from 14.10.1996 till

the date of the application, namely nearly for a period of 21 months, and it worked out to Rs. 1,22,577/-.

4.

The third respondent took up the case as P.S.A. No. 40 of 1998 and ordered notice to the petitioner and the petitioner filed a counter

statement dated Nil-November, 1998. In the counter statement, it was stated that the Board has got its own Standing Orders for the workers and

amounts are paid only in terms of the Standing Orders. In the Service Regulation applicable to the workmen, it was stated that the person should

be staying in the headquarters and if he goes out of the said headquarters, he should seek prior permission from the Executive Engineer. The first

respondent went out of the headquarters without permission and therefore, he was not paid subsistence allowance.

5.

Before the third respondent, the first respondent/workman examined himself as W.W.1 and marked four documents. On the side of the

petitioner/Board, two witnesses - M/s. Kalyanaraman and Dharmarajan were examined as M.W.1 and M.W.2 respectively and five documents

were filed.

6.1. The third respondent held that the first respondent was paid subsistence allowance from August, 1998 to November, 1998 and the

suspension was made in terms of Order 20(2)(a) of the Standing Orders, which was marked as Ex.M4. For the period from 10.12.1997 to

31.12.1997, namely 21 days, also he was paid subsistence allowance.

6.2. The contention that the first respondent was not a workman was rejected on the ground that he was covered by the Certified Standing Orders

and once a person is covered by the Standing Orders ipso facto, he is also covered by Act 43 of 1981.

6.3. With regard to the second contention of the Board that under Order 20(2)(u) of the Standing Orders, subsistence allowance will be paid only

if the workman has not taken up employment elsewhere, it was held that there is no other condition that the worker should produce a certificate

that he is not employed elsewhere and therefore, this argument was also rejected.

6.4. The third contention that the workman did not demand subsistence allowance was also rejected, because under the provisions of Section 3(4)

of Act 43 of 1981, there is no requirement that the workman should seek for such subsistence allowance and it is an automatic right of the worker.

6.5. The last argument was that as per Regulation 56(2) of the Service Regulations an employee is entitled to subsistence allowance only if he

furnishes a certificate that he was not engaged in any other employment, business, profession or vocation. With reference to the objection raised in

this regard as well as the requirement under Regulation 56(4) of the Service Regulations regarding condition of residing within the headquarters, the

third respondent held that when a contention of this nature is raised, it is for the Board to prove that the workman was employed elsewhere and in

the absence of the Board raising such a contention and proving to the satisfaction of the authority, the question of disqualification does not arise.

Thereafter, the authority, finding that the quantum of subsistence allowance was not disputed, computed the amount as Rs.95,032/- by the order

dated 28.6.1999.

7.

Subsequent to the order, the first respondent was dismissed form service on 13.1.2000. Thereafter, the petitioner preferred an appeal under

Rule 5A of the Tamil Nadu Payment of Subsistence Allowance Rules before the second respondent. The second respondent took up the case as

P.S.A. No. 2 of 1999 and issued notice to the first respondent. After hearing the argument for both sides, he came to the conclusion that as per

Section 3(4) of Act 43 of 1981, the employer has to pay subsistence allowance on the date or dates on which it was due to the employee and

there was no requirement that the workman should seek for subsistence allowance. Since the condition precedent for filing appeal, namely the

deposit was also not made, on the grounds of violation of the conditions of appeal as well as lack of merits, the appeal was dismissed. It is as

against both these orders, the present writ petition has been filed as noted already.

8.

The learned Counsel for the petitioner contended that Regulation 56(2) of the Service Regulations is statutory, inasmuch as it was framed u/s

79(c) and (k) of the Electricity (Supply) Act, 1948 and therefore, it is applicable to all the employees of the Board. But while making such an

argument, the learned Counsel overlooked Regulation 112 of the Service Regulations, in which it is stated as follows:

112.

In respect of matters in these Regulations for which there is provision also in the Standing Orders for the employees of the Board framed

under the Industrial Employment (Standing Orders) Act, 1946, the provisions in the Standing Orders shall prevail in regard to the employees

governed by the Standing Orders.

9.

In any event, it is well settled that for the employees covered by the Certified Standing Orders no other regulations can be read into, as held by

the Supreme Court in Western India Match Company Ltd. Vs. Workmen, . Even otherwise, the similar contention raised by the very same

petitioner came to be considered by the Division bench of this Court in Tamil Nadu Electricity Board Vs. Central Organisation of Tamil Nadu

Electricity Employees and Another, . Therefore, the argument must fail.

10.

The second argument that in the absence of the workman producing a certificate as required under the Service Regulations he is not entitled to

subsistence allowance, even assuming this is accepted, that by itself will not prove that the workman was employed elsewhere and therefore, he

suffers a disqualification u/s 3(2) of Act, 43 of 1981. On the other hand, u/s 3(2) of Act 43 of 1981, it is provided as follows:

Section 3. Payment of subsistence allowance:

(1) ...

(2) An employee shall not be entitled to receive any subsistence allowance if he accepts any other employment during the period of his suspension

in any establishment other than the establishment where he had been working immediately before his suspension.

Therefore, when a workman claims subsistence allowance before the authority and when the employer wants to deny subsistence allowance, he

has to make appropriate pleadings and for the purpose of setting the defence as provided u/s 3(2) of Act 43 of 1981, it is for the employer to

prove to the satisfaction of the authorities that the workman is employed in any other place prohibited by the Act and therefore, the question of

payment of subsistence allowance will not arise.

11.

Under such circumstances, the question of gainful employment and the burden of proving the said fact came to be considered by the Supreme

Court in Novartis India Ltd. Vs. State of West Bengal and Others, . After referring to Section 106 of the Indian Evidence Act, the Supreme Court

observed that unless the employer makes a specific pleading about the gainful employment, the question of shifting the burden to the workman will

not arise. In the case on hand, except relying upon Regulation 56(2) of the Service Regulations, which in any event does not apply to the case of

the workman, the Board not discharged its obligation in setting the defence as provided u/s 3(2) of Act 43 of 1981.

In the light of the above, the writ petition is misconceived and accordingly, the same is dismissed. In view of the dismissal, the first respondent is

entitled to withdraw the amount lying in deposit with the second respondent pursuant to the orders of this Court, in case such deposits have been

made. If no such deposit is made, the first respondent is entitled to take appropriate steps to recover the amount from the Board.