High CourtsSingle Bench(2026) 11 BOM CK 2141

The Nehru Nagar Amrapali Coop. Housing Society Limited vs Rebuild & Anr.

Bombay High Court · Decided on 3 November 2026

HON’BLE JUDGES
Amit Borkar, J
RESULT
Disposed Of
CASE NUMBER
COMM ARBITRATION PETITION (L) NO.35787 OF 2026
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

130 paragraphs · 10,885 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

By the present Petition filed under Section 9 of the Arbitration and Conciliation Act, 1996, the Petitioner is seeking directions to direct the Respondents to hand over the original redevelopment documents with respect to the Society’s property, to restrain the Respondents from representing themselves as Developers of the siad Society property, and for other ancillary reliefs as prayed for.

2.

I have heard the learned Advocates appearing for the Petitioner and Respondent No. 2. The dispute has arisen from the Development Agreement dated 13 December 2007, Supplemental Development Agreement dated 5 May 2012 and Deed of Assignment dated 9 November 2015. According to the Petitioner Society, the Respondents failed to complete the redevelopment and did not perform the responsibilities accepted by them under these documents. The Society says that it has terminated the development rights and the Respondents have no right to continue as Developers. It complains that, even after termination, the Respondents have not returned the original redevelopment documents and are preventing the Society from appointing another Developer. Respondent No. 2 has disputed the Society's case. According to it, the earlier termination was later given up by both sides. It is submitted that the Society continued to write letters requesting Respondent No. 2 to complete the remaining work. The Society had agreed to give a necessary Power of Attorney. Therefore, according to Respondent No. 2, the Development Agreement and Deed of Assignment continue to bind the parties. It is stated that the work could not be completed because the Society did not give the required cooperation. The first question is how far this Court should examine the dispute while deciding a Petition under Section 9 of the Arbitration and Conciliation Act, 1996. At this stage, the Court is not required to conduct a full trial. It is not required to finally decide whether the termination of the Development Agreement was legal or not. These questions will be decided by the Arbitral Tribunal after considering the agreements, documents, evidence and submissions of both sides. However, merely because the parties have agreed to resolve their disputes through arbitration, this Court cannot refuse interim protection where it is necessary. The Court has to consider whether the Petitioner has shown a prima facie case, whether the balance of convenience is in its favour and whether protection is required to preserve the subject matter of arbitration. The Court must consider what may happen to the Society and its members if the requested relief is refused. In Kannamwar Nagar Aditya Cooperative Housing Society Limited v. Shraddha Platinum Builders and Developers and Others, Commercial Arbitration Petition (L) No. 8692 of 2026 with Commercial Arbitration Petition (L) No. 23499 of 2026, decided on 17 July 2026, this Court considered a similar dispute between a Society and its Developer. In paragraph 19, this Court observed that the question whether termination was legal would be decided by the Arbitral Tribunal. In a Petition under Section 9, the Court has to consider whether interim protection is required to preserve the subject matter of arbitration. In paragraph 31 of that judgment, this Court observed that questions regarding the procedure followed for termination, opportunity given to the Developer and seriousness of the breaches would require detailed examination of the agreements and evidence. Such questions cannot be finally decided in a Petition under Section 9. The same approach will have to be followed here. However, merely because the Respondents dispute the termination, the redevelopment cannot be allowed to remain stopped for an unlimited period. I shall examine the rival submissions on the basis of the documents available. The findings recorded here are only for deciding the interim relief. They will not finally decide the contrrights and liabilities of the parties.

Nature of the Development Agreement and obligations of the Respondents:

3.

There is no dispute that the Petitioner Society executed a Development Agreement dated 13 December 2007 in favour of Respondent No. 1, M/s. Rebuild. Under this Agreement, Respondent No. 1 was required to redevelop Building No. 133 at Nehru Nagar, Kurla (East), Mumbai. At that time, the Society had 40 members. The old building consisted of a ground floor and four upper floors. Under the original Development Agreement, Respondent No. 1 had agreed to provide permanent alternate accommodation to the Society members. The agreed carpet area was 323 sq. ft., along with the permitted niche and flower bed area. Respondent No. 1 was required to provide transit accommodation and monthly compensation during the redevelopment work. The proposed building was to consist of a ground floor and seven upper floors. Thereafter, the permissible FSI increased from 2.4 to 2.5. Because of this increase, the parties executed the Supplemental Development Agreement dated 5 May 2012. Under this Agreement, the carpet area of each member was increased to 348 sq. ft. Respondent No. 1 accepted monetary responsibilities towards the members and was permitted to construct the eighth floor. It is clear that the original terms were later changed through the Supplemental Agreement. The development potential of the property had increased. Since permission for an additional floor was given, responsibilities arose for its construction and for obtaining the necessary permissions from the concerned authorities.

4.

Respondent No. 1 could not complete the redevelopment work. Thereafter, the Deed of Assignment dated 9 November 2015 was executed between Respondent No. 1, Respondent No. 2 and the Petitioner Society as the confirming party. Neither side disputes execution of the Deed of Assignment. Both sides rely upon this document in support of their respective cases. The important question is what responsibilities Respondent No. 2 accepted under this Deed.

5.

On reading the Deed of Assignment, it appears that Respondent No. 1 was facing financial difficulties and was unable to complete the remaining construction. Respondent No. 2 agreed to provide financial assistance and use its experience for completing the balance work. The incomplete work was described in the Deed as the “Pending Construction Work”. The Deed records that Respondent No. 1 had partly completed the building consisting of ground plus seven floors and that Respondent No. 2 had agreed to complete the remaining work. It was agreed that the Deed of Assignment would be read along with the earlier Development Agreement and Supplemental Agreement. All parties were required to follow the conditions contained in these documents. Therefore, Respondent No. 2 cannot now say that it had no responsibility for the earlier obligations of Respondent No. 1. After accepting the assignment, Respondent No. 2 agreed to complete the pending construction and clear the liabilities accepted by it under the Deed. It accepted the rights arising from the development arrangement, including the right to receive the balance consideration from the new flat purchasers. The Deed provided that Respondent No. 2 would clear the liabilities arising from the development arrangement without creating any encumbrance or lien over the property of the Society or its members. Respondent No. 2 was permitted to obtain financial assistance from banks or other financial institutions at its own risk and cost. The Deed made Respondent No. 2 responsible for completing the pending construction and obtaining the Occupation Certificate from MCGM at its own cost. It was provided that construction of the eighth floor would not begin until the necessary payments were made for obtaining the Commencement Certificate and clearing the dues of the concerned authorities. The Deed showed that timely completion of the pending work was important.

6.

Another important condition is contained in Clause (g). Under this clause, the Society agreed to cooperate in redevelopment of Building No. 132, which is next to Building No. 133. However, this cooperation was subject to the condition that the area in possession of the Society would not be changed or reduced. The entrances, exits and parking arrangements of both buildings were required to remain separate. This condition is important because the later dispute between the parties is about the compound wall and boundary between Building Nos. 132 and 133. Merely because Respondent No. 2 was appointed as Developer of the adjoining building, it cannot claim any additional right over the Society's property. The Deed protects the Society's area and requires that its separate facilities should be maintained.

7.

I find that the contention of Respondent No. 2 that the Society was required to pay the balance corpus amount of Rs.60 lakhs is not supported by the Deed of Assignment. Clause (f) records that Respondent No. 2 had agreed to pay Rs.60 lakhs to the Society on the date of execution of the Deed. There is a receipt dated 2 November 2015 showing that the Society received this amount. Therefore, on the material available, the responsibility to pay this amount was upon Respondent No. 2 and not the Society. This submission of Respondent No. 2 cannot be accepted.

8.

The Respondents have relied upon the Deed of Assignment to say that the Society was required to cooperate in obtaining permissions and completing the construction. This submission requires consideration. The Society cannot deny that the Deed expected it to give cooperation wherever necessary. However, the kind of cooperation required and the extent of the Society's responsibility will have to be understood by reading the entire Deed. In relation to Building No. 132, the Society's responsibility was subject to the condition that its own property area would not be reduced. Therefore, the Deed of Assignment shows that Respondent No. 2 was responsible for completing the remaining construction, obtaining the Occupation Certificate, clearing the project liabilities and protecting the Society against claims made by the new flat purchasers. These responsibilities are important while examining the conduct of Respondent No. 2.

Construction carried out and remaining work:

9.

The Society alleges that the Respondents failed to complete the construction, did not construct the eighth floor, did not obtain the Occupation Certificate and did not follow the requirements of the concerned authorities. It has alleged poor construction quality and damage to the property. Respondent No. 2 has denied these allegations. According to it, Respondent No. 1 had constructed the building consisting of ground plus seven upper floors sometime in or around 2014. The 40 members of the Society had taken possession of their rehabilitation flats and were staying there. Therefore, according to Respondent No. 2, only the eighth floor and certain other remaining work were incomplete.

10.

The statements of both sides regarding the extent of construction will have to be considered along with the earlier proceedings before MahaRERA and this Court. Five flat purchasers had approached MahaRERA complaining that possession of their flats had not been given. By order dated 15 January 2018, the Chairperson of MahaRERA held that the purchasers were entitled to receive possession before 31 December 2018, which was the date mentioned in the project registration. The Appellate Bench of MahaRERA, by order dated 29 August 2018, directed payment of interest at 10.05% per annum from 1 January 2018 until possession was given after obtaining the Completion Certificate.

11.

Respondent No. 2 challenged that order before this Court by filing Second Appeal (St.) Nos. 27914 of 2018 and connected appeals. By judgment dated 29 August 2019, pronounced on 17 September 2019, the appeals were dismissed by the learned Single Judge.

12.

In the observations made in that judgment in paragraph 37, this Court recorded that Respondent No. 1 had constructed the building consisting of ground plus seven upper floors and had given possession of the rehabilitation flats to the Society members without obtaining the Occupation Certificate. In paragraph 38, the Court recorded that construction of the flats proposed on the eighth floor had not even started. The said judgment recorded that Respondent No. 1 had sold nine out of the ten flats proposed to be constructed on the eighth floor. The names of the purchasers were included in the list attached to the Deed of Assignment. The Court held that Respondent No. 2 had accepted the liabilities arising from the earlier development arrangement towards those purchasers. In paragraph 42, this Court held that Respondent No. 2 had accepted the rights and liabilities created by Respondent No. 1, including the rights of the new flat purchasers. In paragraph 48, the Court made it clear that Respondent No. 2 could not avoid its statutory responsibilities towards the purchasers merely by issuing a termination letter. The Court observed:

“The appellant cannot be allowed to wriggle out of such pending obligations under the guise of termination of agreements entered into with the erstwhile promoter which are assigned in favour of the appellant herein.”

13.

In paragraph 55, this Court noticed that Respondent No. 2 had not produced any material to show what steps it had taken against MCGM or MHADA because the necessary Commencement Certificate was not granted. This observation is important while considering the present defence of Respondent No. 2 that the Society's non-cooperation prevented it from obtaining the necessary permissions.

14.

I am aware that the Society was not a party to the above Second Appeal proceedings. Therefore, that judgment cannot be treated as a final decision on the dispute between the Society and Respondent No. 2 regarding termination of the Development Agreement. However, the judgment is relevant for understanding how much construction was completed, what rights of third-party purchasers had been created and what liabilities Respondent No. 2 had accepted under the Deed of Assignment. It is clear that the building was not left without any construction. The rehabilitation portion consisting of ground plus seven floors had been constructed and possession was given to the Society members. At the same time, the eighth floor was not completed, the Occupation Certificate was not obtained and the rights of the flat purchasers still required protection.

15.

The present case cannot be treated as a case where the Developer did not carry out any construction at all. However, the Respondents cannot say that redevelopment was completed merely because possession of the rehabilitation flats was given to the members. Completion of the remaining work and obtaining the Occupation Certificate were important responsibilities accepted by Respondent No. 2 under the Deed of Assignment.

16.

The Society alleges that the building is in a dilapidated and unsafe condition. Respondent No. 2 denies this. The Society has referred to damage to the building and collapse of a slab. However, there is no independent structural audit report before this Court which establishes the condition of the building. I am not recording any final finding about whether the building is structurally safe or unsafe. However, the fact that the Occupation Certificate has not been obtained and the remaining work has not been completed is supported by the material placed before this Court.

17.

Merely because the members were given possession of their rehabilitation flats, their right to have the building completed according to the sanctioned plans and to obtain the Occupation Certificate does not come to an end. Respondent No. 2 had accepted this responsibility under the Deed of Assignment. The judgment of this Court dated 17 September 2019 makes it clear that Respondent No. 2 cannot avoid its statutory responsibilities towards the flat purchasers by relying upon termination of the Deed of Assignment. The rights of those purchasers will have to be protected, whatever may be the dispute between the Society and the Respondents regarding continuation of the development rights.

Termination of the development arrangement:

18.

The next question is whether the development arrangement was terminated and whether the parties later restored it by their conduct. The Petitioner relies upon its notice dated 7 July 2017. Through this notice, the Society terminated the Development Agreement, Supplemental Agreement and Deed of Assignment. The reasons given were delay in construction, failure to construct the eighth floor, failure to provide the collapsible gate, defects in the RCC structure, poor construction quality, deviation from sanctioned plans and non-payment of statutory dues. Even before this, the Society had terminated the Power of Attorney dated 13 December 2007 through its Advocate's letter dated 19 April 2017. The Society had stated that the Respondents were not financially capable of completing the project. Therefore, the notice dated 7 July 2017 was not the first occasion on which the Society raised its complaints. It had earlier called upon the Respondents to complete the remaining work and thereafter took steps to terminate the Power of Attorney.

19.

Respondent No. 2 says that it replied to the termination notice dated 7 July 2017 by its letter dated 3 August 2017. According to it, the allegations made by the Society were denied and it was explained that the Society was not giving cooperation for completing the remaining work. Respondent No. 2 says that the Society did not send any reply to its letter dated 3 August 2017. On this basis, it is argued that the Society had given up its earlier termination.

20.

The reply dated 3 August 2017 is an important document and cannot be ignored. Respondent No. 2 had raised the defence that the Society was not cooperating. However, merely because the Society did not send another reply, it cannot be said that the Society withdrew its termination notice. Whether the Society accepted the explanation of Respondent No. 2 or whether the parties later restored the development arrangement will have to be decided by considering all the later documents and the conduct of both sides. In this connection, the letter dated 1 February 2019 addressed by Respondent No. 2 to the Society is very important. Respondent No. 2, through its Advocates, first stated that the Society had not replied to its earlier letter dated 3 August 2017. It claimed that the Society had accepted its stand and was to be treated as having withdrawn the earlier termination. The letter stated:

“Thus, by its conduct your Society has accepted our Client's contention and deemed to have withdrawn the purported termination.”

21.

However, the letter did not end there. Respondent No. 2 thereafter stated that it had no other option but to terminate the Development Agreement, Power of Attorney and Deed of Assignment. Paragraph 5 of the letter stated:

“the said Documents stand terminated w.e.f. the date of this letter and our Client stands absolved of all their liabilities/responsibilities towards your Society in the matter of development of your Society's plot.”

22.

Thus, the letter dated 1 February 2019 contains two different statements. In the first part, Respondent No. 2 claimed that the Society had withdrawn its earlier termination. In the later part, Respondent No. 2 declared that the Agreements stood terminated from that date and that it was free from its responsibilities towards the Society. Both statements must be read together. Respondent No. 2 cannot rely only upon the first part and ignore the later part. The letter shows that Respondent No. 2 decided to bring the development arrangement to an end with effect from 1 February 2019. It records its intention to recover Rs.91,08,142/-, which it claimed to have spent on the project. It claimed a paramount charge over the remaining development potential of the Society's property. I find that the present submission of Respondent No. 2 that its letter dated 1 February 2019 was only a conditional acceptance of the Society's termination is not supported by the words used in that letter. Respondent No. 2 stated that the development documents stood terminated with effect from that date.

23.

There is another important document supporting this view. On 8 March 2020, Respondent No. 2 addressed a letter to MahaRERA regarding completion of the registered real estate project. In that letter, Respondent No. 2 stated that the Society had terminated the Development Agreement and Deed of Assignment. It stated that the Society was still firm on its decision and that there was no possibility of obtaining permission for restarting and completing the remaining work. The relevant part reads:

“However, since the Society is still firm on its decision, we see no possibility of getting permission to start and complete the balance work of registered project.”

24.

Respondent No. 2 thereafter stated:

“Therefore, now, we have decided to terminate the project on ‘as is where is basis’ and requested MahaRERA to accept the Completion Certificate issued by the Project Architect.”

25.

This letter dated 8 March 2020 was written by Respondent No. 2 to a statutory authority. It was not a statement made by the Society against Respondent No. 2. Respondent No. 2 informed MahaRERA that the Society had terminated the development arrangement, that the Society continued to insist upon its decision and that there was no possibility of restarting the remaining work. It stated that it had decided to terminate the project on an “as is where is” basis.

26.

This conduct of Respondent No. 2 is important. If Respondent No. 2 was always ready and willing to complete the redevelopment under the Deed of Assignment, there was no reason for it to inform MahaRERA that restarting the work was not possible and that it had decided to terminate the project on an “as is where is” basis.

27.

The letter dated 8 March 2020 does not support the argument that the Society had mutually withdrawn its termination notice dated 7 July 2017. On the contrary, Respondent No. 2 informed MahaRERA that the Society continued to insist upon termination. This is different from the present stand of Respondent No. 2 that the Society had accepted its reply dated 3 August 2017 and withdrawn its earlier termination.

28.

I am unable to accept the submission that the original termination was given up immediately after the reply dated 3 August 2017. The documents of February 2019 and March 2020 show that both sides had taken steps and made statements treating the development arrangement as having come to an end. They show that the project was not being continued in the normal manner under the Deed of Assignment. At the same time, I am not recording any final finding that the Society's termination dated 7 July 2017 was valid or that Respondent No. 2 was justified in issuing its own termination letter dated 1 February 2019. The effect of these letters, the rights arising from them and the question whether either termination was effective will have to be decided by the Arbitral Tribunal. However, Respondent No. 2 cannot ignore its own communications of 2019 and 2020 while now claiming that the Deed of Assignment continuously remained in force.

Effect of subsequent correspondence and order dated 4 July 2022:

29.

Respondent No. 2 has placed considerable reliance upon the correspondence exchanged after 2022. According to it, both parties continued to act under the Deed of Assignment. It is submitted that the Society requested Respondent No. 2 to complete the remaining construction, called upon it to construct a new compound wall and assured it that a fresh Power of Attorney would be executed. Therefore, according to Respondent No. 2, both parties later gave up the earlier termination.

30.

The Petitioner has filed an Additional Affidavit and has disputed this meaning given to the correspondence. According to the Petitioner, the later letters were exchanged only for complying with the order dated 4 July 2022 passed by this Court in Writ Petition (L) Nos. 10078 of 2021, 16955 of 2021 and 3335 of 2021. The Society states that the correspondence was mainly regarding the compound wall and demarcation of the boundary between Building Nos. 132 and 133. The Petitioner has stated:

“co-operation does not mean giving up or waiving of termination nor it implies that the correspondences are on the basis that the assignment is valid, binding and subsisting.”

31.

The order dated 4 July 2022 passed by this Court will have to be considered in this background. In those proceedings, the dispute regarding the wall between Building Nos. 132 and 133 was before the Court. The Court recorded that the width of the Development Plan road had changed because of the revised layout. It was observed that the wall between the two buildings was creating a deadlock and the matter was not moving forward.

32.

The learned Advocate appearing for the occupant of Building No. 133 submitted that the Developer had not obtained the Occupation Certificate and that steps would be taken to obtain it if the wall was removed. The Court accepted this statement. The learned Advocate appearing for the Planning Authority submitted that the Developer would remove the wall at its own cost. The learned Counsel appearing for the Developer agreed to do so.

33.

The Court thereafter directed:

“The parties should cooperate with each other for obtaining the Occupancy Certificate.”

34.

On reading the entire order, it is clear that those proceedings mainly concerned removal of the compound wall and taking steps for obtaining the Occupation Certificate. The order does not declare that the Development Agreement or Deed of Assignment was restored or brought back into force. It does not record that the Society had withdrawn its termination notice dated 7 July 2017 or agreed to restore the development rights of Respondent No. 2. The Court directed the parties to cooperate with each other for a particular purpose. Respondent No. 2 had agreed before the Court to remove the compound wall at its own cost and take steps for obtaining the Occupation Certificate. Therefore, merely because the parties complied with this order, it cannot be said that the entire development arrangement was restored.

35.

The letter dated 21 July 2022 addressed by the Petitioner's Advocate to Respondent No. 2 must be understood in this background. Through this letter, the Society called upon Respondent No. 2 to construct a new boundary wall according to the revised demarcation. It asked Respondent No. 2 to give a time schedule for obtaining the Occupation Certificate. Since this letter was sent soon after the order dated 4 July 2022, it can be understood as an effort by the Society to ensure compliance with the directions issued by this Court.

36.

I have considered the letter dated 4 July 2023 addressed by Respondent No. 2 to the Society. The subject of the letter was “Completion of Pending Work of Your Bldg No. 133 ... and obtaining Occupation Certificate”. Respondent No. 2 referred to the Deed of Assignment dated 9 November 2015 and the order dated 4 July 2022. It requested the Society to give a letter on its letterhead to MHADA for carrying out demarcation of Building No. 133. It stated that Respondent No. 2 would pay the charges required for such demarcation. Its subject refers to completion of the pending work and obtaining the Occupation Certificate. It shows that Respondent No. 2 was still trying to take certain steps concerning the Society's building. It shows that Respondent No. 2 was asking the Society to cooperate for obtaining demarcation from MHADA. However, on reading the contents, the main request appears to be for giving a letter for the limited purpose of carrying out demarcation.

37.

Respondent No. 2 has relied upon the Society's letter dated 23.03.2026, other correspondence and the communication dated 11.11.2025. According to Respondent No. 2, these letters show that the Society continued to recognise it as the Developer. It is argued that the Society had agreed to execute a Power of Attorney after construction of the boundary wall. The later correspondence shows that the parties did not stop communicating after the order dated 4 July 2022. Some discussions continued regarding the compound wall, demarcation, Occupation Certificate and completion of the remaining work. This correspondence may be important while deciding whether the Society later gave up its earlier termination or whether both sides agreed to continue with some responsibilities under the Deed of Assignment. However, merely because the parties continued to exchange letters, it cannot be treated as proof that all the development rights which were earlier terminated had been restored. There must be clear material showing that both sides intended to restore the entire development arrangement and permit Respondent No. 2 to continue as Developer with all the rights under the earlier agreements.

38.

The clause in the Deed of Assignment stating that the earlier two agreements would continue until they were substituted, cancelled or revoked in writing is important. Both sides may rely upon this clause before the Arbitral Tribunal while explaining the effect of the termination notices and their later conduct. Whether the correspondence after 2022 was sufficient to restore the entire development arrangement will require reading all the agreements and letters together. At this stage, I am unable to accept the argument of Respondent No. 2 that the order dated 4 July 2022 restored its development rights. The order did not decide that question. Similarly, the Society's cooperation in removing the wall and carrying out demarcation cannot, without anything more, be treated as unconditional withdrawal of its earlier termination.

39.

I find that the allegation that MHADA had directed joint redevelopment of Building Nos. 132 and 133 is not established by the order dated 4 July 2022. That order refers to the changed layout and removal of the wall. It does not direct that both buildings should be redeveloped jointly. The Deed of Assignment provides that the Society's area shall not be reduced and that the entrance, exit and parking arrangements of both buildings shall remain separate. Respondent No. 2 may rely upon the correspondence regarding demarcation and cooperation to support its case. However, it cannot claim an independent right to reduce the Society's property area or insist upon joint redevelopment merely because it is developing Building No. 132.

Allegation of non-cooperation by the Society and Power of Attorney:

40.

Respondent No. 2 has strongly relied upon the fact that the Society did not execute a fresh Power of Attorney in its favour. According to Respondent No. 2, without such Power of Attorney and a letter on the Society's letterhead, it was not possible to submit plans for construction of the eighth floor or take steps before MHADA and MCGM.

41.

This submission requires consideration. Under the original Development Agreement, the Society had agreed to execute a General Power of Attorney in favour of the Developers or their nominees for carrying out the redevelopment. Accordingly, a Power of Attorney dated 13 December 2007 was executed in favour of the partners of Respondent No. 1. The Society later terminated this Power of Attorney by its letter dated 19 April 2017.

42.

Respondent No. 2 contends that after taking over the rights and liabilities under the Deed of Assignment, it was entitled to receive the necessary authority from the Society for completing the remaining work. The Society says that no Power of Attorney was ever executed in favour of Respondent No. 2. It says that it had agreed to give only such cooperation as was provided in the Deed of Assignment.

43.

By letter dated 23 July 2021, the Society's Advocate stated that the Power of Attorney dated 13 December 2007 had been executed in favour of the partners of Respondent No. 1 and that no Power of Attorney was ever executed in favour of Respondent No. 2. Therefore, it is not disputed that no separate Power of Attorney was given to Respondent No. 2. However, whether the Society was required to execute a fresh Power of Attorney in favour of Respondent No. 2 cannot be decided merely because no such document was actually executed. The original Development Agreement provided for execution of a Power of Attorney. The Deed of Assignment stated that the earlier agreements would continue to bind the parties. Therefore, Respondent No. 2 can certainly argue that the Society was required to give the necessary authority for carrying out the work assigned to it.

44.

On the other hand, the Society points out that the Deed of Assignment does not state that a fresh Power of Attorney must be executed in favour of Respondent No. 2. It is its case that after termination of the development arrangement, it was not required to give any authority to Respondent No. 2. This submission of the Society will have to be considered.

45.

Whether refusal to execute the Power of Attorney amounted to a breach by the Society, whether Respondent No. 2 was prevented from obtaining the Commencement Certificate and whether non-cooperation by the Society caused the delay will require examination of the exact terms of the agreements and later correspondence. It will be necessary to examine whether Respondent No. 2 had actually submitted plans and applications before the authorities and whether any permission was refused because the Society had not given the Power of Attorney. I am not accepting the Petitioner's argument that the Society had no duty at all to provide cooperation under the development arrangement. At the same time, I am unable to accept the argument of Respondent No. 2 that the entire delay was caused by the Society. The Respondents were required to take necessary steps before the concerned authorities and produce material showing that they were ready and financially capable of completing the remaining work.

46.

The judgment dated 17 September 2019 passed by this Court in the Second Appeals is relevant even on this issue. As noticed, in paragraph 55 of that judgment, this Court observed that Respondent No. 2 had not produced any material to show what steps it had taken against MCGM or MHADA because the Commencement Certificate was not granted. This observation is important because the present defence of Respondent No. 2 is mainly based upon the allegation that the Society did not provide the required cooperation.

47.

Respondent No. 2 has referred to letters dated 13 April 2017, 13.06.2017 and certain other communications through which it had requested the Society to provide documents and cooperation. These letters may show that requests were made. However, merely making a request does not establish that the Society was responsible for the entire delay. It will have to be shown what particular work could not be carried out, what permissions were required, what steps were taken by Respondent No. 2 and how the Society prevented it from proceeding further.

48.

There is a considerable gap after the letter dated 8 March 2020 addressed by Respondent No. 2 to MahaRERA. If Respondent No. 2 had decided to terminate the project on an “as is where is” basis because the Society was not cooperating, it was necessary for Respondent No. 2 to show when and how the parties thereafter restored their contr-relationship and on what conditions. At present, the material on this aspect is not sufficiently clear. I find that the defence of non-cooperation raised by Respondent No. 2 will have to be decided in arbitration. On the present material, this defence cannot be accepted as a sufficient reason to prevent the Society from taking steps to complete redevelopment through another Developer.

Dispute regarding the compound wall and demarcation:

49.

Respondent No. 2 has alleged that the Society constructed an illegal boundary wall and that this obstructed redevelopment of Building No. 132. According to Respondent No. 2, the revised demarcation issued by MHADA required removal of the wall and shifting it towards Building No. 133. The Society disputes this allegation. It says that it never agreed to reduce or change the area in its possession.

50.

I have referred to Clause (g) of the Deed of Assignment. This clause provides that the boundaries of the Society's plot could be changed without reducing the total area of the plot. It provides that the entrance, exit and parking arrangements of the Society would remain separate from those of the adjoining building. Therefore, the Respondents cannot rely upon the condition regarding cooperation for redevelopment of Building No. 132 to say that the Society had agreed to give up any portion of its property.

51.

The order dated 4 July 2022 passed by this Court does not support the argument that the Society had agreed to joint redevelopment of both buildings. The order records the revised layout, the need to remove the wall and the agreement of the Developer to remove it at its own cost. It directs the parties to cooperate for obtaining the Occupation Certificate. I find that the dispute regarding the compound wall and demarcation is separate from the question whether Respondent No. 2 continues to have development rights under the Deed of Assignment. The Respondents cannot use the dispute regarding the wall to claim an unrestricted right over the Society's property. At the same time, the Society cannot refuse to follow any lawful demarcation or direction issued by the competent authority. The Deed of Assignment protects the Society's total property area. The boundary and any permissible change will have to be decided according to the approved plans and lawful demarcation carried out by the competent authority.

Alleged suppression of correspondence:

52.

Respondent No. 2 has strongly alleged that the Petitioner has not placed important correspondence before this Court. It is pointed out that the Petition was notarised on 7 October 2026 and filed on 14 October 2026, whereas the legal notice issued by Respondent No. 2 was dated 6 October 2026. It is argued that the Society did not disclose the notice dated 11 September 2026 issued on behalf of five flat purchasers or its reply dated 12 October 2026. The Petitioner has explained in its Additional Affidavit that the letter dated 6 October 2026 was received after the Petition was filed. Respondent No. 2 disputes this explanation. However, from the material available, the exact date on which the said letter was actually received is not established. I find that the correspondence dated 11 September 2026 and 12 October 2026 was relevant and should be considered while deciding the dispute. According to Respondent No. 2, the Society's reply stated that the earlier development documents could not be treated as giving any unrestricted or continuing right to Respondent No. 2. Even if the Society accepted that certain rights and responsibilities existed under the earlier documents, such acceptance cannot be treated as an admission that Respondent No. 2 continued to have an unrestricted right to carry out redevelopment.

53.

Respondent No. 2 has referred to letters dated 2 February 2023, 7 March 2023, 14 May 2023, 30 August 2023 and certain letters of 2025, including the letter dated 11 November 2025. According to Respondent No. 2, these communications show that the Society continued to recognise it as the Developer and had agreed to execute the necessary Power of Attorney. The Petitioner disputes the meaning which Respondent No. 2 wants to give to these letters. The complete contents of all these communications will have to be examined by the Arbitral Tribunal. Merely stating that a letter was issued on a particular date does not establish what exact admission or promise was made in it. All the correspondence will have to be read in its proper order and along with the earlier termination notices and the order dated 4 July 2022. I am not inclined to hold that the Petitioner deliberately kept back material facts from this Court merely on the basis of the allegations made by Respondent No. 2. However, the Society will have to place the complete correspondence, including its reply dated 12 October 2026 and all letters concerning the Power of Attorney and demarcation, before the Arbitral Tribunal. The same responsibility applies to Respondent No. 2. It will have to produce the complete correspondence, applications made before the authorities, permissions obtained, expenses incurred and all other documents on which it relies. Neither party should be permitted to rely upon selected letters while keeping the remaining correspondence away from the Arbitral Tribunal.

Claim of Rs.91,08,142/- and alleged charge over development potential:

54.

Respondent No. 2 has claimed that it spent Rs.91,08,142/-towards completion of the project. The letter dated 1 February 2019 gives details of the expenditure which Respondent No. 2 claims to have incurred. This amount includes Rs.60 lakhs paid to the Society and other expenses towards electricity, stamp duty, registration, labour charges, legal expenses, property taxes, repairs and construction materials. The Society disputes the right of Respondent No. 2 to recover this amount. According to the Society, Respondent No. 2 had accepted all the liabilities under the Deed of Assignment and had agreed to clear those liabilities without creating any encumbrance or lien over the Society's property.

55.

I find that the amount claimed by Respondent No. 2 is a money claim arising from the development arrangement. Whether the amount was actually spent, whether the expenditure was necessary for the project, whether it was incurred according to the Deed of Assignment and whether Respondent No. 2 is entitled to recover it from the Society are questions which will have to be decided in arbitration. However, merely because Respondent No. 2 has claimed Rs.91,08,142/-, it does not mean that a charge or lien is created over the Society's property. The Deed of Assignment provided that Respondent No. 2 would obtain financial assistance at its own risk and cost and clear the liabilities without creating any encumbrance over the Society or its members. No separate document creating a charge over the Society's property has been shown to this Court. The statement in the letter dated 1 February 2019 that Respondent No. 2 would have a “paramount charge” over the remaining development potential is not sufficient, , to establish an enforceable charge at this stage. Respondent No. 2 will be free to raise its money claim before the Arbitral Tribunal. However, merely making such a claim cannot prevent the Society from taking steps for redevelopment. The indemnity given under the Deed of Assignment in favour of the Society against claims made by flat purchasers and investors is important. The Respondents had accepted responsibility for claims arising from the sale of flats and other rights created by Respondent No. 1. Therefore, the Society's right to protect its property cannot depend upon Respondent No. 2 first receiving the amounts which it claims to have spent.

Rights of flat purchasers:

56.

There is another aspect which requires separate consideration. The Deed of Assignment records the existence of flat purchasers forming part of the free-sale component. However, the material on record shows different figures regarding the number of flats sold on the eighth floor. The Society refers to seven flats. Respondent No. 2 refers to nine flats. The Deed of Assignment and judgment dated 17 September 2019 refer to ten proposed flats.

57.

The judgment dated 17 September 2019 passed by this Court has considered the rights of five purchasers and recognised the statutory responsibilities of Respondent No. 2 towards them. The rights of these purchasers cannot be taken away by the present order. The dispute regarding termination between the Society and the Respondents cannot be used to defeat the rights created in favour of the purchasers. Respondent No. 2 will have to give complete details of all purchasers, the flats agreed to be sold, the consideration received, the balance consideration payable and the agreements executed with them. It will have to disclose whether any third-party rights were created after execution of the Deed of Assignment.

58.

While proceeding with redevelopment through another Developer, the Society will have to keep in mind the rights of the existing purchasers and follow all applicable provisions of the Real Estate (Regulation and Development) Act, 2016. This Court is not deciding the individual rights of the purchasers in the present Petition. Those rights will remain open and will have to be protected according to law. The statutory responsibilities which this Court had recognised against Respondent No. 2 in the Second Appeals cannot be treated as having come to an end merely because the Society is now being permitted to take steps for redevelopment.

Steps taken by the Society for appointment of a new Developer:

59.

The Society states that the building is in a dilapidated condition and redevelopment should be taken forward without delay. It states that it has followed the procedure under Section 79A of the Maharashtra Co-operative Societies Act, 1960.

60.

By letter dated 25 March 2026, the Society approached the Deputy Registrar of Co-operative Societies and requested appointment of an authorised officer and calling of a Special General Body Meeting for appointment of a new Developer. The Society forwarded the consent of its members in support of the redevelopment proposal. Thereafter, the Executive Engineer, Building Proposal Department, issued a letter dated 13 May 2026 directing the Society to make arrangements for appointing a Project Management Consultant to examine the proposal regarding appointment of a Developer. The Society was directed to arrange video recording and a meeting was fixed on 18 May 2026. These documents show that the Society has started the process of appointing a new Developer. It is not merely stating before this Court that it wants another Developer. It has taken steps before the concerned authorities and is trying to proceed according to the applicable procedure.

61.

Respondent No. 2 argues that these steps are against its contr-rights. According to it, the Society cannot appoint another Developer while the Deed of Assignment continues to bind the parties. This argument will depend upon the final decision regarding termination and the later conduct of the parties. However, as discussed, the project has remained incomplete for a considerable period. The Occupation Certificate has not been obtained. Construction of the eighth floor and other remaining work is still pending. Respondent No. 2 has not placed before this Court any definite and reliable programme showing how the remaining work will now be completed, within what time and through what financial arrangements. The Society cannot be made to wait without any end until the Arbitral Tribunal finally decides the contr-dispute. The purpose of Section 9 is to protect the subject matter of arbitration. It is not meant to allow an incomplete redevelopment project to remain stopped for an uncertain period.

Applicable decisions and principles governing redevelopment disputes:

62.

I have considered the judgment of this Court in Om Vithal Cooperative Housing Society Limited v. Trilogy Infra Private Limited, Arbitration Petition (L) No.25010 of 2026 with Commercial Arbitration Petition (L) No.23586 of 2026, decided on 20 August 2026. This judgment is relevant because it deals with the competing rights of a Society and its Developer after termination of a redevelopment agreement. In paragraph 19, this Court observed that the limited question under Section 9 was whether redevelopment should continue with the existing Developer until arbitration was completed or whether the Society should be permitted to take steps for redevelopment while protecting the rights and claims of the Developer. In paragraph 25, this Court considered the effect of an extension given by the Society to the Developer. It was held that merely because an extension is given, the Developer does not get an unlimited right to delay the project without facing any consequence. The extension is given so that the Developer can complete its responsibilities within the extended period. This principle is relevant here. The later correspondence and cooperation between the parties cannot give Respondent No. 2 an unlimited right to continue with the project without showing progress or giving a definite programme for completion. In paragraphs 27 and 28, this Court held that the validity of termination cannot be finally decided in proceedings under Section 9. The Court can make an interim arrangement so that redevelopment does not remain stopped until arbitration is completed.

63.

The said judgment considered the decision in Pioneer Constructions v. Sahakarnagar Co-operative Housing Society Limited, 2026 SCC OnLine Bom 2711. In paragraph 30, this Court reproduced the following observation:

“the rights of a developer to earn profits through redevelopment contracts would always remain subservient to the rights of the society to have its building reconstructed.”

64.

In paragraph 33, this Court referred to the principle that the Court must make a prima facie examination to find out which party appears to be responsible for breach of the Development Agreement. It was made clear that a Society cannot be permitted to terminate every Development Agreement merely because it wants to appoint another Developer. If the Society has wrongly terminated the Agreement, the Court can put proper conditions upon the Society before allowing it to proceed with redevelopment.

65.

The Court has to examine the conduct of both sides. It cannot assume that the Society is always right or that the Developer is always wrong. The performance of contrresponsibilities, reasons for delay, financial capacity of the Developer and later conduct of both parties must all be considered.

66.

The judgment in Om Vithal Cooperative Housing Society considered the decisions in Ison Builders LLP, Commercial Arbitration Petition (L) No.36533 of 2025, decided on 23 January 2026, and Swashray Co-operative Housing Society Limited v. Shanti Enterprises, Commercial Arbitration Petition (L) No.10432 of 2023, decided on 3 November 2023.

67.

In paragraph 38, this Court referred to the principle that a Developer whose main interest is earning profit under a redevelopment agreement can claim damages if the Society has wrongly terminated the Development Agreement. However, the Developer cannot insist that the Society must wait until the entire arbitration is completed before taking steps for redevelopment.

68.

In paragraph 40, this Court reproduced the following observation from Swashray: “The Petitioner-Society is not expected to be at the mercy of the Respondent-Developer.”

69.

The meaning of this observation is that a Society and its members cannot be forced to remain under an incomplete development arrangement for an unlimited period, particularly when there have been repeated defaults and there is no reasonable assurance that the work will be completed.

70.

At the same time, paragraph 45 of Om Vithal Cooperative Housing Society makes it clear that payment of damages may not be an adequate answer in every case. If the building is substantially completed, the Developer has made substantial investment and is financially capable of completing the remaining work, the Court may have to take a different view. Every case will have to be decided on its own facts and material. In paragraph 47, this Court held that if the Society is prevented from proceeding with redevelopment, the entire project may remain dependent upon the final result of arbitration. Arbitration may take considerable time. The Society and its members cannot be expected to remain uncertain during this period when the project can otherwise be taken forward and the Developer's money claims can be decided separately.

71.

These observations are relevant to the present dispute, though the facts are not exactly the same. Here, the rehabilitation portion has been constructed and possession has been given to the members. Therefore, this is not a case where the members have lost their homes after demolition and are all waiting in transit accommodation. However, the construction remains incomplete, the eighth floor has not been constructed, the Occupation Certificate has not been obtained and the rights of the flat purchasers have not been fully dealt with.

72.

The earlier judgment in Kannamwar Nagar Aditya Cooperative Housing Society Limited is relevant. In that case, this Court considered repeated defaults by the Developer, non-payment of hardship compensation, incomplete construction and repeated assurances which were not followed by performance. In paragraph 28, this Court held that merely saying that defaults would be corrected is not sufficient when earlier assurances had not resulted in compliance. In paragraph 29, this Court considered the argument of the Developer that substantial investment had been made and third-party rights had been created. It held that the money investment could be compensated through arbitration if the Developer succeeded in establishing its claim. However, the loss of time suffered by the members of the Society could not be compensated so easily. In paragraphs 40 to 42, this Court ultimately held that the Society had made out a strong prima facie case for interim protection and permitted it to proceed with redevelopment, while keeping the money claims and other disputed liabilities open for arbitration.

73.

The principles laid down in the above two judgments make it clear that the Court must examine whether continuation of the existing Developer is likely to take redevelopment forward or whether it will only result in disputes and delay. The Court must protect genuine money claims of the Developer and the rights of existing flat purchasers. For making such an interim arrangement, it is not necessary to finally decide the validity of termination.

Overall assessment of the rival submissions:

74.

Applying the above principles to the present case, I find that Respondent No. 2 has raised certain important defences which cannot be ignored. It relies upon the construction completed, possession given to the Society members, execution of the Deed of Assignment, alleged non-cooperation by the Society, absence of a fresh Power of Attorney and correspondence exchanged after the order dated 4 July 2022. These submissions may be important when the matter is decided by the Arbitral Tribunal. In particular, whether the Society was required to execute a fresh Power of Attorney, whether its failure to do so prevented Respondent No. 2 from obtaining necessary permissions and whether the later correspondence amounted to withdrawal of the earlier termination will require detailed examination. However, the question before this Court is not whether Respondent No. 2 may be able to establish some rights before the Arbitral Tribunal. The question is whether, on the material available, Respondent No. 2 should be allowed to continue claiming an independent right to carry out redevelopment and prevent the Society from taking steps for completing the project.

75.

While considering this question, certain facts which are not seriously disputed are important. The original Development Agreement was executed on 13 December 2007. The Supplemental Agreement was executed on 5 May 2012. Respondent No. 1 could not complete the project and thereafter assigned the remaining development work and liabilities to Respondent No. 2 on 9 November 2015. Even after execution of the Deed of Assignment, the project remained incomplete. The rehabilitation portion and the building up to the seventh floor may have been substantially completed and possession was given to the members. However, the eighth floor was not constructed and the Occupation Certificate was not obtained.

76.

Five flat purchasers had to approach MahaRERA for enforcing their rights. Respondent No. 2 faced an adverse order before MahaRERA and thereafter before this Court in the Second Appeals decided on 17 September 2019. This Court held that Respondent No. 2 could not avoid its statutory responsibilities towards the purchasers by relying upon termination of the Deed of Assignment. The letter dated 1 February 2019 issued by Respondent No. 2 and its later letter dated 8 March 2020 addressed to MahaRERA are important. Through these communications, Respondent No. 2 treated the development arrangement as having come to an end and informed the statutory authority that there was no possibility of restarting the remaining work.

77.

The later correspondence after 2022 shows that the parties again started discussing certain pending matters. However, no clear document showing that the entire development rights were unconditionally restored in favour of Respondent No. 2 has been produced. The order dated 4 July 2022 mainly concerned removal of the compound wall and obtaining the Occupation Certificate. Cooperation for complying with that order cannot be treated as restoration of all development rights. Respondent No. 2 has not placed before this Court any reliable material showing that it has now made definite financial arrangements for completing the remaining work. There is no clear construction programme showing what steps have been taken for obtaining the Commencement Certificate for the eighth floor, when the remaining work will be completed and by what date the Occupation Certificate will be obtained. Merely saying that Respondent No. 2 is ready and willing to complete the project is not sufficient. There must be some material showing how and within what time the remaining work will actually be completed. The Society has waited for several years after execution of the Deed of Assignment. Even after the order dated 4 July 2022, the Occupation Certificate has not been obtained. The correspondence relied upon by Respondent No. 2 shows that some efforts were made for demarcation and for resolving the dispute regarding the compound wall. However, these letters do not show that the remaining construction was completed or that the Occupation Certificate was obtained. Efforts for demarcation cannot be treated as completion of the main responsibilities under the Deed of Assignment.

78.

I find that the material available does not give sufficient confidence that Respondent No. 2 will be able to complete the remaining work within any definite and reliable period. On the contrary, the long delay, earlier termination communications, failure to obtain the Occupation Certificate and continuing disputes between the parties show that there is a serious breakdown in their relationship. Merely because Respondent No. 2 has incurred some expenditure or has money claims against the Society, it does not mean that it must necessarily be allowed to continue as Developer. Such claims can be examined by the Arbitral Tribunal. If Respondent No. 2 establishes that the termination was wrongful and that it is entitled to recover any amount, the Tribunal can grant proper money relief. At the same time, the Society cannot use this order to defeat the rights of existing flat purchasers. The Society will have to proceed with redevelopment according to RERA and other applicable laws. Appointment of a new Developer will not bring an end to the responsibilities which Respondent No. 2 has towards the existing purchasers under the earlier agreements and the orders passed in the RERA proceedings. Therefore, the balance of convenience is in favour of permitting the Society to take the redevelopment process forward, while keeping the money claims of Respondent No. 2 protected and ensuring that the rights of existing flat purchasers are not affected. If the Society is prevented from taking steps, the incomplete project may remain dependent upon the final result of arbitration. There is no sufficient reason to make the Society wait for an unlimited period.

79.

I am of the view that the original redevelopment documents should be handed over to the Society. The Society is the owner of the building and is entitled to keep the documents relating to its property. These documents are necessary for placing the title and redevelopment proposal before prospective Developers and the concerned statutory authorities. The Respondents cannot continue to keep the original documents merely because they have raised money claims or dispute the termination. However, Respondent No. 2 must be allowed to keep proper copies of these documents for pursuing its claims in arbitration. These documents are necessary for deciding the amount allegedly spent on the project, the extent of construction completed, the rights of purchasers and the responsibilities of the parties. Therefore, both sides must maintain proper records.

80.

The parties will have to maintain proper accounts of the expenditure incurred and any expenditure which may be incurred for completing the project. The Society will have to keep records of the fresh redevelopment arrangement, payments made to the statutory authorities and transactions with the new Developer.

81.

I am satisfied that the Petitioner has made out a prima facie case for interim protection under Section 9 of the Arbitration and Conciliation Act, 1996. However, the relief must be limited to protecting the redevelopment process and keeping the rights and claims of both sides safe. No final declaration regarding the legality or validity of termination can be made at this stage.

82.

In view of the above discussion and after considering the material placed on record by both sides, the following order is passed:

(i)

The Arbitration Petition filed by the Petitioner Society is partly allowed;

(ii)

The Petitioner Society is permitted to take steps for appointing a new Developer or for undertaking self-redevelopment of Building No. 133, Nehru Nagar, Kurla (East), Mumbai. The Society shall follow the applicable procedure under Section 79A of the Maharashtra Co-operative Societies Act, 1960 and obtain all necessary permissions, approvals and consents under RERA, MHADA, MCGM and other applicable laws;

(iii)

Until commencement and conclusion of the arbitral proceedings, Respondent Nos. 1 and 2, their partners, officers, servants, agents and all persons claiming through or under them shall not represent before any authority, purchaser, Developer or third party that they have an independent and continuing authority to undertake redevelopment of the Society's property on the basis of the Development Agreement dated 13 December 2007, Supplemental Development Agreement dated 5 May 2012 and Deed of Assignment dated 9 November 2015;

(iv)

Respondent Nos. 1 and 2 shall not obstruct or interfere with the Society in taking lawful steps for redevelopment, either by undertaking self-development or through another Developer appointed according to law;

(v)

Respondent Nos. 1 and 2 shall, within two weeks from today, hand over to the Society all original documents relating to the title and redevelopment of Building No. 133 which are in their possession or control. These shall include the Development Agreement dated 13 December 2007, Supplemental Development Agreement dated 5 May 2012, Deed of Assignment dated 9 November 2015, Power of Attorney, Sale Deed, Lease Deed, IOD, Commencement Certificate, MHADA NOC, approved plans, revised layout plans, parking layout approval, permissions, correspondence, receipts, drawings and all other project records;

(vi)

Before handing over the original documents, Respondent Nos. 1 and 2 may keep photocopies or scanned copies of the same. The Society shall prepare a list of all original documents received and shall preserve proper copies for the purpose of arbitration;

(vii)

Respondent No. 2 shall, within three weeks from today, file an Affidavit giving the following details:

a)

Complete details of all flats sold and unsold in the project.

b)

Names and addresses of all flat purchasers, along with copies of the agreements executed with them.

c)

Amounts received from the flat purchasers and the balance consideration payable.

d)

Details of construction expenditure, payments made to the statutory authorities and outstanding dues of MHADA and MCGM.

e)

Details of all creditors, debtors and encumbrances, if any, claimed in respect of the project.

f)

Details of all sanctioned plans, revised plans, permissions, approvals and applications made before the concerned authorities.

g)

Details of the construction work completed and the remaining work which is required to be carried out.

(viii)

Respondent Nos. 1 and 2 and all persons claiming through or under them are restrained from creating any fresh third-party rights, executing fresh agreements, selling, transferring, assigning, mortgaging, charging or otherwise creating any encumbrance over the Society's property or any part of it on the basis of the disputed redevelopment documents;

(ix)

The above restraint shall not affect the existing rights of the flat purchasers under their respective agreements or the statutory responsibilities of Respondent No. 2 under RERA and the orders passed in proceedings relating to those purchasers. The rights of existing purchasers shall not be treated as having come to an end because of this order;

(x)

The Society shall maintain proper accounts and records of all expenses incurred and transactions undertaken under any fresh redevelopment arrangement. It shall preserve all documents, approvals, receipts, agreements and correspondence so that the money claims of Respondent No. 2, if any, can be properly examined by the Arbitral Tribunal;

(xi)

The claim of Respondent No. 2 for recovery of Rs.91,08,142/-, interest, damages and any other amount allegedly spent on the project is kept open for decision by the Arbitral Tribunal. Merely on the basis of the claim made by Respondent No. 2 in its letter dated 1 February 2019, no charge or lien over the Society's property is recognised;

(xii)

All contentions raised by petitioner are kept open for decision by the Arbitral Tribunal;

(xiii)

All rights and liabilities of Respondent Nos. 1 and 2, are kept open for decision in arbitration and appropriate statutory proceedings;

(xiv)

The Society is free to approach the concerned authorities for recording the termination, obtaining fresh approvals, seeking changes in plans and obtaining such other permissions as may be necessary for taking redevelopment forward. Respondent Nos. 1 and 2 shall not obstruct any such lawful steps;

(xv)

Respondent Nos. 1 and 2 shall remove of all articles and contractors from the property.;

(xvi)

The Petitioner Society shall ensure that the rights of existing flat purchasers are protected and that any fresh redevelopment arrangement is entered into only after following all applicable legal requirements. The money claims of Respondent No. 2, if established, shall remain subject to the final arbitral award;

(xvii)

Both sides shall preserve all original documents, correspondence, approvals, sanctioned plans, payment receipts, agreements and other records relating to the redevelopment project. Neither party shall destroy, change or misuse any such document or record;

(xviii)

If the arbitral proceedings have not commenced, the Petitioner shall take proper steps to commence arbitration within ninety days from the date of this order, in accordance with Section 9(2) of the Arbitration and Conciliation Act, 1996;

(xix)

It is made clear that all findings recorded in this order are only prima facie findings for deciding the present Petition under Section 9 of the Arbitration and Conciliation Act, 1996. The learned Arbitral Tribunal shall independently decide all questions, including the legality of termination, alleged breaches, later conduct of the parties, rights of the flat purchasers and money claims. The Tribunal shall not be influenced by any observations made in this order;

83.

The Arbitration Petition is disposed of in the above terms. There shall be no order as to costs.

84.

At this stage, learned Advocate for Respondent No.2 seeks stay of this judgment and order. However, for the reasons recorded above, the request for stay stands rejected.