High CourtsDivision Bench(1910) 12 MAD CK 0024

The Krishna Jute and Cotton Mills Company Limited by their Secretary and Treasurer, Mothe Gangaraju of Ellore vs J. Innes and Others

Madras High Court · Decided on 20 December 1910 · Citation: (1911) 21 MLJ 182

HON’BLE JUDGES
Wallis, J

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

31 paragraphs · 793 words

Wallis, J.—My answer to the reference is that in both the cases put the damages must be ascertained with reference to the date provided for

the performance of the contract. When before the date fixed for performance of a contract the promisor refuses to perform it, and the promisee

rightly rescinds it u/s 39 of the Indian Contract Act, he is u/s 75 entitled to ""compensation for any damage which he has sustained through the non-

fulfilment of the contract."" This appears to me to be the section applicable to the present case and I think that non-fulfilment of the contract means

non-fulfilment at the date specified in the contract, and that, according to the proper construction of the section, compensation is to be ascertained

with reference to that date, and not with reference to the date of the act of refusal which gave rise to the right to rescind. At the hearing of the

appeal, however, and also at first on this reference, the case was argued as if the suit was one to recover compensation u/s 73 for a breach of

contract, the breach in this case being the refusal of the promisor to perform the contract. This, however, is not the way in which the case has been

dealt with in England Frost v. Knight (1872) L.R. 7 Ex. III, Rochester v. De La Tour (1853) 2 E.&B. 678 and I propose so to deal with it here

both for this reason and because I think the result is the same whether the case is regarded as governed directly by Section 75 or Section 73. The

breach being the defendants'' refusal to perform, the plaintiff is then entitled, u/s 73, to compensation for any loss or damage caused to him thereby

which naturally arose in the usual course of things from such breach. This merely expresses the English rule as to the nature of damages in Hadley

v. Baxendale (1854) 9 Ex. 341, so that the general principles upon which compensation or damages are to be assessed in cases of this kind are

the same in India as in England and there is nothing in Section 73 to warrant the question being dealt with on different lines in India. When the

Indian Contract Act was drafted and enacted the correct method of assessing damages in this particular case had not been clearly decided in

England; otherwise seeing the importance of the point, it would probably have been dealt with in an illustration to Section 73 or Section 75. But in

February 1872, the year in which the Indian Contract Act was passed, it was held in England, by the Court of Exchequer Chamber in Frost v.

Knight (1872) L.R. 7 Ex. III and by the Court of Exchequer in the following June in Brown v. Muller (1872) L.R. 7 Ex. 319, though only obiter -

that the damages were to be estimated with refer to the time fixed for performance in the contract. In the following year (1873) the point was

expressly decided in Roper v. Johnson (1873) L.R.C. 8 167, in which the refusal to perform, the bringing of the action and the trial all took place

before the date for performance specified in the contract, and after the case had been argued by two of the foremost lawyers of the day, Holker on

the one side and Herschell on the other, it was held that the true measure of damages was prima facie the difference between the contract price

and the market price at the date fixed for delivery although that date had not arrived when the action was brought and the suit tried. The decision

dealing with an important question of every-day occurrence in a commercial country has now been treated as settled law for nearly thirty years in

England, and also I think I may say in India, having regard to the frequency with which the point must have arisen and the absence of any reported

cases to the contrary. As regards the Original Side of this Court, I can speak personally to its having been followed in several unreported cases. In

these circumstances, I should1 be of opinion that it ought to be followed even if I ventured to differ from the reasons given in the judgments. On the

contrary, those judgments, especially that of Brett J., afterwards Lord Esher, appear to me to be conclusive; and further it seems to me that the

alternative method of ascertaining the compensation with reference exclusively to the date of the breach, viz., the refusal to perform, would in many

cases fail to give compensation for the loss or damage naturally arising in the usual course of things from the breach, and so fail to satisfy Section

73