High CourtsSingle Bench(2012) 08 KL CK 0110

Thayyal Kappanakkal Moosan vs The District Collector, Kannur Pin-670001 and The Special Tahsildar (Land Acquisition) (Ezhimala Naval Academy), Thalassery-670101 Kannur District.

High Court Of Kerala · Decided on 22 August 2012

HON’BLE JUDGES
Antony Dominic, J
CASE NUMBER
Writ Petition (C) . No. 19981 of 2012 (W)

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

4 paragraphs · 295 words

Justice Antony Dominic

1.

Petitioner states that 0.1012 hectors of land in R.S. No. 69/3 of Ramanthali Village was acquired for establishment of Naval Academy at Ezhimala. By submitting Ext.P1, petitioner sought redetermination of the compensation as provided u/s 28A of the Land Acquisition Act. That application was rejected by Ext.P2 order. Thereupon the petitioner sought a reference u/s 28A(3) by submitting Ext.P3. That application was also rejected by Ext.P4. It is challenging Exts.P2 and P4, the writ petition has been filed. A reading of Exts.P2 and P4 orders show that the reason stated for rejection is that the award in LAR.No.120/2006 of Sub Corut, Payyannur relied on by the petitioner in Exts.P1 and P3 applications were rendered in a reference u/s 28A(3) of the Act and not u/s 18 of the Act. Therefore, according to the respondent redetermination is not possible based on such an award. It is also seen that to substantiate the aforesaid conclusion the respondents have relied on the judgment of this court in Haji A. Abdul Rashid V. Spl. Tahsildar (2008 (1) KLT 974.

2.

However, I am of the view that the conclusion in Exts.P2 and P4 is not supported by the principles laid down by this court in judgment referred above. On the other hand, in the judgment in Joseph Vs. District Collector, this court has held that an award u/s 28A(3) is sufficient to maintain a claim u/s 28A. Therefore, Exts,.P2 and P4 are unsustainable and are quashed. The 2nd respondent is directed to pass fresh orders on Ext.P1. This shall be done as expeditiously as possible and at any rate within 8 weeks of production of a copy of the judgment along with a copy of the writ petition.

Writ Petition is disposed of as above.