Judgment
By this Petition filed under Section 9 of the Arbitration and Conciliation Act, 1996, the Petitioner is seeking interim and ad-interim reliefs against the Respondents. According to the Petitioner, the Respondents are not cooperating with the redevelopment of the property bearing CTS No.684, Bharadawadi Road, Andheri (West), Mumbai 400 058. The redevelopment is being carried out pursuant to the registered Development Agreement dated 19 June 2024 and the Supplemental Development Agreement dated 23 May 2026. Out of 47 members, 41 members have complied with the Vacation Notice. However, the remaining non-consenting members have not vacated their respective premises or handed over possession. They have not executed the PAAAs. According to the Petitioner, because of this, the entire redevelopment work is being obstructed.
The facts stated by the Petitioner which have resulted in filing of the present Petition are as follows. The existing building is about 62 years old. It consists of 49 units and there are 47 members. Out of them, 41 members are cooperating, and 4 members are stated to be not cooperating. Respondent No.1 Society had, by majority resolution passed in its Special General Body Meeting ("SGBM") held on 28 July 2012, decided to redevelop its property. Thereafter, Respondent No.1 appointed a Project Management Consultant on 8 February 2014. Through its PMC, Respondent No.1 invited tenders on 6 September 2014 from interested Developers. The group firm of the Petitioner, namely, M/s. Rachanaa, submitted its bid along with 12 other bidders. Out of these bidders, three Developers were shortlisted, including the Petitioner. Between the years 2015 and 2019, Respondent No.1 did not proceed further with the appointment of a Developer because DCPR 2034 was proposed to be introduced. Thereafter, Respondent No.1 again started the process of appointing a Developer from the three Developers who had earlier been shortlisted. The shortlisted Developers were asked to submit revised offers on the basis of DCPR 2034. Only the Petitioner submitted a revised offer. In the SGBM held on 12 October 2019, the majority of the members resolved to accept the offer of the Petitioner. At the instance of the Managing Committee, the PMC submitted a feasibility report dated 3 December 2019 on the basis of DCPR 2034 for the purpose of re-tendering. Thereafter, on 16 January 2020, notices inviting fresh bids were published in three newspapers. Three Developers submitted their bids, including the Petitioner. In the SGBM held on 23 February 2020, Respondent No.1 passed a resolution by majority approving the bid submitted by the Petitioner. The redevelopment process was thereafter kept on hold because of the Covid-19 pandemic. Subsequently, in its SGBM dated 26 January 2022, Respondent No.1 resolved to consider the offer of the Petitioner and to discuss the structural audit report. In the SGBM held on 27 February 2022, Respondent No.1, by a majority of 76% members, resolved to accept the offer of the Petitioner's group firm, M/s. Rachana, for redevelopment of the property.
Between February 2022 and September 2022, Respondent Nos.2 to 11 raised objections and filed complaints regarding the redevelopment process. According to the Petitioner, these objections were without substance. The Deputy Registrar, by order dated 4 October 2022, directed Respondent No.1 to start the process of appointment of Developer afresh under Section 79A of the Maharashtra Co-operative Societies Act, 1960. Respondent No.1 took the stand that the steps required under Section 79A had been completed and that only the final step of inviting the Officer was required to complete the process. Accordingly, Respondent No.1 addressed a letter dated 4 November 2022 to the Deputy Registrar. A box file containing a summary of the steps taken for compliance with Section 79A of the MCS Act was enclosed with the letter. Respondent No.1 requested the Deputy Registrar to depute the Competent Officer to attend the SGBM. By letter dated 17 November 2022, the Deputy Registrar expressed his inability to do so and directed Respondent No.12 Society to initiate the redevelopment process afresh. Thereafter, Respondent No.1 addressed further letters dated 20 December 2022 and 20 January 2023 to the Deputy Registrar regarding its compliance report and again requested that the Competent Officer be deputed to attend the SGBM.
In the SGBM held on 19 February 2023, Respondent No.1, by a majority of 85% of the 39 members who attended the meeting, ratified and approved the appointment of the Petitioner's group firm, M/s. Rachanaa, as the Developer. In April 2023, seven non-consenting members filed Suit No.959 of 2023 against Respondent No.1 seeking to restrain it from proceeding with the redevelopment. Subsequently, on 23 June 2025, Consent Terms were filed between Mr. Suketu Nanavaty and Respondent No.1. Under the said Consent Terms, Mr. Nanavaty agreed to withdraw his objections and Suit No.959 of 2023.
In the SGBM held on 25 June 2023, Respondent No.1's members approved the Memorandum of Agreed Terms ("MOAT") by a resolution passed in the meeting. Respondent Nos.2 to 11 did not agree to the same. Thereafter, on 8 July 2023, the MOAT was signed by Respondent No.1 and the Petitioner. According to the Petitioner, execution of the MOAT marked completion of an important stage in the redevelopment process.
The Deputy Registrar thereafter passed an order dated 7 November 2023 under Section 76(3) of the MCS Act, 1960. By this order, Respondent No.1 was directed to hold an SGBM in the presence of an Authorized Officer for ratifying the resolutions by which the Petitioner had been appointed. The Deputy Registrar had issued a show-cause notice dated 25 July 2023. Pursuant to the order dated 7 November 2023, Respondent No.1 issued notice dated 9 January 2024 calling an SGBM on 28 January 2024. The said meeting was held in the presence of the Authorized Officer deputed by the Deputy Registrar. The members of Respondent No.1 again, by majority, ratified the resolutions dated 19 February 2023 and 25 June 2023 appointing the Petitioner.
On 17 January 2024, Respondent No.10 challenged the notice for the SGBM by filing a dispute before the Co-operative Court. On 23 January 2024, the PMC sought time to engage an Advocate on behalf of Respondent No.1. Respondent No.10 sought an order restraining Respondent No.1 from taking any policy decision pursuant to the notice dated 9 January 2024. According to the Petitioner, the notice dated 9 January 2024 was only for re-confirming decisions which had been taken earlier., there was no question of taking any fresh policy decision in the meeting fixed on 28 January 2024. No injunction was granted against holding the meeting. The PMC appearing before the Court had clarified that the policy matters had been decided and that the earlier decisions were being placed before the members again only because Respondent Nos.2 to 11 had raised objections regarding transparency. The PMC accordingly assured the Court that no fresh policy decision would be taken.
The SGBM was accordingly held on 28 January 2024 in the presence of the Authorized Officer deputed by the Deputy Registrar. In the said meeting, the members of Respondent No.1, by majority, ratified the earlier resolutions dated 19 February 2023 and 25 June 2023. The appointment of the Petitioner for carrying out the redevelopment on the terms recorded in the MOAT dated 8 July 2023 was thereby again confirmed. Thereafter, the Development Agreement ("DA") and Power of Attorney were executed between the Petitioner and Respondent No.1 on 19 June 2024. The said documents had been approved in the SGBM dated 9 June 2023. Respondent No.1 and 35 of its members signed the documents in favour of the Petitioner. Consent Letters were executed by 37 members of Respondent No.1. Subsequently, on 26 April 2025, because of the change in DCPR, the Petitioner increased its offer. The area of the new flats was increased by 8% and the monthly displacement compensation was increased by Rs.5 per sq. ft. over and above the amount agreed under the DA. The members unanimously agreed to this enhancement. According to the Petitioner, this was in terms of Clause 14(ii) and Clause 16(v) of the MOAT and Clauses 3.1, 3.2 and 3.5 of the DA. On 25 July 2025, the Petitioner submitted the required proposal and plans to Respondent No.1 for its approval and for issuance of the IOD. Thereafter, in the Extra Ordinary General Body Meeting held on 15 March 2026, Respondent No.1 unanimously passed a resolution approving the following matters: (i) the Supplemental Development Agreement ("SDA"), which recorded the increase in the area and displacement compensation; (ii) the PAAA; and (iii) the proposed plans to be submitted to Respondent No.12. In the same meeting, the allocation of the new flats and parking spaces to the members was finalized. The list of members who had opted to purchase additional area over and above their free eligible area was finalized.
On 8 June 2026, Respondent No.12, namely, the Executive Engineer, BMC, issued the Intimation of Disapproval ("IOD") in respect of the proposed new building. Thereafter, on 9 June 2026, the Petitioner issued a Vacation Notice to Respondent No.1 in accordance with the DA. By the said notice, the members were called upon to hand over vacant possession of their respective flats within 45 days, that is, on or before 24 July 2026. They were called upon to come forward for registration of the PAAA. Between 10 June 2026 and 6 July 2026, Respondent Nos.2 to 11, through their Advocate, sought copies of the DA and SDA and raised further objections. The Petitioner states that it repeatedly requested them to collect the documents and cooperate with the redevelopment. Respondent Nos.2 to 11 issued a notice dated 22 June 2026 under Section 164 of the MCS Act, 1960, threatening to initiate further litigation. On 4 July 2026, Respondent No.1 informed the Petitioner that, despite its efforts, Respondent Nos.2 to 11 continued to raise objections and had not given any confirmation that they would cooperate with the redevelopment. It is in these circumstances that the Petitioner has filed the present Petition under Section 9 of the Arbitration and Conciliation Act, 1996.
Mr. Gauraj Shah, learned Advocate appearing for the Petitioner, submits that Respondent Nos.2 to 11 have filed different proceedings before the City Civil and Sessions Court, the Co-operative Court and the Consumer Court. According to him, the decision taken by Respondent No.1 Society to redevelop the property is a collective decision of the Society. The decision was taken after following the required procedure and is binding on its members. He submits that once the Society and its members have approved the redevelopment and have approved the final form of the PAAA, six members, comprising ten individuals who are Respondent Nos.2 to 11, cannot be permitted to stop the entire redevelopment project merely by refusing to cooperate.
Mr. Shah submits that the time limits fixed under the Development Agreement are important and have to be followed. The Development Agreement provides specific periods for obtaining approvals, reaching the plinth stage and completing the construction and obtaining the occupation certificate from the Date of Vacating. According to him, even if possession of one flat is not handed over, it affects the entire project. It can delay demolition, mobilisation of the site, commencement of work, financing arrangements, contracts, appointment of consultants, payment of premiums and the obligation to complete the project within time. He submits that payment of money alone cannot sufficiently compensate the Petitioner for this continuing obstruction. He further submits that the loss is not being suffered only by the Petitioner. The other members of Respondent No.1 Society have agreed to vacate their premises and have given Consent Letters. They are waiting for demolition of the existing building and construction of the new building to commence. Their rights and expectations are being seriously affected because of the non-cooperation of Respondent Nos.2 to 11. According to him, the majority members who are ready to cooperate cannot be made to wait indefinitely because of the objections raised by a few members. He submits that Respondent Nos.2 to 11 have, till date, not challenged the Development Agreement and/or the Supplemental Development Agreement in any appropriate proceedings.
Mr. Kadiani, learned Advocate appearing for Respondent Nos.2 to 11, submits that in the dispute proceedings filed by the Respondents before the Co-operative Court, a statement and undertaking was given on 23 January 2024 by the Advocate appearing for Respondent No.1, namely, Adv. Chaitanya Purandare. According to him, it was stated before the Co-operative Court that no policy decision or resolution would be taken in the SGBM proposed to be held pursuant to the notice dated 9 January 2024. He submits that the Petitioner has deliberately tried to mislead this Court in paragraph Nos.20 to 22 of the Petition by not placing the undertaking in its proper meaning and context. According to him, the undertaking was not limited only to taking a "policy decision". It covered passing of any resolution in furtherance of the redevelopment. He submits that the Petitioner is now wrongly trying to give a narrow meaning to the undertaking by saying that only policy decisions were prohibited. He submits that the substance and purpose of the undertaking given by the Advocate for Respondent No.1 was that no policy decision would be taken and no resolution would be passed in furtherance of the redevelopment agenda while the dispute was pending before the Co-operative Court. He relies upon the following statement:
“Opponents are not taking any policy decision or no resolution will be passed in furtherance of the redevelopment agenda, pending consideration of the dispute before the Co-operative Court.”
According to Mr. Kadiani, despite the above position, the Petitioner has filed the present Commercial Arbitration Petition without disclosing the true meaning and effect of the statement made before the Co-operative Court. He submits that this amounts to suppression of material facts and that the Petitioner is seeking interim reliefs from this Court on the basis of an incomplete and misleading presentation of the earlier proceedings.
Mr. Kadiani further submits that despite the statement and undertaking given before the Co-operative Court, the SGBM was held on 28 January 2024. According to him, Respondent No.1 thereafter purportedly ratified and reaffirmed the resolutions dated 19 February 2023 and 25 June 2023 by which the appointment of the Petitioner as Developer had been formalised. He submits that, in substance, these acts amounted to passing of a resolution in furtherance of the same redevelopment agenda which was covered by the undertaking given by the Advocate for Respondent No.1 before the Co-operative Court.
Mr. Kadiani submits that the alleged expenditure of Rs.8,10,20,327/- (Rupees Eight Crores Ten Lakhs Twenty Thousand Three Hundred and Twenty-Seven) incurred by the Petitioner cannot, by, create any equity in favour of the Petitioner. According to him, the Petitioner incurred the said expenditure despite being aware of the objections raised by Respondent Nos.2 to 11 and the directions issued by the Deputy Registrar., such expenditure was incurred by the Petitioner at its own commercial risk. He submits that the amount allegedly spent by the Petitioner cannot be used as a reason to dispossess the Respondents or to compel the members to accept a redevelopment arrangement which is still disputed and has not been finally adjudicated.
Mr. Kadiani further submits that the statement made on behalf of Respondent No.1, referred to in paragraph 21 of the Petition, cannot be understood by considering only the expression "policy decision". According to him, the undertaking has to be understood from the circumstances in which it was given and from its actual substance. He submits that the Advocate appearing for Respondent No.1 had undertaken that Respondent No.1 would not pass any resolution or take any decision in furtherance of the redevelopment agenda while the proceedings were pending before the Co-operative Court. He submits that the steps taken in the SGBM dated 28 January 2024 were substantive steps. They further advanced and formally confirmed the appointment of the Petitioner as Developer and, according to him, were contrary to the undertaking given before the Co-operative Court.
REASONS AND FINDINGS:
I have considered the Petition, the documents placed on record and the submissions made by Mr. Gauraj Shah, learned Advocate for the Petitioner, Mr. Khandeparkar, learned Advocate for Respondent No.1 and Mr. Kadiani, learned Advocate for Respondent Nos.2 to 11. The question, which arises is whether the objections and disputes raised by Respondent Nos.2 to 11 can, at this stage, stop the redevelopment and whether this Court can grant interim relief under Section 9 of the Arbitration and Conciliation Act, 1996.
At the outset, the material shows that the redevelopment was not started suddenly by the Petitioner or only on the basis of an arrangement with a few members. Respondent No.1 Society had been considering redevelopment for a long period. The Society first passed a resolution in the SGBM dated 28 July 2012 to undertake redevelopment. Thereafter, a PMC was appointed and tenders were invited. Offers were considered at different stages. The Petitioner was initially shortlisted and its revised offer was considered. In the SGBM dated 23 February 2020, the Petitioner's bid was approved by majority. Thereafter, on 27 February 2022, the offer of the Petitioner's group firm was accepted by 76% majority. Again, in the SGBM dated 19 February 2023, the appointment was ratified by 85% of the members who attended the meeting. The MOAT dated 8 July 2023 was thereafter executed. Subsequently, after the order of the Deputy Registrar dated 7 November 2023, another SGBM was held on 28 January 2024 in the presence of the Authorized Officer and the earlier resolutions were again ratified by majority. Thereafter, the Development Agreement and Power of Attorney were executed on 19 June 2024., from the material before me, this is not a case where the Petitioner is trying to enter the property on the basis of some doubtful arrangement with only a few members. The redevelopment decision was considered and taken by the General Body of Respondent No.1 at different stages. Respondent Nos.2 to 11 may dispute the legality of some of these resolutions. Such disputes can be considered before the appropriate forum. But the fact that these resolutions were passed and that the Petitioner was repeatedly approved as the Developer cannot, at this stage, be disputed from the material placed before this Court.
Mr. Kadiani has strongly relied upon the statement stated to have been made on 23 January 2024 before the Co-operative Court. According to him, the Advocate for Respondent No.1 had given an undertaking that no policy decision would be taken and no resolution would be passed in furtherance of the redevelopment agenda while the dispute was pending before the Co-operative Court. The following words are relied upon:
“Opponents are not taking any policy decision or no resolution will be passed in furtherance of the redevelopment agenda, pending consideration of the dispute before the Co-operative Court.”
I have considered this submission. The above statement cannot be ignored. At the same time, it has to be understood in the background of the proceedings in which it was made and the matter which was then before the Co-operative Court. The notice dated 9 January 2024 had called the SGBM on 28 January 2024. According to the Petitioner, the meeting was called for re-confirming the decisions which had been taken, as objections regarding redevelopment had been raised. The material placed before this Court shows that no injunction was granted restraining the holding of the SGBM. It is further the case of the Petitioner that the PMC appearing before the Co-operative Court had explained that the policy matters had been decided and that the purpose of placing the matter before the General Body again was only to re-confirm those earlier decisions. Respondent Nos.2 to 11 submit that the undertaking cannot be understood in this limited manner. According to them, it did not prohibit only a fresh policy decision. It prohibited passing of any resolution in furtherance of the redevelopment agenda.
The words "no resolution will be passed in furtherance of the redevelopment agenda" are wide., if it is found that the SGBM dated 28 January 2024 amounted to a fresh prohibited resolution, the Respondents may find support from the language of the undertaking. However, this issue does not decide the present Petition. The record shows that the resolutions dated 19 February 2023 and 25 June 2023 had been passed before the SGBM dated 28 January 2024. The meeting dated 28 January 2024 is stated to have ratified and confirmed those earlier resolutions., from the material available, it cannot be said that the General Body appointed the Petitioner as Developer for the first time on 28 January 2024. What was done was to again confirm an earlier decision. Whether this action was in accordance with the undertaking given before the Co-operative Court is an issue which can be considered in those proceedings or before the appropriate forum. For deciding the present Petition under Section 9, this Court is not required to finally decide whether the undertaking was breached, unless such finding is necessary for deciding the interim relief sought.
Even if it is assumed that Respondent Nos.2 to 11 have a grievance that the SGBM dated 28 January 2024 was contrary to the earlier statement, that fact by does not make the redevelopment arrangement ineffective. The Respondents would have to show what legal effect such alleged breach has upon the subsequent Development Agreement dated 19 June 2024 and the Supplemental Development Agreement. On the material before me, no such legal consequence has been established.
There is another important aspect. Respondent Nos.2 to 11 have raised objections regarding the manner in which the redevelopment was approved. They have filed proceedings before different forums. However, it is stated by the Petitioner that, till date, the Respondents have not challenged the Development Agreement and/or the Supplemental Development Agreement in appropriate proceedings seeking a declaration that these agreements are void or not binding upon them. Raising objections before different authorities or Courts is one matter. Establishing that the Development Agreement executed between Respondent No.1 and the Petitioner is no longer binding is another matter. On the material produced before me, the latter has not been established.
In this regard, the judgment in Pranav Constructions Limited v. Priyadarshini Cooperative Housing Society Limited, Arbitration Appeal (L) No.20093 of 2025, decided on 14 July 2025, is relevant. The Division Bench considered whether disputes raised by individual members against the Society can prevent the Court from granting interim measures under Section 9. In paragraph 17, the Division Bench held:
“In our view, the alleged grievances of Respondents 2 to 4 in respect of various decisions taken by the General Body and Managing Committee of the Society in implementing the redevelopment process cannot be decided in petition filed under Section 9 of the Act nor existence of such disputes would be a bar for Section 9 Court to make interim measures in a given case.”
The Division Bench further held that the members of the Society are bound by the Development Agreement and observed:
“The members of the Society are bound by the covenants of the Development agreement and if they act contrary to the covenants of the Development agreement, the Court exercising power under Section 9 of the Act can step in and make necessary interim measures.”
This observation is relevant to the present case. Respondent Nos.2 to 11 are members occupying premises in the building which is proposed to be redeveloped. The Petitioner is not asking this Court to finally decide all their individual disputes with the Society. The grievance of the Petitioner is that the redevelopment has reached the stage of IOD, but the concerned occupants have not vacated their premises and have not executed the PAAA. According to the Petitioner, because of this, the redevelopment work is not able to proceed further. The Division Bench has made it clear that a grievance regarding appointment of the Developer, implementation of redevelopment or allotment of additional area has to be taken before the proper forum. If the grievance concerns the business of the Society, it can be raised under Section 91 of the M.C.S. Act. If it does not concern the business of the Society, the remedy is by filing a Civil Suit. The mere existence of such disputes does not, by, prevent the Section 9 Court from granting interim measures.
This principle substantially answers the objections raised by Respondent Nos.2 to 11. Their complaints regarding the resolutions of the Society, the redevelopment process and the earlier proceedings may require consideration before the forum having jurisdiction over those matters. But the present proceedings under Section 9 cannot be converted into a complete trial of all such disputes., merely because such disputes are pending, interim protection cannot be refused to the Petitioner.
Mr. Kadiani has submitted that the Petitioner has allegedly spent Rs.8,10,20,327/- despite knowing about the objections raised by the Respondents and the directions of the Deputy Registrar. According to him, the Petitioner knowingly took this commercial risk and cannot now claim any equity merely because it has spent money. This submission is correct only to a limited extent. The amount spent by the Petitioner cannot create a legal right in its favour. Merely because money has been spent, every disputed claim of the Petitioner cannot be accepted. The Court has first to see whether the Petitioner has a legal right., I do not accept the submission that the expenditure alone creates equity sufficient to decide the present Petition. At the same time, the opposite submission of Respondent Nos.2 to 11 cannot be accepted. The expenditure is not being considered separately. The Petitioner relies upon the series of resolutions, execution of the MOAT, the Development Agreement dated 19 June 2024, the enhancement agreed in 2025, approval of the SDA and PAAA in the meeting dated 15 March 2026, issuance of the IOD on 8 June 2026 and the Vacation Notice dated 9 June 2026. These circumstances show that the redevelopment process has gone substantially ahead., the expenditure is one circumstance showing the stage reached by the project. It is not the only reason for granting relief.
Respondent Nos.2 to 11 have questioned the legal effect of the resolutions and their ratification. These questions cannot be finally decided in the present Petition unless it is shown that they destroy the contractual basis of the relief sought. At present, there is a registered Development Agreement and a Supplemental Development Agreement. There is no material before me showing that either of these documents has been cancelled, set aside or declared void by any competent Court., for the limited purpose of considering interim measures, the arrangement has to be treated as continuing.
The next submission is that possession cannot be taken because the disputes raised by Respondent Nos.2 to 11 are still pending. There are two separate questions involved. One is whether Respondent Nos.2 to 11 have grievances which they can pursue. The other is whether, because of those grievances, they can continue to remain in possession and keep the redevelopment stopped for an indefinite period. The existence of the first does not give them the second right. This position finds support from paragraph 21 of the judgment in case of pranav contructions. The Division Bench considered a dispute regarding membership arising from a gift and held that such dispute was not a reason to delay vacation of the premises. The Court observed:
“Vacation of premises by original member and grant of possession of alternate accommodation to the succeeding member is not barred.”
In simple terms, a dispute which can be separately decided does not stop the physical steps required for redevelopment. The present case has to be considered on its own facts. Respondent Nos.2 to 11 are members or occupants of the concerned flats in the old building. They are not claiming that their flats are independent structures and should be kept outside the redevelopment. Their case is that the redevelopment process is disputed and they should not be required to cooperate until those disputes are decided. Merely because proceedings have been filed, this position cannot be accepted.
The Division Bench in Pranav Constructions considered Avenues Seasons Properties LLP and explained why that judgment did not apply to the facts before it. In Avenues Seasons Properties LLP, the concerned persons claimed that their bungalows were separate structures and should not form part of the Society's redevelopment. In the present case, Respondent Nos.2 to 11 are occupying flats in the very building which is proposed to be demolished and redeveloped. They have not taken the position that their flats are outside the redevelopment., the principle applicable to persons claiming exclusion from redevelopment cannot assist Respondent Nos.2 to 11 in resisting vacation of their premises.
The time factor is important in the present case. The Development Agreement provides for time-bound obligations concerning approvals, commencement of work and completion of construction. The IOD was issued on 8 June 2026. The Vacation Notice was issued on 9 June 2026 and 45 days were given for handing over possession, that is, up to 24 July 2026. The Petitioner submits that if even some flats remain occupied, demolition and site mobilisation cannot properly commence. This submission has practical substance. The old building is one common redevelopment site. The project cannot ordinarily proceed in the planned manner if some occupied flats remain in the building which is required to be demolished. The prejudice is not only to the Petitioner. According to the material before me, 41 members have cooperated and complied with the Vacation Notice. They are waiting for demolition of the old building and construction of the new building. If a few members are allowed to retain possession only because they have objections which can otherwise be decided in separate proceedings, the majority members who have agreed to the redevelopment will have to wait. Their rights and expectations cannot be kept pending indefinitely for this reason.
This finding does not mean that every objection raised by Respondent Nos.2 to 11 is false. Nor am I finally deciding all their rights. They remain free to take their grievances before the competent forum. But unless they obtain an order from a competent Court staying or restraining the redevelopment, or otherwise declaring the Development Agreement or the relevant resolutions invalid, they cannot, merely by retaining possession and refusing to execute the PAAA, bring the entire redevelopment project to a standstill.
Mr. Kadiani has submitted that the Court should not compel the members to accept an "unadjudicated and disputed redevelopment arrangement". If there was no valid Development Agreement, or if the Development Agreement had been set aside, or if a competent Court had restrained the redevelopment, the position would have been different. But no such circumstance is shown at present. The main grievance of the Respondents is against the validity of the decisions through which the redevelopment has proceeded. Such grievances have to be considered by the appropriate forum.
Paragraph 20 of Pranav Constructions deals with the submission that the decision of the General Body can be challenged if it is the result of fraud, misrepresentation or violation of statutory provisions. The Division Bench accepted that such a challenge can be made before the proper forum. But it clearly stated which forum is required to decide such dispute. It observed:
“If the resolution adopted by the General Body of the Society touches upon business of the Society, such resolution needs to be challenging by filing application under Section 91 of the M.C.S. Act. On the other hand, if such resolution does not touch upon business of the Society, the remedy for an affected party is to file a Civil suit. Under no circumstances such dispute can be remotely raised in proceedings filed under Section 9 of the Act.”
Therefore, Respondent Nos.2 to 11 cannot seek a final decision regarding the validity of the General Body resolutions indirectly in the present Section 9 proceedings when such dispute is required to be decided by the competent forum.
I have considered the submission regarding the undertaking given on 23 January 2024. Even if Respondent Nos.2 to 11 are correct in saying that the undertaking was wider and covered not only a fresh policy decision but any resolution in furtherance of redevelopment, the later events cannot be ignored. The Development Agreement was executed on 19 June 2024. Thereafter, the supplementary arrangements were approved. The SDA and PAAA were approved by the Society in the meeting dated 15 March 2026. The IOD was issued on 8 June 2026 and the Vacation Notice followed on 9 June 2026. The present Petition is based upon events which occurred after the undertaking of January 2024. The undertaking cannot, without proper adjudication, be treated as cancelling or wiping out all subsequent contractual steps.
There is no material before me showing that Respondent Nos.2 to 11 obtained an order from the Co-operative Court restraining Respondent No.1 from proceeding with the redevelopment after the Development Agreement was executed or after the later approvals were granted. Filing proceedings is relevant. But filing proceedings and obtaining an order stopping the redevelopment are two different things. The Petitioner has further stated that between 10 June 2026 and 6 July 2026, Respondent Nos.2 to 11 sought copies of the Development Agreement and Supplemental Development Agreement and raised further objections. According to the Petitioner, they were repeatedly asked to collect the documents and cooperate with the redevelopment. Even thereafter, no final consent to vacate has been given by Respondent Nos.2 to 11. The Vacation Notice remains uncomplied with.
The execution of the PAAA requires consideration. The format of the PAAA is stated to have been approved by Respondent No.1 in its Special General Meeting dated 15 March 2026. The Petitioner states that printed sets along with the annexures were forwarded to Respondent No.1. Respondent Nos.2 to 11 have not executed the PAAA and have continued to raise objections regarding the redevelopment. Once the Society has approved the PAAA format and the concerned members are entitled to alternate accommodation in the new building, refusal to execute the PAAA merely for postponing the redevelopment cannot, at this stage, be accepted as a sufficient reason to stop the project.
I find that Respondent Nos.2 to 11 may have disputes which can be raised before the appropriate forum. But the material before me does not show any order or legal bar which gives them a right to indefinitely retain possession and prevent the redevelopment. Their objections do not provide sufficient reason to refuse interim protection to the Petitioner.
The next question is whether physical possession should be taken through the Court Receiver if Respondent Nos.2 to 11 do not vacate voluntarily. The judgment in Pranav Constructions holds that where members act contrary to the terms of the Development Agreement, the Court exercising powers under Section 9 can grant necessary interim measures. The question is whether it should be exercised in the present facts. In the present case, the redevelopment has reached the stage where the IOD has been issued. The Vacation Notice has been served. The majority of members are stated to have vacated or agreed to vacate. The new accommodation and PAAA format have been approved. Respondent Nos.2 to 11 continue to remain in possession even after the period mentioned in the Vacation Notice. In these circumstances, merely giving another direction to vacate, without providing an effective consequence for non-compliance, may not sufficiently protect the Petitioner and the members who are cooperating. The prayer for appointment of the Court Receiver is connected with the main relief sought. It is not being granted as the first step. It is a consequential measure in case Respondent Nos.2 to 11 fail to comply with the direction to hand over possession. The Receiver would act only after the time granted by the Court expires. This gives Respondent Nos.2 to 11 a final opportunity to hand over possession voluntarily. While granting such relief, the lawful entitlements of Respondent Nos.2 to 11 have to be protected. The redevelopment documents provide for alternate accommodation and monetary benefits. The Petitioner has sought permission to deposit the amounts payable to the members if they do not accept the same. Such protection is proper because the members' monetary rights should not be affected merely because they have disputes regarding other aspects of the redevelopment.
The objection that the Court should not permit payment because the redevelopment is disputed cannot be accepted at this stage. The exact entitlement can be worked out according to the contractual documents. If Respondent Nos.2 to 11 refuse to accept the amounts, deposit in Court or in the manner directed by the Court will protect both sides. It will remove one possible reason for continuing to withhold possession.
So far as the prayer seeking injunction against Respondent No.1 and its members is concerned, the material shows that the Society has supported the redevelopment and has informed the Petitioner about the continued non-cooperation of Respondent Nos.2 to 11. It is not necessary to record any separate adverse finding against the Society. However, the Society and its members have to ensure that the redevelopment proceeds according to the Development Agreement and applicable law. Respondent Nos.2 to 11 cannot physically obstruct the work, prevent access, delay the work or create third-party rights if such acts directly interfere with the redevelopment.
As regards Respondent No.12, the Petitioner seeks a direction that no NOC or PAAA from Respondent Nos.2 to 11 or their legal representatives should be insisted upon for processing plans and granting further permissions. This concerns the requirements of the municipal and planning authority. A Court should be slow to direct a statutory authority to ignore any requirement prescribed by law. The material before me does not establish that Respondent No.12 is legally required to process every stage without insisting upon documents which may otherwise be required under law., the relief sought against Respondent No.12 cannot be granted in the broad form prayed for merely because relief is being granted against Respondent Nos.2 to 11.
The balance of convenience supports the Petitioner. The Petitioner has shown the contractual arrangement, repeated majority approval, substantial progress in redevelopment and issuance of the IOD. Respondent Nos.2 to 11 have shown that disputes and objections are pending. However, those disputes have not resulted in any order restraining the redevelopment. On the other hand, their occupation is preventing demolition and further work. The balance requires that the redevelopment should be allowed to proceed, while the Respondents' right to pursue their independent legal remedies is kept protected.
The question of irreparable prejudice supports the same course. Delay in redevelopment can affect the schedule and can affect the members who have agreed to vacate and are waiting for their new premises. Some financial loss may be compensated in money. But it cannot be assumed that every consequence of delaying a time-bound redevelopment project can always be properly compensated by damages. The effect upon the project and the cooperating members is a relevant consideration.
I am conscious that relief under Section 9 is discretionary. Such relief cannot be granted merely because there is a Development Agreement. The Court has to consider the rights claimed, the conduct of the parties, the urgency, the balance of convenience and whether interim protection is required. After considering the objections raised by Respondent Nos.2 to 11, I find that the facts of the present case justify granting protective interim measures. The reliance placed by the Respondents upon Wander Ltd. does not change this conclusion. The principle that an appellate Court normally does not interfere with discretionary orders has no direct application to the present exercise because this Court is considering the Petition under Section 9. In any event, the present conclusion is not based only on the expenditure claimed by the Petitioner. It is based upon the continuing contractual documents, repeated approval of the redevelopment, the stage reached by the project, issuance of the IOD and the continued failure to vacate despite the Vacation Notice.
It is necessary to make one position clear. This Court is not deciding in the present Petition that every resolution of Respondent No.1 is beyond challenge. It is not holding that every objection of Respondent Nos.2 to 11 is false. Nor is this Court deciding whether the Respondents will succeed or fail in their pending proceedings. Those questions are left to the competent forum. The finding in the present Petition is limited. The disputes raised by Respondent Nos.2 to 11 do not give them an unconditional right to remain in possession and keep the redevelopment stopped indefinitely.
On considering the entire material, I find that the Petitioner has made out a case for interim protection. Respondent Nos.2 to 11 are required to hand over vacant possession of their respective flats and execute and register the PAAA in the approved format. They are required to cooperate in the remaining redevelopment work. If they fail to do so within the time granted by this Court, consequential relief through the Court Receiver would be necessary to make the direction for handing over possession effective. At the same time, the relief sought against Respondent No.12 cannot be granted in the wide form prayed for without examining the particular statutory requirements applicable to the municipal permission process. The contractual and monetary entitlements of Respondent Nos.2 to 11 under the Development Agreement and Supplemental Development Agreement shall remain protected.
For the above reasons, I hold that the objections and pending proceedings relied upon by Respondent Nos.2 to 11 do not, at this stage, justify withholding the interim measures required for protection and implementation of the redevelopment project. The Petition is required to be allowed to the extent stated in the operative part of the order.
In view of the foregoing discussion and for the reasons recorded hereinabove, the following order is passed:
The Petition is allowed in terms of prayer clauses (a), (b), (d), (e) and (f), subject to the following directions:
Respondent Nos.2 to 11 shall hand over vacant, peaceful and unencumbered possession of their respective premises, namely Flat Nos. A-01, A-02, A-10, B-26, B-27, B-33 and B-42 in the old building of Respondent No.1 Society, together with all keys and access thereto, to the Petitioner within a period of 14 days from the date of uploading of the present order, for the purposes of demolition and redevelopment;
Respondent Nos.2 to 11 shall, within the aforesaid period of 14 days, execute and register the Permanent Alternate Accommodation Agreement in respect of their respective existing flats and the corresponding new premises to be allotted to them in the new building, in the format approved by Respondent No.1 Society at its Special General Meeting dated 15 March 2026;
Respondent Nos.2 to 11 shall cooperate with the Petitioner in execution and registration of the PAAA and in completion of all further steps required for redevelopment in respect of their respective premises;
Respondent No.1 Society and its members, including Respondent Nos.2 to 11, are restrained by an order and injunction from obstructing, interfering with or delaying the redevelopment of the property in any manner. They shall not create any third-party rights or any other hurdles in relation to lawful act being carried out by the Petitioner in furtherance of the redevelopment;
In the event Respondent Nos.2 to 11 fail to hand over vacant possession as directed in clause (ii) above within the stipulated period, the Court Receiver, High Court, Bombay, is appointed as Receiver of Flat Nos. A-01, A-02, A-10, B-26, B-27, B-33 and B-42;
Upon such failure, the Court Receiver shall be entitled to take physical possession of the aforesaid flats and hand over possession thereof to the Petitioner for the purposes of demolition and redevelopment. For implementing this direction, the Court Receiver shall be entitled, if necessary, to break open the locks, remove the occupants, agents, servants, belongings, and articles from the premises and seek police assistance;
The Court Receiver shall take reasonable care of the belongings and articles, if any, found in the premises and shall deal with the same in accordance with further directions of the Court;
In the event Respondent Nos.2 to 11 fail or refuse to execute and register the PAAA despite the direction contained herein, the Court Receiver, or such officer as may be nominated by this Court, shall be entitled to sign, execute and present for registration the PAAA and such other allied or incidental documents as may be necessary for giving effect to the present order, subject to the applicable law and registration requirements;
In the event Respondent Nos.2 to 11 fail or refuse to accept the amounts payable to them under the Development Agreement and/or Supplemental Development Agreement, including hardship allowance, monthly displacement allowance, brokerage allowance and shifting charges, the Petitioner shall be entitled, without prejudice to its rights and contentions, to deposit such amounts in this Court and/or with the Prothonotary and Senior Master, High Court, Bombay, in accordance with the terms of the said agreements and subject to verification of the amounts payable;
As regards prayer clause (g), Respondent No.12 shall process the plans and consider the further permissions for redevelopment in accordance with law. However, Respondent No.12 shall not insist upon the personal NOC/PAAA of Respondent Nos.2 to 11 as a condition contrary to the present order, provided that all other statutory and regulatory requirements applicable to the redevelopment are duly complied with;
It is clarified that the present order is confined to the interim measures granted under Section 9 of the Arbitration and Conciliation Act, 1996. The rights and contentions of the parties in respect of the disputes which are required to be decided by the competent forum are kept open. Nothing contained in this order shall be treated as a final adjudication of such disputes;
The Court Receiver shall act on an authenticated copy of this order;
The Petitioner shall communicate this order to Respondent Nos.2 to 11 and to the Court Receiver forthwith;
The Petition is accordingly disposed of in the above terms;
There shall be no order as to costs.