Tribunals and CommissionsDivision Bench(2023) 08 NCLAT CK 0024

Tata Power Western Odisha Distribution Limited (TPWODL) vs Jagannath Sponge Prviate Limited

National Company Law Appellate Tribunal · Decided on 8 August 2023

HON’BLE JUDGES
Ashok Bhushan, Chairperson · Barun Mitra, Member (T)
RESULT
Dismissed
CASE NUMBER
Company Appeal (AT) (Insolvency) No. 777 Of 2023

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

24 paragraphs · 1,083 words

Ashok Bhushan, J

1.

This Appeal has been filed against the Order dated 18th April, 2023 passed by National Company Law Tribunal, Cuttack Bench, Cuttack (hereinafter referred to as “The Adjudicating Authority”) in IA(IB) No. 14/CB/2023 arising out of CP(IB) No. 1174/KB/2018.

2.

Brief facts of the case necessary to be noticed for deciding this Appeal are:-

i. On an application filed under Section 7 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as “The Code”) against the Jagannath Sponge Private Limited, Corporate Insolvency Resolution Process (CIRP in short) was initiated vide Order dated 20th April, 2019 of the Adjudicating Authority.

ii. The  Resolution  Plan  was  submitted  in  the  CIRP  of  the Corporate Debtor by one M/s Omkara Asset Reconstruction Company which plan was approved by the Adjudicating Authority vide Order dated 06th August, 2021. The Appellant vide Letter dated 19th July, 2022 was informed that Resolution Plan has been approved by the Adjudicating Authority. The Appellant filed C.A.(AT) Insolvency No. 1404 of 2022 challenging the Order dated 06th August, 2021 which Appeal was withdrawn by the Appellant on 25th November, 2022.

iii. The  Respondent  vide  Letter  dated  05th   August,  2022 requested the Appellant to supply electricity with CD 550KVA to its units. The Appellant informed the Respondent of outstanding arrears of Electricity dues amounting to Rs. 13,46,19,931/-. The Respondent filed an Application before the Adjudicating Authority I.A.(IB) 14/2023 seeking direction to Appellant to provide electricity connection to the two units and set aside the demand of arrears of electricity dues. The Adjudicating Authority heard the parties and framed following two points for consideration:

“1. Whether letter dated 08.12.2022 of 2nd respondent demanding Rs. 13,46,19,931/- against the applicant is valid?

2.

Whether  the  applicant  is  entitled  for  service connection?”

iv. The  Adjudicating  Authority  took  the  view  that  Resolution Plan having been approved which is binding, the claim of Appellant against the Successful Resolution Applicant of arrears is not valid. The Adjudicating Authority noted that the Appellant did not file any claim in the Insolvency Resolution Process of the Corporate Debtor. Adjudicating Authority by the Impugned Order issued following directions:

“1. It is hereby declared that the amount of Rs. 13,46,19,931/- claimed by the respondents in their impugned letter dated 08.12.2022 addressed to applicant is not valid and not enforceable as against the corporate debtor/successful resolution applicant.

2.

The 2nd Respondents is directed to consider the service connection application of the applicant submitted by the successful resolution applicant or any other person on its behalf, in accordance with the code/regulation without insisting to make any payment/arrears in whatever nature payable by the corporate debtor prior to 06.08.2021.”

v. Aggrieved by the said order, the Appellant has come up in the Appeal.

3.

Learned Counsel for the Appellant in support of Appeal contends that electricity dues of the Appellant required to be paid before Electricity Connection can be given to the Respondent. It is submitted that electricity was disconnected of the Corporate Debtor in the year 2013 and the two related power supply agreements were terminated with effect from 03.10.2013 and with effect from 01.02.2015. The total arrears of electricity against the Corporate Debtor were Rs. 13,56,19,931/- which is required to be paid. It is submitted that there being no proper publication by the Resolution Professional, Appellant could not file its claim in the CIRP Process.

4.

Learned Counsel for the Respondent refuting the submission of the Appellant contends that Appellant having not filed its claim, its pre-CIRP dues has been extinguished and in the Resolution Plan the Adjudicating Authority has already issued direction that electricity distribution company shall not raise any demand for reference to the past dues.

5.

We have considered the submissions of Learned Counsel for the parties and have perused the record.

6.

The Adjudicating Authority in several paragraphs while dealing with point no. 1 and 2 has extracted the part of the Resolution Plan under the waivers, reliefs and exemptions, Sl. No., which refers as follows:

Sl No.

Waivers, Reliefs and Exemptions sought from NCLT

Orders thereon

The Hon’ble NCLT be pleased to give or issue necessary directions, instructions to the relevant electricity board to give the exemption to the Corporate Debtor from making payment towards reconnection charges of power.

The electricity distribution companies shall not raise any demand with reference to the past dues. They shall, however, treat the application that shall be filed by the corporate debtor, as a new connection and collect charges as applicable for a new connection, without any coercion or precondition to pay the past dues.

7.

There is no dispute to the fact that Appellant did not file any claim of its Pre-CIRP dues of Rs. 13,46,19,931/-. The Adjudicating Authority has rightly relied on Judgment of “Ghanashyam Mishra and Sons Pvt. Ltd. through the Authorized Signatory vs. Edelweiss Asset Reconstruction  Company  Limited  through  the  Director  &  Ors.”, (2021 SCC OnLine SC 313). Paragraph 102.3 of the Supreme Court Judgment is as follows:

“102.3 Consequently all the dues including the statutory dues owed to the Central Government, any State Government or any local authority, if not part of the resolution plan, shall stand extinguished and no proceedings in respect of such dues for the period prior to the date on which the Adjudicating Authority grants its approval under Section 31 could be continued.”

8.

The  submission  of  the  Appellant  that  there  was  no  proper publication of the announcement made by the Resolution Professional has been dealt by the Adjudicating Authority in paragraph 8 of the Order. The Adjudicating Authority has noted the provisions of Regulation and has returned a finding that on the above submission of the Appellant plan approval cannot be held to be vitiated. It is also to be noted that against the plan approval order, Appellant filed an Appeal which was withdrawn by the Appellant themselves. No contention by the Appellant challenging the plan approval can be considered. The Adjudicating Authority while approving the Plan having already issued directions that Electricity Distribution Companies shall not raise any demand with reference to the past dues, we see no error in the direction issued by the Adjudicating Authority by the Impugned Order directing the Appellant to consider the service connection application of the Applicant in accordance with the Code/Regulation without insisting on making any payment of arrears prior to date of plan approval. No grounds have been made out to interfere with the Impugned Order passed by the Adjudicating Authority. There is no merit in the Appeal, the Appeal is dismissed.